CN202881857U CN2012205507803U CN201220550780U CN202881857U CN 202881857 U CN202881857 U CN 202881857U CN 2012205507803 U CN2012205507803 U CN 2012205507803U CN 201220550780 U CN201220550780 U CN 201220550780U CN 202881857 U CN202881857 U CN 202881857U
Authority
CN
China
Prior art keywords
bridge
jack
beam falling
buttress
falls
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012205507803U
Other languages
English (en)
Inventor
穆建廷
雷军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority to CN2012205507803U priority Critical patent/CN202881857U/zh
Application granted granted Critical
Publication of CN202881857U publication Critical patent/CN202881857U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型涉及桥梁施工领域,具体为一种桥梁顶推法施工用落梁装置,解决现有桥梁顶推法施工所用落梁方案极易发生钢桁梁倾覆的问题,包括设置于钢桁梁与桥墩之间的千斤顶矮支垛和位于支座中心线上的落梁高支垛,其中千斤顶矮支垛顶部间隔安装与钢桁梁底部顶紧的落梁千斤顶,所述千斤顶矮支垛和落梁高支垛均是由若干短钢轨纵横交错活动搭设而成的,千斤顶矮支垛底部设有支承垫板,落梁千斤顶顶部与钢桁梁之间设有分配横梁,使得钢桁梁下落更加平稳,不会发生倾覆,结构设计合理,操作简单,省时省力,缩短工期,适用范围广。

Description

桥梁顶推法施工用落梁装置
技术领域
本实用新型涉及桥梁施工领域,具体为一种桥梁顶推法施工用落梁装置。
背景技术
随着我国国民经济的高速发展与建桥技术的逐步提升,高速公路的修建已从路线设计服从桥位选择转到桥位设计服从路线走向上来,而这种设计思路使得现今高速公路上的斜交连续箱梁桥越来越多。顶推法与其他施工方法相比,具有不影响桥位处交通状况、减少施工设备、有利于生产组织、安全可靠和缩短施工工期等优点,因而被广泛采用。
桥梁顶推法就是以千斤顶为动力,对预制好的钢桁梁,借助钢导梁导向,在四氟乙烯板的滑块间,纵或横向推进至设计要求的位置。钢桁梁顶推到位后,落梁成为施工的重中之重,通常钢桁梁总重较重,落梁高差较高,如果落梁方案不当,可能发生钢桁梁倾覆,对桥下行车安全造成重大影响,将造成无法挽回的损失。
发明内容
本实用新型为了解决现有桥梁顶推法施工所用落梁方案极易发生钢桁梁倾覆的问题,提供一种桥梁顶推法施工用落梁装置。
本实用新型是采用如下技术方案实现的:桥梁顶推法施工用落梁装置,包括设置于钢桁梁与桥墩之间的千斤顶矮支垛和位于支座中心线上的落梁高支垛,其中千斤顶矮支垛顶部间隔安装与钢桁梁底部顶紧的落梁千斤顶,所述千斤顶矮支垛和落梁高支垛均是由若干短钢轨纵横交错活动搭设而成的。
所述千斤顶矮支垛底部设有支承垫板,以调整支垛的高度。
所述落梁千斤顶顶部与钢桁梁之间设有分配横梁,通过分配横梁可将各个落梁千斤顶的顶推力平均分配到钢桁梁上,保证钢桁梁在下落过程中不会发生倾覆。
采用本实用新型的结构设计,利用千斤顶矮支垛与落梁高支垛及落梁千斤顶相互配合,在接近设计标高时,落梁千斤顶顶起钢桁梁,拆除一段落梁高支垛,钢桁梁下落至落梁高支垛上,此时再拆除一段千斤顶矮支垛,下放落梁千斤顶,完成一个循环,此后,落梁千斤顶再次顶起钢桁梁,按照上述步骤完成第二个循环,如此往复,直至钢桁梁落至支座的标高处时,落梁千斤顶顶起钢桁梁,安装支座,再将落梁千斤顶落下,支座完全受力,完成落梁过程。
与现有技术相比,采用本实用新型的落梁装置,使得钢桁梁下落更加平稳,不会发生倾覆,结构设计合理,操作简单,省时省力,缩短工期,适用范围广。
附图说明
图1为本实用新型的结构示意图;
图2为本实用新型的俯视图;
图中:1-钢桁梁;2-桥墩;3-千斤顶矮支垛;4-落梁高支垛;5-落梁千斤顶;6-短钢轨;7-支承垫板;8-分配横梁。
具体实施方式
桥梁顶推法施工用落梁装置,如图1、2所示,包括设置于钢桁梁1与桥墩2之间的千斤顶矮支垛3和位于支座中心线上的落梁高支垛4,其中千斤顶矮支垛顶部安装与钢桁梁底部顶紧的落梁千斤顶5,所述千斤顶矮支垛3和落梁高支垛4均是由若干短钢轨6纵横交错活动搭设而成的。千斤顶矮支垛3底部设有支承垫板7。落梁千斤顶5顶部与钢桁梁1之间设有分配横梁8。
下面以工程实例对本实用新型的落梁装置进行详细说明:
    工程概况
京石客运专线石太直通线跨青银高速公路大桥64m双线简支钢桁梁为下承式钢桁架桥,跨径为64m,桁高为12.3m,主桁采用无竖杆三角桁架布置。该桥跨一端为5#墩,另一端为6#台,钢桁梁在6#台后路基上拼装,采用40m长导梁顶推法就位,5#墩大里程旁临时支墩基础为10根φ1.25m的钻孔灌注桩,承台厚1.2m。临时支墩采用钢管桩和加工件拼装,桥墩为13.8m×4m圆端型墩柱,钢桁梁总重1123吨。钢桁梁与青银高速公路斜交71°5′,梁底净高11.6m,落梁高差2.08m。
落梁前的准备工作
(1)50Kg/m钢轨搭设千斤顶矮支垛以及落梁高支垛,用放置于矮支垛上的落梁千斤顶将钢桁梁一端顶起。
(2)拆除滑道,再将钢桁梁放置于位于支座中心线上的落梁高支垛上。
(3)千斤顶、泵站就位。两侧墩台各两台500吨落梁千斤顶和一台高压泵站。
落梁施工
用放置于矮支垛上的落梁千斤顶将钢桁梁一端再次顶起,抽掉落梁高支垛最上面一层钢轨,落梁千斤顶回缩,将钢桁梁放置于位于支座中心线上的落梁高支垛上,完成一个下落循环。5#墩和6#台交替下落,每个桥墩每次下落按15㎝进行控制。接近设计标高时,落梁千斤顶顶起钢桁梁,拆除支座处落梁高支垛,安装支座,落梁千斤顶落下,支座完全受力。测试并调整梁体线形达到设计和规范要求,锚固支座。
严格遵守千斤顶技术规则,起重不超过起重能力,每次起高量不超过活塞高度的四分之三。操作时统一指挥,统一行动,在落梁过程中要使梁的脱空距离保持在1.5cm内,严禁两桥墩同时落梁,通过控制进油压力来确保两台落梁千斤顶受力均匀,且落梁速度一定不要太快,并要均匀下落。随同千斤顶顶升、回缩和落梁垫块的拆除进行随时测量,确保梁底高差控制在设计范围内。

Claims (3)

1.一种桥梁顶推法施工用落梁装置,其特征是包括设置于钢桁梁(1)与桥墩(2)之间的千斤顶矮支垛(3)和位于支座中心线上的落梁高支垛(4),其中千斤顶矮支垛顶部安装与钢桁梁底部顶紧的落梁千斤顶(5),所述千斤顶矮支垛(3)和落梁高支垛(4)均是由若干短钢轨(6)纵横交错活动搭设而成的。
2.根据权利要求1所述的桥梁顶推法施工用落梁装置,其特征是千斤顶矮支垛(3)底部设有支承垫板(7)。
3.根据权利要求1或2所述的桥梁顶推法施工用落梁装置,其特征是落梁千斤顶(5)顶部与钢桁梁(1)之间设有分配横梁(8)。
CN2012205507803U 2012-10-25 2012-10-25 桥梁顶推法施工用落梁装置 Expired - Fee Related CN202881857U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012205507803U CN202881857U (zh) 2012-10-25 2012-10-25 桥梁顶推法施工用落梁装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012205507803U CN202881857U (zh) 2012-10-25 2012-10-25 桥梁顶推法施工用落梁装置

Publications (1)

Publication Number Publication Date
CN202881857U true CN202881857U (zh) 2013-04-17

Family

ID=48073298

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012205507803U Expired - Fee Related CN202881857U (zh) 2012-10-25 2012-10-25 桥梁顶推法施工用落梁装置

Country Status (1)

Country Link
CN (1) CN202881857U (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103290779A (zh) * 2013-06-15 2013-09-11 中南大学 一种桥梁横向防落梁装置
CN103614972A (zh) * 2013-11-06 2014-03-05 中铁二十一局集团第二工程有限公司 钢桁梁纵横向就位调整装置
CN103981809A (zh) * 2014-05-15 2014-08-13 宝鸡中铁宝桥天元实业发展有限公司 中小桥梁桥面支撑落梁方法及专用支撑装置
CN105350457A (zh) * 2015-11-13 2016-02-24 中铁大桥局集团第一工程有限公司 一种桥梁步履式顶推施工中钢槽梁落梁的方法
CN106245529A (zh) * 2016-08-24 2016-12-21 中铁十七局集团有限公司铺架分公司 铁路t形梁安全快速落梁方法
CN107165037A (zh) * 2017-04-11 2017-09-15 中铁十九局集团有限公司 一种落梁装置和落梁施工方法
CN107938521A (zh) * 2017-12-27 2018-04-20 兰州理工大学 一种v型桥墩刚构桥合拢顶推系统
CN110820591A (zh) * 2019-12-04 2020-02-21 中国葛洲坝集团第三工程有限公司 一种可快速拆解的支墩结构及其在钢桁架桥安装中的应用
CN111236083A (zh) * 2020-03-13 2020-06-05 中铁五局集团建筑工程有限责任公司 一种悬吊式钢结构桥梁高位分级落梁装置及其操作方法
CN111501574A (zh) * 2020-05-11 2020-08-07 中交二公局第五工程有限公司 钢板梁s平面线型无导梁分联平行顶推施工方法
CN111778854A (zh) * 2020-05-15 2020-10-16 中交世通(重庆)重工有限公司 一种可用于落梁施工中的钢管混凝土垫块
CN114438904A (zh) * 2021-12-22 2022-05-06 中铁二十五局集团第二工程有限公司 一种大跨度下承式连续钢桁梁顶推工艺

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103290779B (zh) * 2013-06-15 2015-05-20 中南大学 一种桥梁横向防落梁装置
CN103290779A (zh) * 2013-06-15 2013-09-11 中南大学 一种桥梁横向防落梁装置
CN103614972A (zh) * 2013-11-06 2014-03-05 中铁二十一局集团第二工程有限公司 钢桁梁纵横向就位调整装置
CN103614972B (zh) * 2013-11-06 2016-08-17 中铁二十一局集团第二工程有限公司 钢桁梁纵横向就位调整装置
CN103981809A (zh) * 2014-05-15 2014-08-13 宝鸡中铁宝桥天元实业发展有限公司 中小桥梁桥面支撑落梁方法及专用支撑装置
CN103981809B (zh) * 2014-05-15 2016-01-20 宝鸡中铁宝桥天元实业发展有限公司 中小桥梁桥面支撑落梁方法及专用支撑装置
CN105350457A (zh) * 2015-11-13 2016-02-24 中铁大桥局集团第一工程有限公司 一种桥梁步履式顶推施工中钢槽梁落梁的方法
CN106245529B (zh) * 2016-08-24 2018-04-06 中铁十七局集团有限公司铺架分公司 铁路t形梁安全快速落梁方法
CN106245529A (zh) * 2016-08-24 2016-12-21 中铁十七局集团有限公司铺架分公司 铁路t形梁安全快速落梁方法
CN107165037A (zh) * 2017-04-11 2017-09-15 中铁十九局集团有限公司 一种落梁装置和落梁施工方法
CN107938521A (zh) * 2017-12-27 2018-04-20 兰州理工大学 一种v型桥墩刚构桥合拢顶推系统
CN107938521B (zh) * 2017-12-27 2024-04-26 兰州理工大学 一种v型桥墩刚构桥合拢顶推系统
CN110820591A (zh) * 2019-12-04 2020-02-21 中国葛洲坝集团第三工程有限公司 一种可快速拆解的支墩结构及其在钢桁架桥安装中的应用
CN111236083A (zh) * 2020-03-13 2020-06-05 中铁五局集团建筑工程有限责任公司 一种悬吊式钢结构桥梁高位分级落梁装置及其操作方法
CN111501574A (zh) * 2020-05-11 2020-08-07 中交二公局第五工程有限公司 钢板梁s平面线型无导梁分联平行顶推施工方法
CN111501574B (zh) * 2020-05-11 2021-11-09 中交二公局第五工程有限公司 钢板梁s平面线型无导梁分联平行顶推施工方法
CN111778854A (zh) * 2020-05-15 2020-10-16 中交世通(重庆)重工有限公司 一种可用于落梁施工中的钢管混凝土垫块
CN114438904A (zh) * 2021-12-22 2022-05-06 中铁二十五局集团第二工程有限公司 一种大跨度下承式连续钢桁梁顶推工艺

Similar Documents

Publication Publication Date Title
CN202881857U (zh) 桥梁顶推法施工用落梁装置
CN102587291B (zh) 一种钢箱梁步履式多点顶推施工方法及施工系统
CN102080357B (zh) 钢管墩贝雷梁现浇支架整体落梁装置及方法
CN103669226B (zh) 一种跨江预应力混凝土连续梁桥箱梁0#块支架施工方法
CN202492807U (zh) 钢箱梁步履式多点顶推施工系统
CN102477717B (zh) 一种桥梁顶推施工方法
CN102146732A (zh) 超大面积双曲面焊接球网架滑移施工方法
CN103437300A (zh) 墩顶钢梁无墩旁托架架设双悬臂的施工方法
CN109537460B (zh) 一种用于顶推桥梁高位落梁施工方法
CN103233588B (zh) 带筏板基础建筑物的平移方法
CN109778700B (zh) 一种跨越既有道路的现浇槽形梁三点滑移顶推施工方法
CN102786004A (zh) 无缆风绳带载整体移动式液压提升系统及提升方法
CN108221711A (zh) 跨越既有铁路营业线简支系杆拱顶推平转及高位落梁装置
CN107892238B (zh) 一种用于贝雷梁的吊放装置及方法
CN205242238U (zh) 一种应用于自锚式悬索桥的主梁结构
CN201720676U (zh) 大型构件精确调位装置
CN210031458U (zh) 大跨度高度差系杆拱结构顶推机构
CN106012863A (zh) 一种吊装门架及其在异型反对称钢主塔施工中的使用方法
CN203625777U (zh) 可调型轮轨式梁上运梁车
CN108385452B (zh) 一种治理路基沉降的起升调整机构、系统及方法
CN100543228C (zh) 更换铁路道岔施工工艺及道岔换铺设备
CN203715115U (zh) 一种用于门式起重机自提升系统的支撑点结构
CN108342984B (zh) 一种滩涂软弱地基栈桥及其安装沉降方法
CN203099228U (zh) 一种地脚螺栓调平结构
CN206111212U (zh) 一种岩锚梁施工台车

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130417

Termination date: 20201025