CN203147282U - Running system for long-distance pipeline coal slurry transportation of plurality of transportation pumps - Google Patents

Running system for long-distance pipeline coal slurry transportation of plurality of transportation pumps Download PDF

Info

Publication number
CN203147282U
CN203147282U CN 201320082857 CN201320082857U CN203147282U CN 203147282 U CN203147282 U CN 203147282U CN 201320082857 CN201320082857 CN 201320082857 CN 201320082857 U CN201320082857 U CN 201320082857U CN 203147282 U CN203147282 U CN 203147282U
Authority
CN
China
Prior art keywords
diaphragm pump
piston diaphragm
transportation
long
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320082857
Other languages
Chinese (zh)
Inventor
吴嘉林
张建民
刘睿
温占稳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Shenwei Coal Pipeline Transportation Co ltd
Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Original Assignee
Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Design and Research Institute of China Coal Technology and Engineering Group filed Critical Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Priority to CN 201320082857 priority Critical patent/CN203147282U/en
Application granted granted Critical
Publication of CN203147282U publication Critical patent/CN203147282U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

The utility model discloses a running system for the long-distance pipeline coal slurry transportation of a plurality of transportation pumps. A first flow meter is sequentially connected with one end of each of a first piston diaphragm pump, a second piston diaphragm pump, a third piston diaphragm pump, a fourth piston diaphragm pump, a fifth piston diaphragm pump and a sixth piston diaphragm pump in parallel through a pipeline and a three-way pipe respectively, and the other end of each of the first, second, third, fourth, fifth and sixth piston diaphragm pumps is connected in parallel with a second flow meter, wherein five pumps are started, and the other one pump is standby. The running system has the characteristics of simple structure, convenience for mounting, low logistics and operation cost, safety, high efficiency, energy saving, land saving, environment friendliness, economy, freeness from external interference, high pressure, great number, long distance and constant flow, and is widely used for the coal industry and other mineral industries, the transportation pressure of roads and railways is reduced, environment friendliness during transportation is ensured, and the influence of a ground transportation environment is eliminated.

Description

Many transfer pump long-distance pipes are carried the operational system of coal slurry
Technical field
The utility model relates to the system of the defeated coal of long-distance pipe, is specifically related to the operational system of many transfer pump long-distance pipes conveying coal slurries of a kind of high pressure, big quantity, long distance, firm discharge.
Background technique
In China's economy rapid growth, the particularly sustainable and stable development of industries such as metallurgy, petrochemical industry, oil, chemical fertilizer, coal in recent years, price lifting along with the energy, cost of transportation is more and more higher, and utilize the pipeline coal transporting technology, not only will thoroughly break " bottleneck " of long-term restriction energy enterprise Coal Transport and change the intrinsic general layout of Coal Transport mode, reduce BUSINESS LOGISTICS cost and operation cost greatly, and advanced technology, safe and efficiently, energy-conservation save land, environmental protection and economy, be not subjected to external interference, for coal outward transport new tunnel provides good demonstration and propelling.
Article one convey coal pipe of dropping into commercial operation built up in the Ohio in nineteen fifty-seven in the world, pipeline length overall 140km, and 1,400,000 tons of year fortune coal amounts are topic because the high infraction of operation cost and coal slurry pipeline etc. are technical, force in 1963 years and close; The Hei Maisha convey coal pipe of another convey coal pipe U.S. was constructed and put into operation in November, 1970, whole audience 440km, 5,000,000 tons of year fortune coal amounts, operation is to 2004, after stopped transport in 2005 for various reasons.
In long-distance pipe is carried, the method of operation of defeated many transfer pumps of coal of long-distance pipe is to adopt first in Chinese pipeline slurry body mode, the employing of this mode is for remote, big quantity slurry body provides a kind of strict system that controls pipeline slurry stream amount.
Summary of the invention
The purpose of this utility model provides a kind of simple in structure, easy for installation, logistics and operation cost are low, safe and efficiently, energy-conservation save land, environmental protection and economy, be not subjected to external interference, the operational system that many transfer pump long-distance pipes of high pressure, big quantity, long distance, firm discharge are carried coal slurries.
Above-mentioned purpose of the present utility model is achieved by the following technical programs: the operational system of the defeated coal slurry of a kind of many transfer pump long-distance pipes, this system is made up of first flow meter, second flowmeter, piston diaphragm pump, pipeline, three-way pipe, and special way of the present utility model is that described first flow meter is connected in parallel by pipeline and three-way pipe and first piston diaphragm pump, second piston diaphragm pump, the 3rd piston diaphragm pump, the 4th piston diaphragm pump, five piston diaphragm pump, the 6th piston diaphragm pump one end respectively successively; Described first piston diaphragm pump, second piston diaphragm pump, the 3rd piston diaphragm pump, the 4th piston diaphragm pump, five piston diaphragm pump, the 6th piston diaphragm pump the other end and second flowmeter are connected in parallel; Wherein 5 startups, one is standby, and pipeline is connected by three-way pipe with diaphragm pump, by the entrance end of piston diaphragm pump pipeline in parallel a flowmeter is installed respectively at coal slurry.
Described piston diaphragm pump all is equipped with coal slurry flow automatic regulating system.
The utility model compared with prior art, have simple in structure, easy for installation, logistics and operation cost are low, safe and efficiently, energy-conservation save land, environmental protection and economy, be not subjected to external interference, the characteristics of high pressure, big quantity, long distance, firm discharge, reduce highway and railway transport pressure, the environmental protection transportation is not subjected to the influence of ground transport environment, is widely used in coal and other mineral products industries.
Description of drawings
Fig. 1 is the utility model structural representation block diagram.
Embodiment
Below in conjunction with accompanying drawing summary of the invention is described in further detail:
As shown in Figure 1, the operational system of the defeated coal slurry of a kind of many transfer pump long-distance pipes is made up of first flow meter, second flowmeter, piston diaphragm pump, pipeline, three-way pipe, and described first flow meter 7 is connected in parallel by pipeline and three-way pipe and first piston diaphragm pump 1, second piston diaphragm pump 2, the 3rd piston diaphragm pump 3, the 4th piston diaphragm pump 4, five piston diaphragm pump 5, the 6th piston diaphragm pump 6 one ends respectively successively; Described first piston diaphragm pump 1, second piston diaphragm pump 2, the 3rd piston diaphragm pump 3, the 4th piston diaphragm pump 4, five piston diaphragm pump 5, the 6th piston diaphragm pump 6 the other ends and second flowmeter 8 are connected in parallel; Wherein 5 startups, one is standby, and pipeline is connected by three-way pipe with diaphragm pump, by the entrance end of piston diaphragm pump pipeline in parallel a flowmeter is installed respectively at coal slurry.
Piston diaphragm pump all is equipped with coal slurry flow automatic regulating system.
By reference to the accompanying drawings the utility model has been carried out exemplary description above; obvious realization of the present utility model is not subjected to the restriction of aforesaid way; as long as the various improvement of having adopted concept of system of the present utility model and technological scheme to carry out; or without improving design of the present utility model and technological scheme are directly applied to other occasion, all in protection domain of the present utility model.

Claims (2)

1. one kind many transfer pump long-distance pipes are carried the operational systems of coal slurries, this system is made up of first flow meter, second flowmeter, piston diaphragm pump, pipeline, three-way pipe, it is characterized in that described first flow meter (7) is connected in parallel by pipeline and three-way pipe and first piston diaphragm pump (1), second piston diaphragm pump (2), the 3rd piston diaphragm pump (3), the 4th piston diaphragm pump (4), five piston diaphragm pump (5), the 6th piston diaphragm pump (6) one ends respectively successively; Described first piston diaphragm pump (1), second piston diaphragm pump (2), the 3rd piston diaphragm pump (3), the 4th piston diaphragm pump (4), five piston diaphragm pump (5), the 6th piston diaphragm pump (6) the other end and second flowmeter (8) are connected in parallel; Wherein 5 startups, one is standby, and pipeline is connected by three-way pipe with diaphragm pump, by the entrance end of piston diaphragm pump pipeline in parallel a flowmeter is installed respectively at coal slurry.
2. the operational system of many transfer pump long-distance pipes conveying coal slurry according to claim 1 is characterized in that described piston diaphragm pump all is equipped with coal slurry flow automatic regulating system.
CN 201320082857 2013-02-22 2013-02-22 Running system for long-distance pipeline coal slurry transportation of plurality of transportation pumps Expired - Fee Related CN203147282U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320082857 CN203147282U (en) 2013-02-22 2013-02-22 Running system for long-distance pipeline coal slurry transportation of plurality of transportation pumps

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320082857 CN203147282U (en) 2013-02-22 2013-02-22 Running system for long-distance pipeline coal slurry transportation of plurality of transportation pumps

Publications (1)

Publication Number Publication Date
CN203147282U true CN203147282U (en) 2013-08-21

Family

ID=48974805

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320082857 Expired - Fee Related CN203147282U (en) 2013-02-22 2013-02-22 Running system for long-distance pipeline coal slurry transportation of plurality of transportation pumps

Country Status (1)

Country Link
CN (1) CN203147282U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111137686A (en) * 2019-12-31 2020-05-12 陕西神渭煤炭管道运输有限责任公司 Pipeline coal conveying system interstation open-circuit starting and switching closed-circuit control system and method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111137686A (en) * 2019-12-31 2020-05-12 陕西神渭煤炭管道运输有限责任公司 Pipeline coal conveying system interstation open-circuit starting and switching closed-circuit control system and method

Similar Documents

Publication Publication Date Title
CN202402949U (en) High-concentration coal water slurry long-distance pipeline conveying device
CN103628857A (en) Crude oil gas-liquid separation process integrated method and equipment thereof
CN102862822A (en) Large-volume long-distance airtight relay pipeline coal handling system and method
CN202868308U (en) Intermediate station pumping system device of long-distance pipeline coal transporting system
CN203147282U (en) Running system for long-distance pipeline coal slurry transportation of plurality of transportation pumps
CN104019369A (en) Long-distance pulp pipeline flow division conveying system and slurry flow division switching and conveying method
CN202868307U (en) Long-distance pipeline coal transporting head end coal water slurry transporting station system
CN214618266U (en) Energy-dissipation pressure-reduction anti-blocking piece for deep well filling pipeline and long-distance slurry pipeline conveying system
CN104229480A (en) Novel solid-liquid completely-separated pipeline conveying device and conveying method thereof
CN102182922B (en) High-head fall-off ore pump transportation pipeline
CN203998115U (en) A kind of online also Slurry Pipeline Transportation system of pipe of distance of growing
CN204534129U (en) A kind of device of anti-frozen block
CN104176505B (en) A kind of Slurry Pipeline Transportation system and conveying changing method growing the online also pipe of distance
CN105151791A (en) Novel pipeline logistics conveying system for solid goods in metro region and conveying method of novel pipeline logistics conveying system
CN206295794U (en) Limestone-gypsum wet desulfuration one is with three for lime stone pulp feeding system
CN202864467U (en) Sealed relay pipeline coal transporting system with large transportation volume and long distance
CN202868314U (en) Long-distance pipeline coal transporting high-drop energy dissipation system device
CN202188307U (en) On-line-operation automatic bypass system for long-distance high pressure pipe pump
CN204265002U (en) The novel solid pipeline transporter that solid-liquid is separated entirely
CN203215107U (en) Composite steel tube with glass reinforced plastic tube lined inside
CN203922091U (en) Solution gambling device in a kind of two phase flow delivery duct
CN215258409U (en) Energy dissipation station in slurry conveying process
CN204933418U (en) A kind of sodium sulfite adds equipment
CN201884938U (en) Multistage demagnetizing system of long-distance iron ore concentrate delivering pipe used in complex terrain
CN204704492U (en) The anticorrosion conveyance conduit of a kind of novel easy installation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Patentee after: WUHAN DESIGN & RESEARCH INSTITUTE CO., LTD. OF CHINA COAL TECHNOLOGY & ENGINEERING Group

Address before: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Patentee before: Wuhan Design and Research Institute of China Coal Technology & Engineering Group

TR01 Transfer of patent right

Effective date of registration: 20151221

Address after: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Patentee after: WUHAN DESIGN & RESEARCH INSTITUTE CO., LTD. OF CHINA COAL TECHNOLOGY & ENGINEERING Group

Patentee after: Shaanxi Shenwei Coal Pipeline Transportation Co.,Ltd.

Address before: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Patentee before: WUHAN DESIGN & RESEARCH INSTITUTE CO., LTD. OF CHINA COAL TECHNOLOGY & ENGINEERING Group

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130821

Termination date: 20170222

CF01 Termination of patent right due to non-payment of annual fee