CN203097905U - Tunnel secondary lining back arch grouting pipe reserving system - Google Patents

Tunnel secondary lining back arch grouting pipe reserving system Download PDF

Info

Publication number
CN203097905U
CN203097905U CN 201320090867 CN201320090867U CN203097905U CN 203097905 U CN203097905 U CN 203097905U CN 201320090867 CN201320090867 CN 201320090867 CN 201320090867 U CN201320090867 U CN 201320090867U CN 203097905 U CN203097905 U CN 203097905U
Authority
CN
China
Prior art keywords
grouting pipe
lining
tunnel
spring
hogback
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201320090867
Other languages
Chinese (zh)
Inventor
王炳军
唐振兴
敖鹏
康宝
王帅
沈建海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHANGYE CONSTRUCTION GROUP Co Ltd
Original Assignee
CHANGYE CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHANGYE CONSTRUCTION GROUP Co Ltd filed Critical CHANGYE CONSTRUCTION GROUP Co Ltd
Priority to CN 201320090867 priority Critical patent/CN203097905U/en
Application granted granted Critical
Publication of CN203097905U publication Critical patent/CN203097905U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model belongs to the field of a grouting pipe pre-buried technology in the tunnel secondary lining construction process, and discloses a tunnel secondary lining back arch grouting pipe reserving system which comprises a lining trolley panel, an elastic cushion body provided with a longitudinal through hole, and a grouting pipe. The elastic cushion body and the grouting pipe are installed in a matched mode from top to bottom in sequence, and the grouting pipe is communicated with the longitudinal through hole of the elastic cushion body. The lower end of the grouting pipe penetrates through the lining trolley panel and extends downwards. A spring is installed on the outer wall, located under the lining trolley panel, of the grouting pipe. The top end of the spring is fixedly connected with the lining trolley panel, the bottom end of the spring is fixedly connected with the grouting pipe, and the spring is in a stretching state. The tunnel secondary lining back arch grouting pipe reserving system not only can achieve reservation of the grouting pipe, but also can effectively prevent the grouting pipe from jacking and breaking a waterproof plate, and can be tightly attached to the waterproof plate to prevent cement paste from flowing backwards and blocking the grouting pipe in the secondary lining construction process when concrete pouring is carried out.

Description

The Tunnel Second Lining hogback is reserved the Grouting Pipe system
Technical field
The utility model discloses a kind of Tunnel Second Lining hogback and reserves the Grouting Pipe system, belongs to the pre-buried technical field of Grouting Pipe in the Tunnel Second Lining Construction process.
Background technology
In recent years, along with greatly developing of traffic engineering, highway, railway and municipal construction of tunnel in use hidden danger such as secondary lining cracking, infiltration are more and more, and it is the principal element that forms hidden danger that the secondary lining hogback comes to nothing.The highway tunnel design and the job specfication requirement of new revision must be reserved the top injected hole during Second Lining Construction, after Second Lining Construction is intact, must carries out the hogback mud jacking and handle.In the prior art, because vault secondary lining thickness deviation is bigger in construction, lining trolley can float and sink during concreting, exists easy bursting splash guard, lining trolley panel deformation, two to serve as a contrast fixedly problem such as Grouting Pipe of unreinforced sections.Also exist cement paste to flow out, stop up the phenomenon of reserving Grouting Pipe when simultaneously, two linings bind mud jacking from Grouting Pipe.In addition, also exist the reservation Grouting Pipe to get rusty for a long time and pollute the problems of two linings.
The utility model content
At a series of construction difficult problems in the above-mentioned background technology, the utility model provides a kind of Tunnel Second Lining hogback to reserve the Grouting Pipe system, this system is in the Second Lining Construction process, during fluid concrete, not only can realize the reservation of Grouting Pipe, and can effectively prevent Grouting Pipe bursting splash guard, also can be close to splash guard and prevent cement paste refluence obstruction Grouting Pipe.
For achieving the above object, the technical scheme that the utility model adopted is:
A kind of Tunnel Second Lining hogback is reserved the Grouting Pipe system, comprise the lining trolley panel, have elastic pad, the Grouting Pipe of longitudinal hole, wherein elastic pad and Grouting Pipe from top to bottom cooperate installation successively, and Grouting Pipe is communicated with the longitudinal hole of elastic pad, the lower end of Grouting Pipe penetrates the lining trolley panel and extends downwards, Grouting Pipe is positioned on the outer wall of lining trolley panel below spring is installed, fixedly connected with the platform building cart panel in the top of spring, fixedly connected with Grouting Pipe in the bottom of spring, spring is in extended state simultaneously.
As the further setting of such scheme, the top of described spring is fixedly connected with packing ring, is installed with the positioning component of holding packing ring on the lower surface of lining trolley panel.
Described positioning component comprises junction plate, steel plate latch, two reinforcing bar latches, draw-in groove, and junction plate and draw-in groove all are fixedly mounted on the lower surface of lining trolley panel, and junction plate and draw-in groove lay respectively at the relative both sides of packing ring; One side of steel plate latch has notch, corresponding another side is provided with lug; The steel plate latch is installed between the lower surface and packing ring of lining trolley panel, and an end of steel plate latch band lug is fixed in the draw-in groove, the end of steel plate latch trough of belt mouth is fixed between the lower surface of junction plate and lining trolley panel, and the Grouting Pipe holding is in the notch of steel plate latch; Two reinforcing bar latches are fixed between lug and the junction plate, and the packing ring holding is between reinforcing bar latch and steel plate latch.This positioning component not only can carry out packing ring holding location, and this positioning component can disassembly and assembly, so that recycle.
The lower end of described junction plate is provided with the guide strip of tape guide groove, and the lower end of Grouting Pipe is passed behind the gathering sill and downwards and extended, and guide strip is positioned at the below of spring.Guide strip can occur in the process of come-up or sinking Grouting Pipe being played certain guide effect in Grouting Pipe.
From top to bottom also cooperate successively between described elastic pad and the Grouting Pipe tube connector, band wire connection head are installed.In Second Lining Construction, before the final set, Grouting Pipe can be split out behind the concrete initial set, and elastic pad, tube connector, band wire connection head are embedded in the concrete, the later stage need be carried out the hogback mud jacking when handling, and only needs Grouting Pipe is screwed into to get final product.The Grouting Pipe that so, just can effectively solve reservation is got rusty for a long time and is polluted the problems of two linings.
The bottom of described spring is fixedly connected with nut, and the outer wall of nut and Grouting Pipe is by being threaded.
The lower end outer wall of described elastic pad and the upper end inwall of tube connector be by being threaded, and the upper end outer wall of the lower end inwall of tube connector and band wire connection head is by being threaded, and the lower end inwall of band wire connection head and the upper end outer wall of Grouting Pipe are by being threaded.
Offer big hole and the small sircle hole that is interconnected on the described lining trolley panel, Grouting Pipe runs through the lining trolley panel by small sircle hole, and the steel plate latch covers big hole fully, seals.The setting of big hole is mainly used in convenient the installation.After elastic pad, tube connector, band wire connection head, Grouting Pipe connect successively, insert in two linings, hold out against splash guard by big hole, vertical then traversing to small sircle hole.
Described elastic pad is bowl-shape, is preferably rubber cup.
Described tube connector is a pvc pipe, and band wire connection head is a PVC band wire connection head.
The utility model Tunnel Second Lining hogback is reserved the Grouting Pipe system, at elastic pad and the combination that is in the spring of extended state all the time be provided with down, can effectively prevent Grouting Pipe bursting splash guard, also can be close to splash guard and prevent cement paste refluence obstruction Grouting Pipe, also because elastic pad has elasticity, can also make cement paste be pressed into two from Grouting Pipe normally during the hogback mud jacking and serve as a contrast the position of coming to nothing simultaneously.
The utility model is described in further detail below in conjunction with the drawings and specific embodiments.
Description of drawings
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is the structural representation of facing of Fig. 1;
Fig. 3 is the structural representation of lining trolley panel;
Fig. 4 is the structural representation of steel plate latch;
Fig. 5 is the structural representation of junction plate;
Fig. 6 is the right TV structure schematic diagram of Fig. 5.
The specific embodiment
As Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, shown in Figure 6, the utility model Tunnel Second Lining hogback is reserved the Grouting Pipe system, comprise lining trolley panel 1, the elastic pad 3 that has longitudinal hole 2, tube connector 4, band wire connection 5, Grouting Pipe 6, wherein elastic pad 3, tube connector 4, band wire connection 5, Grouting Pipe 6 from top to bottom cooperates successively to install and is communicated with, tube connector 4 is communicated with the longitudinal hole 2 of elastic pad 3, the lower end of Grouting Pipe 6 penetrates lining trolley panel 1 and extends downwards, Grouting Pipe 6 is positioned on the outer wall of lining trolley panel 1 below spring 7 is installed, fixedly connected with platform building cart panel 1 in the top of spring 7, fixedly connected with Grouting Pipe 6 in the bottom of spring 7, spring 7 is in extended state simultaneously.
In the present embodiment, concrete annexation between elastic pad 3, tube connector 4, band wire connection 5, the Grouting Pipe 6 is: the lower end outer wall of elastic pad 3 and the upper end inwall of tube connector 4 are by being threaded, the upper end outer wall of the lower end inwall of tube connector 4 and band wire connection 5 is by being threaded, and the lower end inwall of band wire connection 5 and the upper end outer wall of Grouting Pipe 6 are by being threaded.
The concrete mounting method of spring 7 is as follows: the top of spring 7 is fixedly connected with packing ring 8, be installed with the positioning component of holding packing ring 8 on the lower surface of lining trolley panel 1, the bottom of spring 7 is fixedly connected with nut 9, and the outer wall of nut 9 and Grouting Pipe 6 is by being threaded.
Positioning component comprises junction plate 10, steel plate latch 11, two reinforcing bar latches 12, draw-in groove 13, and junction plate 10 and draw-in groove 13 all are fixedly mounted on the lower surface of lining trolley panel 1, and junction plate 10 and draw-in groove 13 lay respectively at the relative both sides of packing ring 8; One side of steel plate latch 11 has notch 14, corresponding another side is provided with lug 15; Steel plate latch 11 is installed between the lower surface and packing ring 8 of lining trolley panel 1, and an end of steel plate latch 11 band lugs 15 is fixed in the draw-in groove 13, the end of steel plate latch 11 trough of belt mouths 14 is fixed between the lower surface of junction plate 10 and lining trolley panel 1, and Grouting Pipe 6 holdings are in the notch 14 of steel plate latch 11; Two reinforcing bar latches 12 are fixed between lug 15 and the junction plate 10, and packing ring 8 holdings are between reinforcing bar latch 12 and steel plate latch 11.The lower end of junction plate 10 is provided with the guide strip 17 of tape guide groove 16, and the lower end of Grouting Pipe 6 is passed gathering sill 16 backs and extended downwards, and guide strip 17 is positioned at the below of spring 7.
Install for convenient, offer the big hole 18 and the small sircle hole 19 that are interconnected on the lining trolley panel 1, Grouting Pipe 6 runs through lining trolley panel 1 by small sircle hole 19.Steel plate latch 11 in the positioning component also has the effect of coverings, sealing big hole 18 and partly not covered small sircle hole 19 of living except fixing Grouting Pipe 6.
In the present embodiment, elastic pad 3 is bowl-shape, is preferably rubber cup; Tube connector 4 is a pvc pipe, and band wire connection 5 is with the wire connection head for PVC.
Concrete mounting method of the present utility model is as follows:
Elastic pad 3, tube connector 4, band wire connection 5, Grouting Pipe 6 cooperated to install to be communicated with successively form fastener inserts, connect again after if any the space between each connector with the band winding.Before installing between Grouting Pipe 6 and the band wire connection 5, be easy to disassembling of later stage at Grouting Pipe 6 upper end coating butters.
Above-mentioned fastener inserts is inserted in two linings by the big hole on the lining trolley panel 1 18, made elastic pad 3 hold out against splash guard, vertical traversing to small sircle hole 19.
Insert steel plate latch 11, fixedly Grouting Pipe 6.One end of steel plate latch 11 band lugs 15 is fixed in the draw-in groove 13, the end of steel plate latch 11 trough of belt mouths 14 is folded in that (junction plate 10 upper surfaces offer two breach 20 between the lower surface of junction plate 10 and lining trolley panel 1, form groove between the lower surface of breach 20 and lining trolley panel 1, the end of steel plate latch 11 trough of belt mouths 14 then is plugged in the groove).
Insert reinforcing bar latch 12, retaining washer 8, with packing ring 8 holdings between reinforcing bar latch 12 and steel plate latch 11.Offer on lug 15 and the junction plate 10 and specialize in the through hole that reinforcing bar latch 12 wears usefulness.
Nut 9 is twisted downwards, make spring 7 be in extended state, guarantee that elastic pad 3 holds out against splash guard.
After the utility model installs, in the process of concrete perfusion, during two lining chassis come-ups, packing ring 8 upwards can be drawn, make that spring 7 is further stretched, in the process that spring 7 is further stretched, nut 9 can drive upwards top of Grouting Pipe 6, makes elastic pad 3 all the more hold out against splash guard at last.Two lining chassis sink when binding, though packing ring 8 can be pressed down, reduced the stretch range of spring 7, but spring 7 be in all the time be subjected to extended state (because the stretch range that reduces all the time less than spring 7 original be subjected to stretch range), therefore can guarantee between elastic pad 3 and the splash guard closely connectedly all the time, guarantee that cement paste does not pour in the Grouting Pipe 6.When two lining chassis come-ups or the domains of walker of sinking have exceeded scope of design, so only need to increase the height of junction plate 10, change long spring 7 and get final product.
Behind the concrete initial set before the final set (concrete final set grouting behind shaft or drift lining pipe 6 back-out difficulty), pull out reinforcing bar latch 12, pull out steel plate latch 11, Grouting Pipe 6 is back-outed.Arrive this, the pre-buried success of pre-buried guard system, pre-buried band wire connection 5 has internal thread, and later stage Grouting Pipe 6 can be screwed into, the effective connection when guaranteeing slip casting.
If the various factors in the concreting process causes the lining cutting hogback to have the phenomenon of coming to nothing, grouting pressure can be washed rubber cup open, makes cement paste fill up the space.Because rubber cup has elasticity, can make cement paste be pressed into two from Grouting Pipe normally during the hogback mud jacking and serve as a contrast the position of coming to nothing.
Adopt the utility model Tunnel Second Lining hogback to reserve the Grouting Pipe system, effectively solved cement paste plugging problem, more can effectively guarantee the function of use of pre-pipe laying.The most of GB accessory that adopts of native system, it is convenient to buy, other handling eases, the native system applicability is strong, and any type of tunnel double-lining all is suitable for, and only needs to change the length of tube connector 4.Positioning component recycles, and the life-span is long, low price, and a cover is no more than 100 yuan; Fastener inserts cheap (3 yuan of less thaies) can be saved cost 75%.Native system is easy for installation, pre-pipe laying set-up time less than 5 minutes.
The utility model is applicable to the pre-buried Grouting Pipe of any type of secondary lining, only needs to get final product according to the tube connector 4 of different lining thickness intercepting appropriate length.
The foregoing description only is used to the inventive concept of the present utility model of explaining, but not to the qualification of the utility model rights protection, allly utilizes this design that the utility model is carried out the change of unsubstantiality, all should fall into protection domain of the present utility model.

Claims (10)

1. a Tunnel Second Lining hogback is reserved the Grouting Pipe system, it is characterized in that: comprise the lining trolley panel, have elastic pad, the Grouting Pipe of longitudinal hole, wherein elastic pad and Grouting Pipe from top to bottom cooperate installation successively, and Grouting Pipe is communicated with the longitudinal hole of elastic pad, the lower end of Grouting Pipe penetrates the lining trolley panel and extends downwards, Grouting Pipe is positioned on the outer wall of lining trolley panel below spring is installed, fixedly connected with the platform building cart panel in the top of spring, fixedly connected with Grouting Pipe in the bottom of spring, spring is in extended state simultaneously.
2. Tunnel Second Lining hogback as claimed in claim 1 is reserved the Grouting Pipe system, and it is characterized in that: the top of described spring is fixedly connected with packing ring, is installed with the positioning component of holding packing ring on the lower surface of lining trolley panel.
3. Tunnel Second Lining hogback as claimed in claim 2 is reserved the Grouting Pipe system, it is characterized in that: described positioning component comprises junction plate, steel plate latch, two reinforcing bar latches, draw-in groove, junction plate and draw-in groove all are fixedly mounted on the lower surface of lining trolley panel, and junction plate and draw-in groove lay respectively at the relative both sides of packing ring; One side of steel plate latch has notch, corresponding another side is provided with lug; The steel plate latch is installed between the lower surface and packing ring of lining trolley panel, and an end of steel plate latch band lug is fixed in the draw-in groove, the end of steel plate latch trough of belt mouth is fixed between the lower surface of junction plate and lining trolley panel, and the Grouting Pipe holding is in the notch of steel plate latch; Two reinforcing bar latches are fixed between lug and the junction plate, and the packing ring holding is between reinforcing bar latch and steel plate latch.
4. Tunnel Second Lining hogback as claimed in claim 3 is reserved the Grouting Pipe system, and it is characterized in that: the lower end of described junction plate is provided with the guide strip of tape guide groove, and the lower end of Grouting Pipe is passed behind the gathering sill and downwards and extended, and guide strip is positioned at the below of spring.
5. Tunnel Second Lining hogback as claimed in claim 1 is reserved the Grouting Pipe system, it is characterized in that: from top to bottom also cooperates successively between described elastic pad and the Grouting Pipe tube connector is installed, is with the wire connection head.
6. Tunnel Second Lining hogback as claimed in claim 1 is reserved the Grouting Pipe system, and it is characterized in that: the bottom of described spring is fixedly connected with nut, and the outer wall of nut and Grouting Pipe is by being threaded.
7. Tunnel Second Lining hogback as claimed in claim 5 is reserved the Grouting Pipe system, it is characterized in that: the lower end outer wall of described elastic pad and the upper end inwall of tube connector are by being threaded, the upper end outer wall of the lower end inwall of tube connector and band wire connection head is by being threaded, and the lower end inwall of band wire connection head and the upper end outer wall of Grouting Pipe are by being threaded.
8. Tunnel Second Lining hogback as claimed in claim 3 is reserved the Grouting Pipe system, and it is characterized in that: offer big hole and the small sircle hole that is interconnected on the described lining trolley panel, Grouting Pipe runs through the lining trolley panel by small sircle hole.
9. Tunnel Second Lining hogback as claimed in claim 1 is reserved the Grouting Pipe system, and it is characterized in that: described elastic pad is a rubber cup.
10. Tunnel Second Lining hogback as claimed in claim 5 is reserved the Grouting Pipe system, and it is characterized in that: described tube connector is a pvc pipe, and band wire connection head is a PVC band wire connection head.
CN 201320090867 2013-02-28 2013-02-28 Tunnel secondary lining back arch grouting pipe reserving system Expired - Lifetime CN203097905U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320090867 CN203097905U (en) 2013-02-28 2013-02-28 Tunnel secondary lining back arch grouting pipe reserving system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320090867 CN203097905U (en) 2013-02-28 2013-02-28 Tunnel secondary lining back arch grouting pipe reserving system

Publications (1)

Publication Number Publication Date
CN203097905U true CN203097905U (en) 2013-07-31

Family

ID=48849314

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320090867 Expired - Lifetime CN203097905U (en) 2013-02-28 2013-02-28 Tunnel secondary lining back arch grouting pipe reserving system

Country Status (1)

Country Link
CN (1) CN203097905U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114863A (en) * 2013-02-28 2013-05-22 长业建设集团有限公司 Tunnel secondary lining back arch grouting pipe reserving system
CN108442938A (en) * 2018-02-01 2018-08-24 中铁十二局集团有限公司 A kind of two lining band of full hydraulic flat car is molded into pulp grinder structure and its grouting process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114863A (en) * 2013-02-28 2013-05-22 长业建设集团有限公司 Tunnel secondary lining back arch grouting pipe reserving system
CN103114863B (en) * 2013-02-28 2015-01-28 长业建设集团有限公司 Tunnel secondary lining back arch grouting pipe reserving system
CN108442938A (en) * 2018-02-01 2018-08-24 中铁十二局集团有限公司 A kind of two lining band of full hydraulic flat car is molded into pulp grinder structure and its grouting process

Similar Documents

Publication Publication Date Title
CN103114863B (en) Tunnel secondary lining back arch grouting pipe reserving system
CN103821180B (en) The two water-stopping structure of a kind of concrete extension joint
CN206625403U (en) A kind of sleeve grouting envelope storehouse system
CN209344734U (en) A kind of urban road construction underground pipe network pre-embedded device
KR101732669B1 (en) Reinforcement member, concrete box reinforced with the same and the construction method thereof
CN203097905U (en) Tunnel secondary lining back arch grouting pipe reserving system
CN113653355B (en) Construction method for plugging reserved hole of lower laminate of closed space
CN103857857B (en) With method and the wall assembly of dry wall wall components assembling wall
CN203176574U (en) Seepage resistant convenient concrete layer drainage pipe connecting embedding device
CN205171502U (en) Device is flowed in lap guard of underground continuous wall flexible rubber hose formula
CN209637782U (en) Tunnel water proofing discharge structure
CN205975951U (en) Side fascia installation node
CN214274724U (en) Water pipe for temporary construction of pre-buried overground building
CN205444570U (en) Wallboard connected node
CN110230326A (en) A kind of underground connecting pipeline structure waterproofing of movement joints construction
CN211285496U (en) Water stopping structure at joint between water inlet pool and main canal box culvert of matched engineering
CN104727276B (en) The manufacture method of the double; two water sealing structure of concrete extension joint
CN204728365U (en) A kind of aqueduct valve well mounting structure
CN103924694B (en) A kind of mending-leakage processing method of water proofing property concrete extension joint
CN105863125A (en) Mounting joint for external wall panel
CN105863130A (en) External wall panel mounting joint
CN206109980U (en) Saddle end part sealing device with two locators
CN205976140U (en) Side fascia installation node
CN212507441U (en) Slip casting pipe interface protection device
CN207062995U (en) Hoisting port

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130731