CN203035255U - Double-skip inclined shaft bottom ore loading device - Google Patents

Double-skip inclined shaft bottom ore loading device Download PDF

Info

Publication number
CN203035255U
CN203035255U CN 201320038882 CN201320038882U CN203035255U CN 203035255 U CN203035255 U CN 203035255U CN 201320038882 CN201320038882 CN 201320038882 CN 201320038882 U CN201320038882 U CN 201320038882U CN 203035255 U CN203035255 U CN 203035255U
Authority
CN
China
Prior art keywords
skip
ore deposit
shaft
inclined shaft
ore loading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320038882
Other languages
Chinese (zh)
Inventor
汪顺民
戴紫孔
陶平凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CINF Engineering Corp Ltd
Original Assignee
CINF Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CINF Engineering Corp Ltd filed Critical CINF Engineering Corp Ltd
Priority to CN 201320038882 priority Critical patent/CN203035255U/en
Application granted granted Critical
Publication of CN203035255U publication Critical patent/CN203035255U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Carbon Steel Or Casting Steel Manufacturing (AREA)

Abstract

The utility model discloses a double-skip inclined shaft bottom ore loading device which comprises two skips, wherein an ore loading section track is arranged at an inclined shaft bottom. The ore loading section track is alternately connected with two operating tracks of the two skips through a turnout. An inclined shaft which is arranged above a skip loading position of the ore loading section track is connected with a jack shaft, and a set of ore loading device is fixed at the bottom of the jack shaft. The skips conduct up-down operation along the ore loading section tracks and operating tracks of the skips. Ore loading of the two skips of the inclined shaft can be conducted only through a section of jack shaft and the set of ore loading device. The double-skip inclined shaft bottom ore loading device has the main advantages of being capable of saving the section of jack shaft and the set of ore loading device, reducing construction work amount, reducing investment of capital construction, shortening construction period, enabling a mine to be put in production as quickly as possible, and creating good economic benefits.

Description

Dress ore deposit, a kind of double-loop pattern inclined shaft shaft bottom equipment
Technical field
The utility model relates to a kind of dress ore deposit equipment, particularly dress ore deposit, a kind of double-loop pattern inclined shaft shaft bottom equipment.
Background technology
When inclined shaft year 30~600,000 tons of lifting capacitys, inclined shaft skip dress ore deposit can be considered to adopt in the inclined shaft inclination angle in the time of 20 °~35 °.Skip bucket dress ore deposit equipment is mechanization system, speed of service height, good stability, security of operation.Inclined shaft skip adopts the double hook Hoisting System more, and 2 skip buckets are along orbital motion separately in the inclines, and when 1 skip bucket loaded in the shaft bottom, 1 skip bucket unloaded at well head in addition.As shown in Figure 1, dress ore deposit in double-loop pattern inclined shaft shaft bottom normally disposes 2 suit ore deposit devices and gives 2 skip bucket dress ore deposits respectively in the shaft bottom.This mode 2 sections drop shafts of need constructing are arranged 1 suit ore deposit device respectively every section drop shaft bottom.This configuration mode construction works amount is big, construction period lengthens, increased investment, under underground weak-walled situation, has increased difficulty of construction especially.Therefore be necessary dress ore deposit, existing double-loop pattern inclined shaft shaft bottom mode is improved.
Summary of the invention
Technical problem to be solved in the utility model is at the prior art deficiency, to provide dress ore deposit, a kind of double-loop pattern inclined shaft shaft bottom equipment, minimizing construction works amount and difficulty of construction, shortening construction period.
For solving the problems of the technologies described above, the technical scheme that the utility model adopts is: dress ore deposit, a kind of double-loop pattern inclined shaft shaft bottom equipment, comprise two skip buckets, described inclined shaft shaft bottom is provided with dress ore deposit section track, and described dress ore deposit section track alternately is connected with two orbits of described two skip buckets by a track switch; Described drop shaft is connected by the dress ore deposit device that is fixed on described drop shaft bottom with described inclined shaft; Described skip bucket moves up and down along described dress ore deposit section track and orbit separately.
As preferred version, described track switch is electronic bilateral turnout, and described electronic bilateral turnout is provided with electrically operated derailleur; Described skip bucket orbit is provided with detector.
Characteristics according to the double-loop pattern inclined shaft hoisting, the i.e. different fashionable dresses of two skip buckets ore deposits, when 1 skip bucket loads in the shaft bottom, in addition 1 skip bucket is in the characteristics of well head unloading, by arranging 1 electronic bilateral turnout between dress ore deposit section track and two skip buckets (i.e. 1, No. 2 skip bucket) orbit at the bottom of the skip shaft, make that adorning ore deposit section track at the bottom of the skip shaft is connected with No. 1 or No. 2 skip bucket orbits.When adorning the ore deposit at the bottom of No. 1 skip shaft, electronic bilateral turnout is adorned ore deposit section track and No. 1 skip bucket orbit at the bottom of connecting skip shaft, when finish in No. 1 skip bucket dress ore deposit, upwards operation is by behind the electronic bilateral turnout, the up signalizing activity that passes through of No. 1 skip bucket that electronic bilateral turnout sends according to detector, adorn ore deposit section track and No. 2 skip bucket orbits at the bottom of transferring the connection skip shaft to, for getting ready in No. 2 descending skip buckets dress ore deposits.
Compared with prior art, the beneficial effect that the utility model has is: the utility model only needs 1 section drop shaft, 1 suit ore deposit device just can give two inclined shaft skip dress ore deposits, its topmost advantage is to save 1 section drop shaft and 1 suit ore deposit device, can reduce the construction works amount, reduce capital investment, shorten construction period, can be put into production as early as possible in the mine, create good economic benefit.
Description of drawings
Fig. 1 is dress ore deposit, traditional double skip bucket inclined shaft shaft bottom equipment vertical view;
Fig. 2 is the utility model one embodiment vertical view;
Fig. 3 is the utility model one embodiment front view.
The specific embodiment
As shown in Figures 2 and 3, the utility model one embodiment comprises two skip buckets 9, is provided with dress ore deposit section track 3 in the described inclined shaft, and two orbits 6 of described dress ore deposit section track 3 by an electronic bilateral turnout 4 and described two skip buckets, one of 7 are connected; On the described skip bucket orbit 6,7 detector 5 is housed respectively, after the detector on No. 1 skip bucket orbit 6 detects No. 1 up passing through of skip bucket, send signal and give electronic bilateral turnout, bilateral turnout changes, transfer to and connect skip bucket dress ore deposit section track and No. 2 skip bucket orbits 7, make No. 2 descending skip buckets can enter skip bucket dress ore deposit section track.On the contrary, when the detector on No. 2 skip bucket orbits 7 detect No. 2 skip buckets up by after send signal and give electronic bilateral turnout, bilateral turnout changes, and transfers to connecting skip bucket dress ore deposit section track and No. 1 skip bucket orbit 6.The inclined shaft of top, section track 3 skip loading positions, described dress ore deposit is connected with a drop shaft 1, and a suit ore deposit device 2 is fixedly arranged at described drop shaft 1 bottom, and described drop shaft is connected by the dress ore deposit device that is fixed on described drop shaft bottom with described inclined shaft; Described skip bucket moves up and down along described dress ore deposit section track 3 and orbit separately.
Dress ore deposit device is installed in the drop shaft bottom, is used for to skip bucket dress ore deposit, and can be that vibration ore dumping machine also can be to the ore deposit gate.
Electronic bilateral turnout is provided with electrically operated derailleur 8, electrically operated derailleur 8 bases
The signalizing activity that detector 5 sends makes track switch connect the orbit of skip bucket dress ore deposit section track and No. 1 skip bucket or No. 2 skip buckets.
After No. 1 skip bucket goes downwards to dress section track 3 skip loading positions, ore deposit, shaft bottom, skip bucket stops descending, dress ore deposit device 2 is opened, with the ore of 1 li of the drop shaft skip bucket of packing into No. 1, dress ore deposit device 2 was closed after No. 1 skip bucket was filled ore, it is up that No. 1 skip bucket begins, and low speed jerking motion continues upwards to run to No. 1 skip bucket orbit 6 with normal speed after by electronic bilateral turnout 4 again.When detecting No. 1 skip bucket, No. 1 up detector 5 of skip bucket upwards sends signal after the operation, electrically operated derailleur is controlled electronic bilateral turnout 4 actions, skip bucket is adorned ore deposit section track 3 be connected with No. 2 skip bucket orbits 7, be convenient to No. 2 descending skip buckets and enter skip bucket dress ore deposit section track 3 by electronic bilateral turnout 4.After No. 2 skip buckets go downwards to dress section track 3 skip loading positions, ore deposit, shaft bottom, skip bucket stops descending, dress ore deposit device 2 is opened, with the ore of 1 li of the drop shaft skip bucket of packing into No. 2, dress ore deposit device 2 was closed after No. 2 finished in skip bucket dress ore deposit, No. 2 upwards operations of skip bucket, when detecting No. 2 skip buckets, the up detector 5 on No. 2 skip bucket orbits upwards sends signal after the operation, electrically operated derailleur is controlled electronic bilateral turnout 4 actions, skip bucket is adorned ore deposit section track be connected with No. 1 skip bucket track, get ready for No. 1 descending skip bucket enters dress ore deposit, shaft bottom section track 3.So go round and begin again, realized that 1 drop shaft, 1 suit ore deposit device are to two inclined shaft skips dress ore deposits.

Claims (2)

1. dress ore deposit, double-loop pattern inclined shaft shaft bottom equipment comprises two skip buckets, it is characterized in that, described inclined shaft shaft bottom is provided with dress ore deposit section track, and described dress ore deposit section track alternately is connected with two orbits of described two skip buckets by a track switch; Top, section track skip loading position, described dress ore deposit is provided with a drop shaft, and described drop shaft is connected by the dress ore deposit device that is fixed on described drop shaft bottom with described inclined shaft; Described skip bucket moves up and down along described dress ore deposit section track and orbit separately.
2. dress ore deposit, double-loop pattern inclined shaft shaft bottom according to claim 1 equipment is characterized in that described track switch is electronic bilateral turnout, and described electronic bilateral turnout is provided with electrically operated derailleur, and described skip bucket orbit is provided with detector.
CN 201320038882 2013-01-24 2013-01-24 Double-skip inclined shaft bottom ore loading device Expired - Fee Related CN203035255U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320038882 CN203035255U (en) 2013-01-24 2013-01-24 Double-skip inclined shaft bottom ore loading device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320038882 CN203035255U (en) 2013-01-24 2013-01-24 Double-skip inclined shaft bottom ore loading device

Publications (1)

Publication Number Publication Date
CN203035255U true CN203035255U (en) 2013-07-03

Family

ID=48687388

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320038882 Expired - Fee Related CN203035255U (en) 2013-01-24 2013-01-24 Double-skip inclined shaft bottom ore loading device

Country Status (1)

Country Link
CN (1) CN203035255U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109533842A (en) * 2018-12-19 2019-03-29 远安县燎原矿业有限责任公司 A kind of drop shaft formula ore storage bin automatic assembling and disassembling system and handling method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109533842A (en) * 2018-12-19 2019-03-29 远安县燎原矿业有限责任公司 A kind of drop shaft formula ore storage bin automatic assembling and disassembling system and handling method

Similar Documents

Publication Publication Date Title
CN201810342U (en) Dump crane
CN104653182B (en) A kind of coal-mining method that the bastard coal of coal seam containing thick dirt band point is adopted
CN201496069U (en) Bridge type transfer machine with large span
CN203035255U (en) Double-skip inclined shaft bottom ore loading device
CN105821775A (en) Construction method for using cable crane for overturning arch bridge arch rib
CN102619242A (en) Flat-pushing type flat bucket material discharging mechanism
CN207209790U (en) A kind of cantilever crane of stable operation
CN202788899U (en) Large-swing beam structured top coal caving hydraulic support
CN203531952U (en) Skip bucket well ore rock separate-loading and separate-carrying system
CN104500072B (en) Mineral transport automatic butt joint system
CN201486593U (en) Inclined well slag digging machine
CN201627596U (en) Transverse self-advancing combined suspension hydraulic support
CN105923541B (en) The handling apparatus and rock tunnel(ling) machine of rock tunnel(ling) machine
CN201416458Y (en) Slag-raking machine of slant well
CN107686012A (en) A kind of conveying device
CN205078302U (en) Scrape board -like waste rock conveyor under skip shaft
CN205820665U (en) Underground mine vertical shaft bottom-dump skip promotes system
CN203476334U (en) Self-moving type transshipping machine for mining working face for open-pit mine
CN207332878U (en) Slusher machine is unloaded goods device
CN201416456Y (en) Slag-raking machine of slant well
CN203685189U (en) Working face tower type transfer conveyor for an open-pit mine
CN109823868A (en) A kind of coal mine twin-skip divides storage system automatically
CN207451030U (en) A kind of multiple spot for mine multi-rope friction hoisting vertical shaft fills ore deposit ore discharging apparatus
CN202768002U (en) Large dip angle rail slope structure for assisting main tunnel construction
CN204802849U (en) Hang hopper mode device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130703

Termination date: 20200124

CF01 Termination of patent right due to non-payment of annual fee