CN203213295U - Check valve for jacking and pouring of concrete - Google Patents

Check valve for jacking and pouring of concrete Download PDF

Info

Publication number
CN203213295U
CN203213295U CN 201320178432 CN201320178432U CN203213295U CN 203213295 U CN203213295 U CN 203213295U CN 201320178432 CN201320178432 CN 201320178432 CN 201320178432 U CN201320178432 U CN 201320178432U CN 203213295 U CN203213295 U CN 203213295U
Authority
CN
China
Prior art keywords
flange
concrete
check valve
flashboard
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320178432
Other languages
Chinese (zh)
Inventor
郭颖
杨太洲
陆海英
赵国录
陈默
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Third Construction Engineering Co Ltd of China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Third Construction Engineering Co Ltd of China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, Third Construction Engineering Co Ltd of China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN 201320178432 priority Critical patent/CN203213295U/en
Application granted granted Critical
Publication of CN203213295U publication Critical patent/CN203213295U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a check valve for jacking and pouring of concrete. The check valve for jacking and pouring of the concrete comprises a front joint and a rear joint, wherein the front joint and the rear joint are respectively connected with a pump pipe. A front flange is arranged at the rear end of the front joint. A rear flange is arranged at the front end of the rear joint. A moving flashboard is arranged between the front flange and the rear flange. An upper limiting plate which is vertical to the moving flashboard is arranged at the upper end of the moving flashboard. A lower limiting plate which is vertical to the moving flashboard is arranged at the lower end of the moving flashboard. A through hole is formed in the lower portion of the moving flashboard. Baffles are arranged on the two sides of the moving flashboard. The baffles, the front flange and the rear flange are connected through bolts. When the check valve for jacking and pouring of the concrete is used, the check valve is in a sealed state towards the outside, gas does not leak and construction is convenient to perform with safety and reliability. The joints are adopted to be connected with the concrete conveying pump pipe so that the check valve is convenient to use. The check valve can be used repeatedly in a circulation mode and is low in cost.

Description

Be used for the flow-stop valve that concrete lift-up is built
Technical field
The utility model relates to a kind of flow-stop valve, particularly a kind of flow-stop valve of building for concrete lift-up.
Background technology
At present, the construction technology of steel pipe column inner concrete jacking is: open one than the hole of the bigger 3mm of carrier pipe at the bottom of steel pipe column tube wall, be attached thereto with the outlet of high-pressure delivery pump line with concrete pump, concrete is injected in the steel pipe column by carrier pipe continuously by pump pressure, fills with concrete in pipe.The steel pipe column top arranges the overflow steam vent, to reduce pumping pressure.On the pump line of steel pipe column bottom, adopt the method that flow-stop valve is set, prevent that concrete from flowing backwards.At present, adopt more flow-stop valve to adopt the board plug type structure, plug in flashboard is wedge shape, and adopts finger setting.Under the effect of pumping of concrete, the pump line vibrations, and the vibrations of pump line can directly cause the loosening of wedge shape flashboard, thus making flow-stop valve gas leakage, safety and reliability are lower.
The utility model content
The utility model for solve the technical problem that exists in the known technology provide a kind of safety and reliability higher be used for the flow-stop valve that concrete lift-up is built.
The utility model for the technical scheme that solves the technical problem that exists in the known technology and take is: a kind of flow-stop valve of building for concrete lift-up, comprise the front connector and the back joint that are connected with pump line respectively, the rear end of described front connector is provided with forward flange, the front end of described back joint is provided with rear flange, between described forward flange and described rear flange, be provided with movable flashboard, the upper end of described movable flashboard is provided with perpendicular upper limit plate, the lower end of described movable flashboard is provided with perpendicular lower limiting board, the bottom of described movable flashboard is provided with via, both sides at described movable flashboard are equipped with baffle plate, described baffle plate, described forward flange is connected by bolt with described rear flange.
Rear end face at described forward flange is equipped with the front sealing packing ring, at the front end face of described rear flange the rear seal packing ring is installed.
Described via is diminishing horn-like along the concrete throughput direction.
Advantage and the good effect that the utlity model has are: when 1) using, externally be closed state, and air tight, easy construction, safe and reliable; 2) adopt joint to be connected with concrete delivery pump pipe, easy to use.3) can repetitive cycling use, cost is lower.
Description of drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the 1-1 sectional drawing of Fig. 1.
Among the figure: 1, pump line; 2, front connector; 3, forward flange; 4, movable flashboard; 4-1, lower limiting board; 4-2, via; 4-3, upper limit plate; 5, rear flange; 6, bolt; 7, back joint, 8, baffle plate.
The specific embodiment
For further understanding summary of the invention of the present utility model, characteristics and effect, exemplify following examples now, and conjunction with figs. is described in detail as follows:
See also Fig. 1 and Fig. 2, a kind of flow-stop valve of building for concrete lift-up, comprise the front connector 2 and the back joint 7 that are connected with pump line 1 respectively, the rear end of described front connector 2 is provided with forward flange 3, the front end of described back joint 7 is provided with rear flange 5, between described forward flange 3 and described rear flange 5, be provided with movable flashboard 4, the upper end of described movable flashboard 4 is provided with perpendicular upper limit plate 4-3, the lower end of described movable flashboard 4 is provided with perpendicular lower limiting board 4-1, the bottom of described movable flashboard 4 is provided with via 4-2, be equipped with baffle plate 8 in the both sides of described movable flashboard 4, described baffle plate 8, described forward flange 3 is connected by bolt 6 with described rear flange 5.During use, in the flashboard seam of described forward flange 3 and described rear flange 5 and 4 formation of described movable flashboard, fill butter, to prevent flashboard seam gas leakage in the process that the concrete pumping jacking is built.Also can solve the problem of flashboard seam gas leakage from structure: the rear end face at described forward flange 3 is installed the front sealing packing ring, at the front end face of described rear flange 5 the rear seal packing ring is installed.No matter be in the flashboard seam, to fill butter or at the end face of flange seal washer is installed, all be for when flow-stop valve uses, externally be closed state.Described via 4-2 is diminishing horn-like along the concrete throughput direction.To reduce concrete transporting resistance.
Although by reference to the accompanying drawings preferred embodiment of the present utility model is described above; but the utility model is not limited to the above-mentioned specific embodiment; the above-mentioned specific embodiment only is schematic; be not restrictive; those of ordinary skill in the art is under enlightenment of the present utility model; not breaking away under the scope situation that the utility model aim and claim protect, can also make a lot of forms, these all belong within the protection domain of the present utility model.

Claims (3)

1. one kind is used for the flow-stop valve that concrete lift-up is built, it is characterized in that, comprise the front connector and the back joint that are connected with pump line respectively, the rear end of described front connector is provided with forward flange, the front end of described back joint is provided with rear flange, between described forward flange and described rear flange, be provided with movable flashboard, the upper end of described movable flashboard is provided with perpendicular upper limit plate, the lower end of described movable flashboard is provided with perpendicular lower limiting board, the bottom of described movable flashboard is provided with via, both sides at described movable flashboard are equipped with baffle plate, described baffle plate, described forward flange is connected by bolt with described rear flange.
2. flow-stop valve of building for concrete lift-up according to claim 1 is characterized in that, at the rear end face of described forward flange the front sealing packing ring is installed, and at the front end face of described rear flange the rear seal packing ring is installed.
3. flow-stop valve of building for concrete lift-up according to claim 1 is characterized in that described via is diminishing horn-like along the concrete throughput direction.
CN 201320178432 2013-04-10 2013-04-10 Check valve for jacking and pouring of concrete Expired - Fee Related CN203213295U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320178432 CN203213295U (en) 2013-04-10 2013-04-10 Check valve for jacking and pouring of concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320178432 CN203213295U (en) 2013-04-10 2013-04-10 Check valve for jacking and pouring of concrete

Publications (1)

Publication Number Publication Date
CN203213295U true CN203213295U (en) 2013-09-25

Family

ID=49202844

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320178432 Expired - Fee Related CN203213295U (en) 2013-04-10 2013-04-10 Check valve for jacking and pouring of concrete

Country Status (1)

Country Link
CN (1) CN203213295U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610331A (en) * 2018-12-18 2019-04-12 中国五冶集团有限公司 A kind of steel pipe of arch bridge inner concrete casting method and its device and application

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610331A (en) * 2018-12-18 2019-04-12 中国五冶集团有限公司 A kind of steel pipe of arch bridge inner concrete casting method and its device and application

Similar Documents

Publication Publication Date Title
CN203213295U (en) Check valve for jacking and pouring of concrete
CN204459454U (en) Constructing device is pushed up again after a kind of jacking construction stops
CN205956550U (en) Construction flexible slip casting pipe among steel cylinder concrete pipe for method is advanced on top
CN204694428U (en) A kind of axle system stern tube hydraulic sealing test device
CN203961899U (en) Upwards extend the hole sealing device of boring
CN207324172U (en) A kind of anti-vacuum structure of water-closing-barrel
CN205135482U (en) Gas drilling pressure release manifold device
CN202970758U (en) Hole packer used for crushing coal bed
CN104141286A (en) Construction adit blocking structure
CN207227335U (en) A kind of water circle device of coke oven coke oven uprising tube
CN203978865U (en) A kind of high suction depth Jet injector auxiliary float device
CN102951383A (en) Sealed oil nozzle used for oil bag
CN206844229U (en) A kind of blower pump for pipeline position is higher than the fire cistern of water level
CN208531310U (en) A kind of two-compartment oil tank
CN202614482U (en) Air-tightness detecting device of plunger-type cylinder
CN208040445U (en) A kind of underground mine use paste body filling bag
CN206681786U (en) A kind of high negative pressure methane gas extraction pipeline tailrace device
CN204855144U (en) A hydrostatic test system for valve body foundry goods
CN206054441U (en) The overload protection arrangement of oil cylinder
CN206636793U (en) Underground mine suction-type pump house water absorber
CN107083763A (en) A kind of sluice with hydraulic lock
CN217897955U (en) Increase and ooze device and take out and adopt system
CN203867516U (en) Grouting hole packer with air exhaust pipeline
CN201851817U (en) Hydraulic flange sealing device
CN203977439U (en) Prevent the filling system that Urban Underground water level declines

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130925

Termination date: 20200410