CN202969388U - Elimination system of pile position hole bottom sediments - Google Patents

Elimination system of pile position hole bottom sediments Download PDF

Info

Publication number
CN202969388U
CN202969388U CN 201220588753 CN201220588753U CN202969388U CN 202969388 U CN202969388 U CN 202969388U CN 201220588753 CN201220588753 CN 201220588753 CN 201220588753 U CN201220588753 U CN 201220588753U CN 202969388 U CN202969388 U CN 202969388U
Authority
CN
China
Prior art keywords
communicated
valve
mud
sedimentation basin
pile position
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220588753
Other languages
Chinese (zh)
Inventor
焦安亮
黄延铮
史少博
陈磊
张煜
李阳
周支军
陈致昂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN 201220588753 priority Critical patent/CN202969388U/en
Application granted granted Critical
Publication of CN202969388U publication Critical patent/CN202969388U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses an elimination system of pile position hole bottom sediments, which comprises a sedimentation basin. The sedimentation basin is communicated with a mud pit; the mud pit is provided with a mud pump; the mud pump is provided with two mud ditches, one mud ditch is connected with a first valve, while the other mud ditch is connected with a second valve; the mud ditch on the first valve is communicated with a pile position; the mud ditch which is communicated with the second valve is also provided with two ditches, one ditch is communicated with the pile position, while the other ditch is communicated with a reverse circulation pump by a third valve; the reverse circulation pump is communicated with the sedimentation basin; and the pile position is communicated with the sedimentation basin. According to the utility model, each of the valves is opened selectively, the pile position hole bottom sediments are disturbed through direct circulation and reverse circulation, so that the accumulated sediments are changed into loose particles, and then the hole bottom sediments are easy to eliminate. The elimination system of the pile position hole bottom sediments is beneficial to the acceleration of a construction progress.

Description

Sediment removal system at the bottom of hole, stake position
Technical field
The utility model belongs to the realm of building construction, the system of sediment at the bottom of hole, cleaning stake position when being specifically related to a kind of basement pile anchoring.
Background technology
In building construction process, often need to build basement to increase land use area, conveniently stop etc.Before Construction of Basement, need at first buried stake.Need at first to punch before pile anchoring, and sediment at the bottom of the hole is removed clean.Under common geologic condition, the removing of sediment is more convenient.But cobble, middle weathering core and Dou Yan are contained in some zone in bottom, and the sand factor between each rock stratum is up to 12% ~ 15%, and the construction hole depth reaches 72m the most deeply, and the sediment at the bottom of hole, stake this moment position is difficult to remove, and affects the progress of engineering.
The utility model content
The purpose of this utility model is for above-mentioned the deficiencies in the prior art, and sediment removal system at the bottom of hole, a kind of position is provided, and the sediment at the bottom of the hole can be become bulk granular and discharge.
the technical solution of the utility model realizes in the following manner: at the bottom of hole, a kind of position, sediment is discharged system, comprise sedimentation basin, sedimentation basin is communicated with mud pit, be provided with slush pump in mud pit, be divided into two-way from slush pump mud ditch out, wherein be connected with on the way the first valve, separately be connected with on the way the second valve, mud ditch on the first valve is communicated with a position, the mud ditch that communicates with the second valve is divided into again two-way, wherein one the tunnel is communicated with a position, another road is communicated with inverse circulation pump by the 3rd valve, inverse circulation pump is communicated with sedimentation basin, the stake position is communicated with sedimentation basin.
The utility model carries out disturbance with positive and negative circulation to bottom, stake position sediment by optionally opening each valve, makes the sediment that accumulates in together become the particle of loose shape, and at the bottom of the hole, sediment is easily discharged like this.The utility model is conducive to accelerating construction progress.
Description of drawings
Fig. 1 is that the utility model uses state one schematic diagram.
Fig. 2 is that the utility model uses state two schematic diagrames.
Fig. 3 is that the utility model uses state three schematic diagrames.
The specific embodiment
As shown in drawings, at the bottom of hole, a kind of position, sediment is discharged system, comprise sedimentation basin 1, sedimentation basin 1 is communicated with mud pit 2, be provided with slush pump 3 in mud pit 2, be divided into two-way from slush pump 3 mud ditch out, wherein be connected with on the way the first valve 4, separately be connected with on the way the second valve 5, mud ditch on the first valve 4 is communicated with a position 8, the mud ditch that communicates with the second valve 5 is divided into again two-way, wherein one the tunnel is communicated with stake position 8, another road is communicated with inverse circulation pump 7 by the 3rd valve 6, inverse circulation pump 7 is communicated with sedimentation basin 1,8 are communicated with sedimentation basin 1.
The utility model use procedure is as follows: at first close the second valve 5 and the 3rd valve 6, open the first valve 4, utilize proportion at 1.20 ~ 1.25 mud, the suspension sediment of large particle diameter to be removed, this circulation is approximately after 20 minutes, close the first valve 4, open the second valve 5 and the 3rd valve 6, allow mud be full of slurry pipeline and open inverse circulation pump 7 afterwards, close the second valve 5, open the 3rd valve 6, carry out anti-circulation cleaning hole.Carry out the several reverse circulation in the process of anti-circulation cleaning hole and combine, allow mud form at the bottom of 8 holes, stake position and liquidate, stir sediment, reach the purpose of the less sediment of smooth discharge.

Claims (1)

1. sediment removal system at the bottom of hole, a stake position, comprise sedimentation basin (1), sedimentation basin (1) is communicated with mud pit (2), be provided with slush pump (3) in mud pit (2), it is characterized in that: be divided into two-way from slush pump (3) mud ditch out, wherein be connected with on the way the first valve (4), separately be connected with on the way the second valve (5), mud ditch on the first valve (4) is communicated with stake position (8), the mud ditch that communicates with the second valve (5) is divided into again two-way, wherein one the tunnel is communicated with stake position (8), another road is communicated with inverse circulation pump (7) by the 3rd valve (6), inverse circulation pump (7) is communicated with sedimentation basin (1), stake position (8) is communicated with sedimentation basin (1).
CN 201220588753 2012-11-09 2012-11-09 Elimination system of pile position hole bottom sediments Expired - Fee Related CN202969388U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220588753 CN202969388U (en) 2012-11-09 2012-11-09 Elimination system of pile position hole bottom sediments

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220588753 CN202969388U (en) 2012-11-09 2012-11-09 Elimination system of pile position hole bottom sediments

Publications (1)

Publication Number Publication Date
CN202969388U true CN202969388U (en) 2013-06-05

Family

ID=48510482

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220588753 Expired - Fee Related CN202969388U (en) 2012-11-09 2012-11-09 Elimination system of pile position hole bottom sediments

Country Status (1)

Country Link
CN (1) CN202969388U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107952760A (en) * 2017-12-28 2018-04-24 辽宁三三工业有限公司 Mud channel sediment pulse cleaning system
CN109114004A (en) * 2018-10-24 2019-01-01 林玉瑶 Two-way borehole cleaning mud pump apparatus

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107952760A (en) * 2017-12-28 2018-04-24 辽宁三三工业有限公司 Mud channel sediment pulse cleaning system
CN107952760B (en) * 2017-12-28 2023-10-13 辽宁三三工业有限公司 Mud pipeline sediment pulse cleaning system
CN109114004A (en) * 2018-10-24 2019-01-01 林玉瑶 Two-way borehole cleaning mud pump apparatus

Similar Documents

Publication Publication Date Title
CN102774896B (en) Integral purification device and method for particles in rain and sewage
CN104452656B (en) A kind of river course segmentation Dredging Construction method
CN104174191A (en) Integrated grit chamber for treating rainwater and treatment method
CN101705680B (en) Construction method of stock dump capable of accelerating dehydration and drying process of dredging deposited sludge
CN205063005U (en) Can carry out novel rainwater well that compensates to groundwater
CN108999179A (en) The method of vacuum pre-pressed joint microorganism sand fixing technology reinforcing soft soil foundation
CN202969388U (en) Elimination system of pile position hole bottom sediments
CN204952530U (en) Modified fertilizer production dust removal water tank
CN203374227U (en) Direct circulation hole-cleaning device
CN203173911U (en) Precipitation device
CN112983425B (en) Jet flow scouring type stripping-collecting device for seabed semi-buried nodule and collecting method thereof
CN204625447U (en) A kind of artificial wet land system
CN205182284U (en) Gravity type valveless filter
CN202249851U (en) Reverse circulation hole forming equipment for cast-in-place pile
CN204447424U (en) A kind of architectural engineering groundwater treatment and reclamation set
CN203989972U (en) Integrated grit chamber for treating rainwater
CN207727748U (en) A kind of rainwater energy dissipation tank with processing function
CN207846625U (en) A kind of biology delaying basin
CN203374314U (en) Non-plugging auxiliary mine drainage system
CN206438508U (en) Split type quick hole cleaning device
CN202055248U (en) Pile foundation mud pit
CN201614592U (en) Device capable of separating mud in piling
CN205077478U (en) Drainage structures for soft soil foundation
CN209144964U (en) A kind of efficient rainwater isolation collection device
CN203382577U (en) Combined construction type grille aerated grit chamber

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130605