CN202882947U CN2012205507856U CN201220550785U CN202882947U CN 202882947 U CN202882947 U CN 202882947U CN 2012205507856 U CN2012205507856 U CN 2012205507856U CN 201220550785 U CN201220550785 U CN 201220550785U CN 202882947 U CN202882947 U CN 202882947U
Authority
CN
China
Prior art keywords
lining
blocking head
trolley
stopper
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012205507856U
Other languages
Chinese (zh)
Inventor
史赵鹏
闫志刚
雷军
赵香萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority to CN2012205507856U priority Critical patent/CN202882947U/en
Application granted granted Critical
Publication of CN202882947U publication Critical patent/CN202882947U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to the field of pouring tunnel double-lining concrete, in particular to a tunnel double-lining concrete trolley blocking head formwork reinforcing structure which solves the problem that an existing blocking head template is unreasonable in support, serious in formwork shifting, faulting in slab ends of lining slab joints after form removal and unable to be used repeatedly. The tunnel double-lining concrete trolley blocking head formwork reinforcing structure comprises an annular fixed frame annularly fixed tightly attached to the edge of an arc ring mould of a lining trolley, wherein a clamping gap for a blocking head formwork is reversed between the annular fixed frame and the lining trolley. The tunnel double-ling concrete trolley blocking head formwork reinforcing structure further comprises steel tube support beams annularly fixed on the lining trolley at intervals, a reinforcing steel bar where an end of the blocking head formwork is inserted and a reinforcing inclined support abutting against the inner side of the blocking head formwork. When the tunnel lining trolley constructs, the formwork reinforcing structure enables the blocking head formwork to be convenient, quick, stable, safe and reliable to operate and enables a double-lining blocking head formwork to be reasonable and firm. The tunnel double-lining concrete trolley blocking head formwork reinforcing structure is integrated with a trolley, can be used repeatedly, quickens construction speed, saves material cost and improves construction safety and structural stability.

Description

A kind of tunnel double-lining concrete chassis stopper formwork reinforcement structure
Technical field
The utility model relates to tunnel double-lining concreting field, is specially a kind of tunnel double-lining concrete chassis stopper formwork reinforcement structure.
Background technology
Country rock is ever-changing behind the tunnel excavation, for supporting after in time satisfying fast tunnel excavation becomes circulating application worker requirement, prevent that the tunnel from caving in, must catch Best Times to finish the supporting Cheng Huan of the rear weak surrounding rock of excavation, behind excavation, original country rock equilibrium state is broken, peripheral rock and vault have produced plasticity variation and lax, in order to stop by the over-travel of the country rock after the excavation disturbance and distortion, reduce and sink and convergence, must there be rational supporting and protection structure to retrain the pressure that bears country rock.Traditional method is to use the bow member supporting, set anchor tube (bar), hang reinforced mesh, concrete spraying support, after just finishing, and then will construct two the lining concrete, just can finish the last supporting in tunnel, as the tunnel contour moulding form, the termination adopts the stopper wooden form to reinforce, because the tunnel is longer by lining trolley (generally long 12m) in two lining concretings, whenever build the 12m that advances, will dismantle once the stopper template, reinforce again once when building next plate, repeat above operation until tunnel double-lining is finished.Stopper formwork reinforcement speed, quality, be directly to affect in speed of application, the concreting operation under pressure, the distortion of trolley formwork toe-in causes liner plate seam faulting of slab ends, and the tunnel plate sews up smooth-going success or failure.
Traditional method is, after chassis was in place, stopper template from bottom to top annular was reinforced, and supports while reinforcing, after the form removal, the stopper template does not reach recycling, causes the wooden form waste, and the activity duration is long, and the stopper shuttering supporting is unreasonable, the race mould is serious, and liner plate seam faulting of slab ends must repairing could satisfy the planeness requirement after the form removal.
Summary of the invention
The utility model is unreasonable in order to solve existing stopper shuttering supporting, runs mould serious, and liner plate seam faulting of slab ends after the form removal, and the problem that can't reuse provide a kind of tunnel double-lining concrete chassis stopper formwork reinforcement structure.
The utility model is to adopt following technical scheme to realize: a kind of tunnel double-lining concrete chassis stopper formwork reinforcement structure, comprise and be close to lining trolley arch ring mould edge ring to fixing annular fixing frame, reserve the fixing gap of stopper template between annular fixing frame and the lining trolley, also comprise spacer ring and insert the reinforcing bar retainer ring of laying and the reinforcing diagonal brace that holds out against with stopper template inboard to the steel pipe support beam, the confession stopper form stop that are fixed on the lining trolley.Adopt structure design of the present utility model, stopper template one end and splash guard hold out against, in the fixing gap between one end insertion annular fixing frame and the lining trolley, the steel pipe support beam that arranges can be played the reinforcement supporting role, reinforcing bar retainer ring and reinforcing diagonal brace play auxiliary reinforcement effect.
Be provided with timber wedge between described stopper template and the annular fixing frame, can further lock template.
The added pile platform that is provided with of described steel pipe support beam, the pile platform outside is hung with safety guard net, can be placed on after the form removable on the pile platform, and safety guard net can guarantee construction safety simultaneously.
Compared with prior art, when the utility model provides a kind of tunnel double-lining chassis construction, the stopper template is easy, rapid, firm, the reliable formwork reinforcement structure of job safety, make two lining stopper templates more reasonable, more firm, form integral body with chassis, and can reuse, can guarantee that physical dimension meets design requirement, under the concrete pressure effect, not cause the distortion of trolley formwork toe-in, cause concrete lining plate seam faulting of slab ends, accelerate speed of application, the economical with materials cost has improved the stability of working security and structure.
Description of drawings
Fig. 1 is front schematic view of the present utility model;
Fig. 2 is lateral view of the present utility model;
Among the figure: the 1-lining trolley; The 2-annular fixing frame; 3-fixes the gap; 4-steel pipe support beam; 5-reinforcing bar retainer ring; 6-reinforces diagonal brace; 7-stopper template; The 8-timber wedge; 9-pile platform; The 10-safety guard net.
The specific embodiment
A kind of tunnel double-lining concrete chassis stopper formwork reinforcement structure, as shown in Figure 1, 2, comprise and be close to lining trolley 1 arch ring mould edge ring to fixing annular fixing frame 2, reserve the fixing gap 3 of stopper template 7 between annular fixing frame and the lining trolley, be provided with timber wedge 8 between stopper template 7 and the annular fixing frame 2, also comprise spacer ring and insert the reinforcing bar retainer ring 5 of laying and the reinforcing diagonal brace 6 that holds out against with stopper template inboard to the steel pipe support beam 4, the confession stopper form stop that are fixed on the lining trolley.The steel pipe support beam 4 added pile platforms 9 that are provided with, the pile platform outside is hung with safety guard net 10.
During concrete the making, the stopper template is comprised of the plank of some thick 50mm, and template length is greater than lining thickness, and every width selects 30 ~ 40cm to be advisable, and is convenient to operation; The steel lining trolley is by factory process, splicing assembles at the scene, walking is moved by rail, behind the measurement and positioning, mounting block head mould plate, build two lining during Concretes generation race moding shapes for not making, adopt the annular fixedly steel pipe of Φ 42mm as annular fixing frame, be close to along the chassis edge ring to being welded and fixed as support, insert the support of laying as the stopper template, install for strengthening supporting, make the steel pipe support beam every 1.2 ~ 1.5m with Φ 80mm steel pipe, squeeze between the annular fixedly steel pipe of Φ 42mm and the stopper template locking with timber wedge; After the form removal stopper template is deposited on the pile platform, reuse next time, for construction safety, the outer side mounting safety guard net of pile platform, in addition, the stopper template is reinforced by reinforcing diagonal brace, and the reinforcing bar retainer ring plays auxiliary reinforcement effect, the stopper template back side can arrange ribs, and the stopper template is played the connection supporting role.

Claims (3)

1. tunnel double-lining concrete chassis stopper formwork reinforcement structure, it is characterized in that comprising and be close to lining trolley (1) arch ring mould edge ring to fixing annular fixing frame (2), reserve the fixing gap (3) of stopper template (7) between annular fixing frame and the lining trolley, also comprise spacer ring and insert the reinforcing bar retainer ring (5) of laying and the reinforcing diagonal brace (6) that holds out against with stopper template inboard to the steel pipe support beam (4), the confession stopper form stop that are fixed on the lining trolley.
2. a kind of tunnel double-lining concrete chassis stopper formwork reinforcement structure according to claim 1 is characterized in that being provided with timber wedge (8) between stopper template (7) and the annular fixing frame (2).
3. a kind of tunnel double-lining concrete chassis stopper formwork reinforcement structure according to claim 1 and 2 is characterized in that the added pile platform (9) that is provided with of steel pipe support beam (4), and the pile platform outside is hung with safety guard net (10).
CN2012205507856U 2012-10-25 2012-10-25 Tunnel double-lining concrete trolley blocking head formwork reinforcing structure Expired - Fee Related CN202882947U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012205507856U CN202882947U (en) 2012-10-25 2012-10-25 Tunnel double-lining concrete trolley blocking head formwork reinforcing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012205507856U CN202882947U (en) 2012-10-25 2012-10-25 Tunnel double-lining concrete trolley blocking head formwork reinforcing structure

Publications (1)

Publication Number Publication Date
CN202882947U true CN202882947U (en) 2013-04-17

Family

ID=48074387

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012205507856U Expired - Fee Related CN202882947U (en) 2012-10-25 2012-10-25 Tunnel double-lining concrete trolley blocking head formwork reinforcing structure

Country Status (1)

Country Link
CN (1) CN202882947U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105065035A (en) * 2015-09-09 2015-11-18 中国铁建大桥工程局集团有限公司 Light pushing-sliding tunnel lining trolley
CN105971631A (en) * 2016-05-03 2016-09-28 中铁隧道集团二处有限公司 Fixture type end formwork containing steel bar arch wall in tunnel and installation method
CN107762536A (en) * 2017-11-02 2018-03-06 中铁四局集团第二工程有限公司 A kind of reinforcement means of new tunnel lining trolley step plug and the plug
CN110593553A (en) * 2019-09-17 2019-12-20 中建八局轨道交通建设有限公司 End template reinforcing apparatus

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105065035A (en) * 2015-09-09 2015-11-18 中国铁建大桥工程局集团有限公司 Light pushing-sliding tunnel lining trolley
CN105971631A (en) * 2016-05-03 2016-09-28 中铁隧道集团二处有限公司 Fixture type end formwork containing steel bar arch wall in tunnel and installation method
CN105971631B (en) * 2016-05-03 2018-02-16 中铁隧道集团二处有限公司 The fixture type end head formwork and installation method of a kind of tunnel arch wall containing reinforcing bar
CN107762536A (en) * 2017-11-02 2018-03-06 中铁四局集团第二工程有限公司 A kind of reinforcement means of new tunnel lining trolley step plug and the plug
CN107762536B (en) * 2017-11-02 2024-03-19 中铁四局集团有限公司 Novel stepped plug of tunnel lining trolley and reinforcing method of plug
CN110593553A (en) * 2019-09-17 2019-12-20 中建八局轨道交通建设有限公司 End template reinforcing apparatus

Similar Documents

Publication Publication Date Title
CN102493341A (en) Construction method for hollow thin-walled high pier non-bracket formwork turnover of railway
CN202882947U (en) Tunnel double-lining concrete trolley blocking head formwork reinforcing structure
CN2893055Y (en) Super high wall body three-section form
CN101818570B (en) Method for constructing girder structure conversion layer of high-rise building
CN104631512A (en) Post-cast strip beam and slab construction method adopting formwork hanging method
CN213710348U (en) Underground station side wall formwork supporting system combined with full support
CN209799969U (en) A integrally lift up cantilever formwork device for quick construction shaft lining cutting
CN211007659U (en) Device for controlling forming of embedded steel plate in concrete column on column surface
CN109869153A (en) The whole of rapid construction vertical shaft lining cutting promotes cantilever form device and construction method
CN202900288U (en) Steel section skeleton combined structure of tunnel minor radius section lining pouring
CN102454292A (en) Supporting steel frame of high altitude large-span cantilever structure mold frame
CN103696567B (en) The construction method of assembling concrete in mass beam is built with Special supporting device
CN204983661U (en) Light steel is framed greatly, integrative -in -place mould support system is decorated in protection that keeps warm
CN102011490B (en) Template supporting construction process of wall after slab for high-rise shear wall structure system
CN108729466B (en) Large formwork supporting method for constructing anchor-free concrete retaining wall
CN204475145U (en) Self-anchored suspension bridge anchoring is across cast-in-place box beam
CN203603462U (en) Post-cast strip beam plate formwork supporting structure
CN216664766U (en) Assembled parapet that cornices
CN109653770A (en) A kind of middle board construction method carried out using original temporary support
CN106639099B (en) Plant-fibre type heat preservation dismounting-free formwork formwork system surface smoothness control method
CN106320662B (en) Decorating outer wall of building ultra-wide concrete wire construction method
CN204608615U (en) Case formwork support structure in a kind of bridge
CN212025941U (en) Cast-in-place concrete structure formwork mounting support frame for steel-concrete composite beam flange plate
CN109854277B (en) Construction method of large-span super-thick tunnel secondary lining structure
CN213359377U (en) Building templates support frame

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130417