CN203239685U CN 201320007489 CN201320007489U CN203239685U CN 203239685 U CN203239685 U CN 203239685U CN 201320007489 CN201320007489 CN 201320007489 CN 201320007489 U CN201320007489 U CN 201320007489U CN 203239685 U CN203239685 U CN 203239685U
Authority
CN
China
Prior art keywords
fuel tank
pumping plant
body board
main body
plant fuel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201320007489
Other languages
Chinese (zh)
Inventor
刘相尚
李哲
万介荣
唐国华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Leadwell Technology Co Ltd
Original Assignee
Shenzhen Leadwell Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Leadwell Technology Co Ltd filed Critical Shenzhen Leadwell Technology Co Ltd
Priority to CN 201320007489 priority Critical patent/CN203239685U/en
Application granted granted Critical
Publication of CN203239685U publication Critical patent/CN203239685U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Details Of Rigid Or Semi-Rigid Containers (AREA)

Abstract

The utility model discloses a pump station fuel tank integrated structure which comprises a pump station fuel tank, a main body cabinet and an auxiliary cabinet. The pump station fuel tank is inserted into the middle of the main body cabinet as a drawer and connected with the main body cabinet through bolts. The connecting faces do not need to be processed. The pump station fuel tank is communicated with the auxiliary cabinet through a hose communicating mechanism. The main body cabinet and the auxiliary cabinet are fixed through bolts and pins, and the fixing faces need to be processed. The pump station fuel tank integrated structure has the advantages that all parts can be manufactured, installed and debugged independently and synchronously in an assembly mode, the production efficiency is improved, all the parts are compact in structure, disassembling, assembling, transporting and maintaining are convenient, the material use ratio is high, the operation space is large, welding is easy, the layout is attractive, daily maintenance is convenient, the cost is low, the time of installing and debugging equipment is short, and the service life is long.

Description

Pumping plant fuel tank integrative-structure
Technical field
The utility model relates to a kind of pumping plant fuel tank integrative-structure, refers in particular to a kind of drawer type independence pumping plant Oiltank structure.
Background technique
The forming equipment such as die casting machine, injection machine is widely used in industry and the fields such as automobile making, communications and transportation, metallurgy, 3C, national defence, Aeronautics and Astronautics; the pumping plant fuel tank is converted into mechanical energy the fluid pressure energy in the forming equipments such as die casting machine, injection machine; for whole equipment provides power source, realize the control and protection of system.
There is following defective in the pumping plant fuel tank that is used for the forming equipments such as die casting machine, injection machine in the prior art:
The first, when pumping plant fuel tank and main body board were designed to integrative-structure, structure was heavy, the size overlength, the transportation difficulty, dismounting is inconvenient, plate needs the multi-sheets splicing, and material can not rationally utilize, and it is inner that fuel tank is embedded in the main body board, the operating space is narrow and small, welding difficulty, oiling, oil extraction and regular maintenance are extremely inconvenient, and liquid, gas, fulgurite (line) road are many and in disorder, layout is not attractive in appearance, and potential safety hazard is large;
Second, when pumping plant independence, when fuel tank and main body board are designed to integrative-structure, fuel tank mainly also is to be embedded in main body board inside, the operating space is narrow and small, the welding difficulty, oiling, oil extraction and regular maintenance are extremely inconvenient, and pumping plant is independent, can make, install with kit form separately, but can not debug separately, and guarantee that with the difficulty that cooperates of fuel tank attachment portion liquid, gas, fulgurite (line) are passed by many and long, friction and interference occur often, lengthen the installment and debugging time of equipment, shortened the working life of equipment, increased the maintenance cost of equipment;
The 3rd, when fuel tank independence, when pumping plant and main body board are designed to integrative-structure, pumping plant mainly is to be attached to main body board end or side, size overlength, transportation difficulty, plate exists needs the multi-sheets splicing, material can not rationally utilize, and the operating space is narrow and small, the welding difficulty, regular maintenance is inconvenient, fuel tank is independent, can make with kit form separately, install, but can not debug separately, and with difficult assurance of cooperating of pumping plant attachment portion, liquid, gas, the friction of fulgurite (line) road and interference also occur often, have shortened the working life of equipment, have increased the maintenance cost of equipment;
The model utility content
The technical problems to be solved in the utility model is, for structure heaviness in the prior art, size overlength, make and the transportation difficulty, dismounting and maintenance are inconvenient, and layout is in disorder, not attractive in appearance, can not be separately with defectives such as kit form making, installment and debuggings, a kind of novel structure is provided, transportation, making, dismounting, easy to maintenance, layout is attractive in appearance, can be separately with kit form making, installment and debugging, long service life, a kind of pumping plant fuel tank integrative-structure that maintenance cost is low.
The technological scheme that its technical problem that solves the utility model adopts is: construct a kind of drawer type independence pumping plant fuel tank integrative-structure, comprise pumping plant fuel tank, main body board, attached body board, in described pumping plant fuel tank, be provided with Oiltank structure, supporting structure, power system and control system, described pumping plant fuel tank equally inserts main body board middle part like drawer, and described pumping plant fuel tank is communicated with by soft larynx means of communication with attached body board.
In the utility model pumping plant fuel tank integrative-structure, described pumping plant fuel tank is formed by Oiltank structure and pump station structure integral production.
In the utility model pumping plant fuel tank integrative-structure, described pumping plant fuel tank can be separately with kit form making, installment and debugging.
In the utility model pumping plant fuel tank integrative-structure, described pumping plant fuel tank equally inserts main body board middle part like drawer, be bolted with the main body board, and junction surface all need not processing.
In the utility model pumping plant fuel tank integrative-structure, described pumping plant fuel tank is communicated with by soft larynx means of communication with attached body board.
In the utility model pumping plant fuel tank integrative-structure, described main body board and attached body board are fixed by bolt and pin, and stationary plane all needs processing.
The utlity model has following beneficial effect: pumping plant fuel tank integrative-structure comprises the pumping plant fuel tank, the main body board, attached body board, each several part is made separately, installment and debugging, can carry out synchronously, improved manufacturing efficiency, the pumping plant fuel tank equally inserts main body board middle part like drawer, and is bolted with the main body board, compact structure, dismounting, transportation, easy to maintenance, stock utilization is high, and the operating space is large, welding easily, regular maintenance is convenient, and layout is attractive in appearance, is beneficial to liquid, gas, the smooth vertical and horizontal layout in fulgurite (line) road and pipe clamp are fixed, service life of equipment is long, and maintenance cost is low.
Description of drawings
The utility model is described in further detail below in conjunction with drawings and Examples, in the accompanying drawing:
Fig. 1 is pumping plant Oiltank structure plan view in the utility model pumping plant fuel tank integrative-structure;
Fig. 2 is pumping plant Oiltank structure plan view in the utility model pumping plant fuel tank integrative-structure;
Fig. 3 is the utility model pumping plant fuel tank integrative-structure each several part structural front view;
Fig. 4 is the utility model pumping plant fuel tank integrative-structure each several part structure plan view;
Fig. 5 is the utility model pumping plant fuel tank integrative-structure each several part assembling schematic representation;
Fig. 6 is the utility model pumping plant fuel tank integrative-structure each several part dismounting schematic representation;
Embodiment
In order to make the purpose of this utility model, technological scheme and advantage clearer, below in conjunction with drawings and Examples, the utility model is further elaborated.Should be appreciated that specific embodiment described herein only in order to explaining the utility model, and be not used in restriction the utility model.
As shown in Figure 1, 2, pumping plant fuel tank main structure supporting base 1, electric-motor pump group 2, protective housing 4, fuel tank 6 in the utility model pumping plant fuel tank integrative-structure, be provided with control valve group 5 at fuel tank 6 tops, be provided with connecting base 3 in supporting base 1 end, be provided with connection seat 7 in fuel tank 6 ends.When making the pumping plant fuel tank, the good supporting base 1 of assembly welding at first, follow the good fuel tank 6 of assembly welding, then supporting base 1 and fuel tank 6 assembly weldings are integral or by bolt and rivet both are linked into an integrated entity, then supporting base 1 and fuel tank 6 are formed body process polishing, pickling, sanding, spray paint, the operations such as detection complete, but interlock system performs protective housing 4 in said process, again supporting base 1, electric-motor pump group 2, protective housing 4, control valve group 5, fuel tank 6, connecting base 3 and connection seat 7 are assembled into pumping plant fuel tank 10 at last, making and the installation process of pumping plant fuel tank 10 are finished at this point.
Then, pumping plant fuel tank 10 is tried out and related commissioning work by actuator and control detection system by the outside.
After related work was finished, pumping plant fuel tank 10 can independently be deposited, transport, and at any time wait is docked with main body actuator, installment and debugging.
Such as Fig. 3,4,5, shown in 6, after main body board 12 and attached body board 13 complete by related request, fix by bolt and locating stud, and stationary plane 9 all needs processing, then will debug good pumping plant fuel tank 10 and equally insert main body board 12 middle parts like drawer, be connected with main body board 12 by bolt, and junction surface 8 all need not processing, and be communicated with attached body board 13 by soft larynx means of communication 11, so far, pumping plant fuel tank 10, main body board 12 and attached body board 13 all dock, installation, after connecting at last relevant actuator and controlling detection system, complete machine can move.
Shown in Fig. 3,4,5,6, when the forming equipments such as die casting machine, injection machine need to be dismantled, first with relevant actuator and the dismounting of control detection system, the personnel of following enter main body board 12 middle parts soft larynx means of communication 11 are unclamped, then with junction surface 8 place's Bolt dismantlings, pumping plant fuel tank 10 is namely separable with main body board 12 and attached body board 13 assemblying bodys, then with stationary plane 9 place's bolts and pin dismounting, main body board 12 is namely separable with attached body board 13, after each several part separates, it is extremely convenient to dismantle, transport, keep in repair, and the manpower and materials cost is low.
Such as Fig. 3,4,5, shown in 6, work as die casting machine, after the forming equipments such as injection machine use certain hour, fuel tank need to be cleared up iron filings, precipitation waits foreign material and more renews hydraulic oil, pumping plant needs periodical repair, the utility model only needs first former hydraulic oil to be extracted out, the personnel of following enter main body board 12 middle parts soft larynx means of communication 11 are unclamped, then with junction surface 8 place's Bolt dismantlings, pumping plant fuel tank 10 is namely separable, the fuel tank cleaning, hydraulic oil is changed and the pumping plant maintenance can be carried out, other parts need not dismounting, the fuel tank cleaning, after hydraulic oil replacing and pumping plant maintenance are finished, pumping plant fuel tank 10 equally inserts main body board 12 middle parts like drawer, is connected with main body board 12 by junction surface 8, and is communicated with attached body board 13 by soft larynx means of communication 11, so far, pumping plant fuel tank 10, main body board 12 and attached body board 13 all dock, installation, after connecting at last relevant actuator and controlling detection system, complete machine can move.
Should be understood that, for those of ordinary skills, can be improved according to the above description or conversion, and all these improvement and conversion all should belong to the protection domain of the utility model claims.

Claims (6)

1. pumping plant fuel tank integrative-structure, comprise pumping plant fuel tank (10), main body board (12) and attached body board (13), described pumping plant fuel tank (10) comprises supporting base (1), electric-motor pump group (2), protective housing (4), fuel tank (6), be provided with control valve group (5) at fuel tank (6) top, be provided with connecting base (3) in supporting base (1) end, be provided with connection seat (7) in fuel tank (6) end, pumping plant fuel tank (10) equally inserts main body board (12) middle part like drawer, be connected with main body board (12) by junction surface (8), and be communicated with attached body board (13) by soft larynx means of communication (11), main body board (12) is fixing by stationary plane (9) with attached body board (13).
2. pumping plant fuel tank integrative-structure according to claim 1 is characterized in that, described pumping plant fuel tank (10) is formed by Oiltank structure and pump station structure integral production.
3. pumping plant fuel tank integrative-structure according to claim 1 is characterized in that, described pumping plant fuel tank (10) can be separately with kit form making, installment and debugging.
4. pumping plant fuel tank integrative-structure according to claim 1, it is characterized in that, described pumping plant fuel tank (10) equally inserts main body board (12) middle part like drawer, be bolted with main body board (12), and junction surface (8) all need not processing.
5. pumping plant fuel tank integrative-structure according to claim 1 is characterized in that, described main body board (12) is fixed by bolt and pin with attached body board (13), and stationary plane (9) all needs processing.
6. pumping plant fuel tank integrative-structure according to claim 1 is characterized in that, described pumping plant fuel tank (10), main body board (12) and attached body board (13) all can be separately with kit form making, installment and debuggings.
CN 201320007489 2013-01-04 2013-01-04 Pump station fuel tank integrated structure Expired - Lifetime CN203239685U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320007489 CN203239685U (en) 2013-01-04 2013-01-04 Pump station fuel tank integrated structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320007489 CN203239685U (en) 2013-01-04 2013-01-04 Pump station fuel tank integrated structure

Publications (1)

Publication Number Publication Date
CN203239685U true CN203239685U (en) 2013-10-16

Family

ID=49316991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320007489 Expired - Lifetime CN203239685U (en) 2013-01-04 2013-01-04 Pump station fuel tank integrated structure

Country Status (1)

Country Link
CN (1) CN203239685U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104528588A (en) * 2014-12-26 2015-04-22 苏州威尔特铝合金升降机械有限公司 Shears-fork type lift convenient to move and maintain

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104528588A (en) * 2014-12-26 2015-04-22 苏州威尔特铝合金升降机械有限公司 Shears-fork type lift convenient to move and maintain

Similar Documents

Publication Publication Date Title
CN103542067A (en) Novel combined type gear
CN203239685U (en) Pump station fuel tank integrated structure
CN104162566A (en) Hydraulic pipe bending device
CN220679940U (en) Horizontal press for disassembling and assembling interference fit parts
CN102430910B (en) Assembly tooling for side frame chute wearing plate
CN203712168U (en) Tool for welding tundish car and motor positioning lug
CN203678963U (en) Hydraulic pipe bending device
CN103100848B (en) Cooler for recycled exhaust gas assembling machine for core
CN105179225A (en) Water outlet cavity structure of high-pressure pump
CN204457639U (en) Oil well hydraulic operation vehicle
CN205043411U (en) Pneumatic upset workstation
CN205487839U (en) Load switch mechanical properties break -in frock
CN103939313A (en) Manual two-stage rapid oil delivery pump
CN204725267U (en) Flange trimming equipment
CN102849605A (en) Excavator sucker
CN202580467U (en) Pipe breakage rapid repair auxiliary device
CN202240281U (en) Butt-welding assembly for container component with assembling demand on upper and lower flanges
CN202370949U (en) Hydraulic station of side frame chute wearing plate assembling tooling
CN104499996B (en) Oil well hydraulic operation vehicle
CN204487097U (en) Filtering oil for transformer pump tool specially for attaching and detaching
CN204724732U (en) The pipeline assembling device of pipeline assembling pipe-expanding machine
CN204320850U (en) Pneumatic fluid pressure type tramcar shaper
CN202462332U (en) Disassembly and assembly device for auxiliary inverter of subway train
CN103644351A (en) Novel feed valve and using method thereof
CN103659213B (en) Fill with pearl oiling machine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20131016

CX01 Expiry of patent term