CN202868308U - Intermediate station pumping system device of long-distance pipeline coal transporting system - Google Patents

Intermediate station pumping system device of long-distance pipeline coal transporting system Download PDF

Info

Publication number
CN202868308U
CN202868308U CN 201220533494 CN201220533494U CN202868308U CN 202868308 U CN202868308 U CN 202868308U CN 201220533494 CN201220533494 CN 201220533494 CN 201220533494 U CN201220533494 U CN 201220533494U CN 202868308 U CN202868308 U CN 202868308U
Authority
CN
China
Prior art keywords
pump
main
pumps
pressure transmitter
main pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220533494
Other languages
Chinese (zh)
Inventor
吴嘉林
李书兴
于新胜
王铁力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Shenwei Coal Pipeline Transportation Co ltd
Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Original Assignee
Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Design and Research Institute of China Coal Technology and Engineering Group filed Critical Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Priority to CN 201220533494 priority Critical patent/CN202868308U/en
Application granted granted Critical
Publication of CN202868308U publication Critical patent/CN202868308U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Control Of Non-Positive-Displacement Pumps (AREA)

Abstract

The utility model discloses an intermediate station pumping system device of a long-distance pipeline coal transporting system. The intermediate station pumping system device consists of a coal slurry inlet, outlet main pipelines, one pressure transmitter, the other pressure transmitter, a valve and a main pump machine set. The inlet end of coal water slurry inlet main pipeline is connected with one pressure transmitter, the outlet end of the coal slurry outlet main pipeline is connected with the other pressure transmitter, the coal slurry inlet main pipeline and the coal slurry outlet main pipeline are sequentially and respectively in parallel connection with main pumps in head-to-end mode, and any one of the six main pumps serves as a standby pump. The intermediate station pumping system device is reasonable in structure, convenient to use, safe and reliable, ensures safe operation of pipelines, improves the pump station utilization efficiency and prolongs the service life of pump stations. When the intermediate station pumping system device runs normally, the six pumps undertake flows of five pumps, running load of each pump is reduced, and the service life of the pumps are prolonged. When the main pumps are required to be overhauled, the flows of the overhauled pump are reduced, and the flows of other pumps are increased. When the overhauled pump shuts down, other five pumps undertake transportation flows of the six pumps.

Description

The midship pumping system device of long-distance pipe coal handling system
Technical field
The utility model relates to COAL SLURRY PIPE TRANSPORT, is specifically related to the midship pumping system device of long-distance pipe coal handling system.
Background technique
China's solid material is from the place of production to user at present, and its product is preferably used railway basically, and highway is selected water transport in place with good conditionsi, and all there is certain defective in above-mentioned three kinds of means of transportation:
1), railway transport: because railway transport is subjected to the restriction of train number scheduling and transport capacity, can not in time the Coal Transport of Product transport to client place, especially thermal power plant often can not be satisfied the demands.
2), highway transport: because highway transport vehicle is too much, be prone to accident in the road, block up, harsh weather etc. have had a strong impact on conveying efficiency.
3), water route transportation: owing to being subjected to the impact of geographical environment, need to repeatedly have bad luck, increase haulage time, coal loss and the environmental pollution in the way.
4), above-mentioned several means of transportation also exist along with the price of the energy promotes, cost of transportation also will improve gradually.Simultaneously, a large amount of dischargings of vapour, diesel exhaust have destroyed environment in transportation process, and the loss of airborne dust and material is also larger in the way.
Summary of the invention
The purpose of this utility model provides a kind of rational in infrastructure, and is easy to use, the midship pumping system device of safe and reliable long-distance pipe coal handling system.
In order to guarantee the safe operation of pipeline; reduce the pipeline outage rate; the technical solution of the utility model settling mode is: this device of midship pumping system device of a kind of long-distance pipe coal handling system is by coal slurry entrance main pipe; coal slurry outlet main pipe; one pressure transmitter; another pressure transmitter; valve; the main pump unit forms; special way of the present utility model is that the entry end of described coal slurry entrance main pipe connects a pressure transmitter; the outlet end of described coal slurry outlet main pipe connects another pressure transmitter; described coal slurry entrance main pipe; the first main pump successively is connected in parallel from beginning to end respectively between the coal slurry outlet main pipe; the second main pump; the 3rd main pump; the 4th main pump; the 5th main pump; the 6th main pump wherein selects arbitrarily 1 main pump as stand by pump in 6 main pumps.
Described main pump system head and the tail two ends all arrange pressure transmitter, the operation of the pressure control main pump by pressure transmitter.
Described each main pump inlet pipeline and outlet conduit all are connected with valve, and each pump inlet valve specification is identical, and each pump discharge valve specification is identical.
The utility model compared with prior art has rational in infrastructure, easy to use, safe and reliable characteristics, in order to guarantee the safe operation of pipeline, improve the utilization ratio of pumping plant, increase the working life of pump, when simple mode is taked the main pump normal operation exactly, each pump is in running state, when a certain main pump of operation need to overhaul, increases other its main pump flows, reduce the maintenance pump duty, main pump stops the most at last.Like this, the pump group is in running, and every pump is all being born operating flux, greatly reduces the operating load of every pump.And can adjust according to main pump inlet/outlet pressure condition the running state of main pump.
Description of drawings
Fig. 1 is many pumps of the utility model switching construction schematic diagram.
Embodiment
Accompanying drawing is embodiment of the present utility model.
Below in conjunction with accompanying drawing the model utility content is further described in detail:
With reference to shown in Figure 1, a kind of midship pumping system device of long-distance pipe coal handling system, comprise coal slurry entrance main pipe, coal slurry outlet main pipe, one pressure transmitter, another pressure transmitter, valve, the main pump unit, the entry end that it is characterized in that described coal slurry entrance main pipe 9 connects a pressure transmitter 7, the outlet end of described coal slurry outlet main pipe 10 connects another pressure transmitter 8, described coal slurry entrance main pipe 9, the first main pump 1 successively is connected in parallel from beginning to end respectively between the coal slurry outlet main pipe 10, the second main pump 2, the 3rd main pump 3, the 4th main pump 4, the 5th main pump 5, the 6th main pump 6 wherein selects arbitrarily a main pump to can be used as stand by pump in six main pumps.
Described main pump system head and the tail two ends all arrange pressure transmitter, the operation of the pressure control main pump by pressure transmitter.
Described main pump head and the tail two ends all connect as one by pipeline and flange.
Described each main pump inlet pipeline and outlet conduit all are connected with valve, and each pump inlet valve specification is identical, and each pump discharge valve specification is identical.
Be provided with a plurality of midships in the whole coal slurry transport system, the capital equipment of each pumping plant includes a pressure transmitter, another pressure transmitter and 6 main pumps, and the inlet/outlet of every main pump has valve; Common 6 main pumps 1,2,3,4,5,6 move simultaneously, if wherein a main pump needs maintenance (supposing main pump 1), at this moment need to improve other main pump flows 2,3,4,5,6, can stably the maintenance pump be stopped like this, but not allowing whole system stop, system normally moves.
When the midship pumping system device operation main pump of long-distance pipe coal handling system need to overhaul, the maintenance pump stopped to carry out according to the following step:
(1), maintenance main pump 1 reduces flow gradually, simultaneously other 5 operation main pumps 2,3,4,5,6 increase flow gradually, until the maintenance pump is shut down, this moment, 5 main pumps were born whole flows of normal conveying;
(2), overhaul changing pump;
(3), complete when maintenance pump maintenance, will overhaul pump and come into operation; The process that the maintenance pump comes into operation is: other operation main pump 2,3,4,5,6 flows are reduced, and maintenance main pump 1 flow raises, and finally reaches 6 main pump flow equilibriums, the normal operation of recovery system.
The above has carried out exemplary description to the utility model by reference to the accompanying drawings; obvious realization of the present utility model is not subjected to the restriction of aforesaid way; as long as the various improvement of having adopted the technical solution of the utility model to carry out; or without improving design of the present utility model and technological scheme are directly applied to other occasion, all in protection domain of the present utility model.

Claims (3)

1. the midship pumping system device of a long-distance pipe coal handling system, this device is by coal slurry entrance main pipe, coal slurry outlet main pipe, one pressure transmitter, another pressure transmitter, valve, the main pump unit forms, the entry end that it is characterized in that described coal slurry entrance main pipe (9) connects a pressure transmitter (7), the outlet end of described coal slurry outlet main pipe (10) connects another pressure transmitter (8), described coal slurry entrance main pipe (9), the first main pump (1) successively is connected in parallel from beginning to end respectively between the coal slurry outlet main pipe (10), the second main pump (2), the 3rd main pump (3), the 4th main pump (4), the 5th main pump (5), the 6th main pump (6) wherein selects arbitrarily a main pump to can be used as stand by pump in six main pumps.
2. the midship pumping system device of described long-distance pipe coal handling system according to claim 1 is characterized in that described main pump system head and the tail two ends all arrange pressure transmitter, the operation of the pressure control main pump by pressure transmitter.
3. the midship pumping system device of described long-distance pipe coal handling system according to claim 1 is characterized in that described each main pump inlet pipeline and outlet conduit all are connected with valve, and each pump inlet valve specification is identical, and each pump discharge valve specification is identical.
CN 201220533494 2012-10-18 2012-10-18 Intermediate station pumping system device of long-distance pipeline coal transporting system Expired - Fee Related CN202868308U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220533494 CN202868308U (en) 2012-10-18 2012-10-18 Intermediate station pumping system device of long-distance pipeline coal transporting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220533494 CN202868308U (en) 2012-10-18 2012-10-18 Intermediate station pumping system device of long-distance pipeline coal transporting system

Publications (1)

Publication Number Publication Date
CN202868308U true CN202868308U (en) 2013-04-10

Family

ID=48035024

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220533494 Expired - Fee Related CN202868308U (en) 2012-10-18 2012-10-18 Intermediate station pumping system device of long-distance pipeline coal transporting system

Country Status (1)

Country Link
CN (1) CN202868308U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103234119A (en) * 2013-05-11 2013-08-07 中煤科工集团武汉设计研究院 With-paste starting method for long distance pipeline coal conveying system
CN103267228A (en) * 2013-05-23 2013-08-28 中煤科工集团武汉设计研究院 Control method for operation of devices of long-distance pipeline coal transporting intermediate station
CN103939742A (en) * 2014-04-21 2014-07-23 云南大红山管道有限公司 Stable pumping system of high pressure slurry pipeline
CN104154419A (en) * 2014-06-18 2014-11-19 云南大红山管道有限公司 Double-concentration-basin slurry pipeline conveying system
CN111137686A (en) * 2019-12-31 2020-05-12 陕西神渭煤炭管道运输有限责任公司 Pipeline coal conveying system interstation open-circuit starting and switching closed-circuit control system and method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103234119A (en) * 2013-05-11 2013-08-07 中煤科工集团武汉设计研究院 With-paste starting method for long distance pipeline coal conveying system
CN103267228A (en) * 2013-05-23 2013-08-28 中煤科工集团武汉设计研究院 Control method for operation of devices of long-distance pipeline coal transporting intermediate station
CN103939742A (en) * 2014-04-21 2014-07-23 云南大红山管道有限公司 Stable pumping system of high pressure slurry pipeline
CN103939742B (en) * 2014-04-21 2016-08-24 云南大红山管道有限公司 A kind of steady pumping system of high-pressure slurry pipeline
CN104154419A (en) * 2014-06-18 2014-11-19 云南大红山管道有限公司 Double-concentration-basin slurry pipeline conveying system
CN104154419B (en) * 2014-06-18 2016-08-17 云南大红山管道有限公司 A kind of double concentration basin Slurry Pipeline Transportation system
CN111137686A (en) * 2019-12-31 2020-05-12 陕西神渭煤炭管道运输有限责任公司 Pipeline coal conveying system interstation open-circuit starting and switching closed-circuit control system and method

Similar Documents

Publication Publication Date Title
CN202868308U (en) Intermediate station pumping system device of long-distance pipeline coal transporting system
CN202705328U (en) Skidded complete set of device for collecting and processing oil field gas
CN201605036U (en) Fluidized air supply device for ash transportation system
CN104019365B (en) A kind of multi stage pumping station slurry pipeline multi-line induction system and method
CN205118669U (en) Long distance solid material pipeline switches multi -thread conveying system on line
CN204164652U (en) A kind of LCNG gas station auxiliary gas feeder and the gas station comprising it
CN203998115U (en) A kind of online also Slurry Pipeline Transportation system of pipe of distance of growing
CN202868307U (en) Long-distance pipeline coal transporting head end coal water slurry transporting station system
CN205295265U (en) High pressure highly resistance sulphur sled dress separator
CN204629080U (en) A kind of mobile LNG skid air supply system
CN204083783U (en) The skid of a kind of LNG gasification pressure regulation metering
CN203047370U (en) Long tube trailer without continuous beam
CN202627069U (en) Movable combined-type intaking pump station
CN208932437U (en) A kind of generating set conveying equipment
CN113320549A (en) Special line-mounted station plane arrangement structure for heavy haul railway surrounding rail-connecting station
CN104118437B (en) A kind of vacuum stream pipe-line transportation system
CN203223740U (en) Multi-channel parallel CNG (Compressed Natural Gas) skid-mounted gas unloading device
CN102410442A (en) CNG (Compressed Natural Gas) storage and transportation gas filling trailer
CN203147282U (en) Running system for long-distance pipeline coal slurry transportation of plurality of transportation pumps
CN202012324U (en) Module structure of gas injection and gas extraction for gas storage wellhead
CN205708982U (en) A kind of gas cylinder loading/unloading platform structure
CN205155553U (en) Two pressure boost sled dress devices of unloading that unload parking stall
CN108556687A (en) Contact net power supply air source provides system and method
CN208428996U (en) Contact net power supply gas source provides system
CN202381976U (en) Double-gun and double-line gas filling column

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHAANXI SHENWEI COAL PIPELINE TRANSPORTATION CO.,

Effective date: 20150327

C56 Change in the name or address of the patentee

Owner name: WUHAN DESIGN AND RESEARCH INSTITUTE CO., LTD. PF C

Free format text: FORMER NAME: WUHAN DESIGN AND RESEARCH INSTITUTE OF CHINA COAL TECHNOLOGY + ENGINEERING GROUP

CP01 Change in the name or title of a patent holder

Address after: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Patentee after: WUHAN DESIGN & RESEARCH INSTITUTE CO., LTD. OF CHINA COAL TECHNOLOGY & ENGINEERING Group

Address before: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Patentee before: Wuhan Design and Research Institute of China Coal Technology & Engineering Group

TR01 Transfer of patent right

Effective date of registration: 20150327

Address after: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Patentee after: WUHAN DESIGN & RESEARCH INSTITUTE CO., LTD. OF CHINA COAL TECHNOLOGY & ENGINEERING Group

Patentee after: Shaanxi Shenwei Coal Pipeline Transportation Co.,Ltd.

Address before: 430064 Hubei Province, Wuhan city Wuchang District Wuluo Road No. 442

Patentee before: WUHAN DESIGN & RESEARCH INSTITUTE CO., LTD. OF CHINA COAL TECHNOLOGY & ENGINEERING Group

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130410

Termination date: 20161018

CF01 Termination of patent right due to non-payment of annual fee