CN202792330U - Heat pipe anchor rod air conditioning device - Google Patents

Heat pipe anchor rod air conditioning device Download PDF

Info

Publication number
CN202792330U
CN202792330U CN 201220498247 CN201220498247U CN202792330U CN 202792330 U CN202792330 U CN 202792330U CN 201220498247 CN201220498247 CN 201220498247 CN 201220498247 U CN201220498247 U CN 201220498247U CN 202792330 U CN202792330 U CN 202792330U
Authority
CN
China
Prior art keywords
heat pipe
anchor rod
anchor pole
rod
cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220498247
Other languages
Chinese (zh)
Inventor
管伟明
张东升
刘洪林
陈辉
李虎威
亚尔·买买提
王军党
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang University
Original Assignee
Xinjiang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang University filed Critical Xinjiang University
Priority to CN 201220498247 priority Critical patent/CN202792330U/en
Application granted granted Critical
Publication of CN202792330U publication Critical patent/CN202792330U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a heat pipe anchor rod air conditioning device which comprises an anchor rod, a support plate and a heat pipe. A thread end head is arranged at one end of the anchor rod and the end, provided with a thread end head, of the anchor rod is fixed inwards on the support plate. The other end of the anchor rod is fixed on surrounding rock. A cavity is arranged in the anchor rod. The heat pipe is arranged in the cavity. The heat pipe comprises a rod body, a vacuum cavity body and a liquid absorption core. A mesh-shaped liquid absorption core is arranged in an inner wall of the rod body. The inner portion of the liquid absorption core is the vacuum cavity. The rod body is divided into an evaporation section, a heat insulation section and a condensation section inside. The conductivity coefficient of the anchor rod is 80000 watt per meter per degree. The heat pipe anchor rod air conditioning device is simple in structure, has an anchoring function and meanwhile has a good heat conductive property.

Description

Heat pipe anchor pole aircondition
Technical field
The utility model belongs to the air temp regulator field, relates in particular to mine or tunnel air temperature-adjusting device.
Background technology
The northern area of China winter temperature extremely low (10 ℃--30 ℃), for ensureing operating ambient temperature suitable under the coal mine, " safety regulations in coal mine " regulation mine must be installed air heating system, " guaranteeing that the following air themperature of air inlet is through being everlasting more than 2 C ".The most mine all adopts the heating room to carry out the mine air adjustment, as shown in Figure 2, forms hot air flow 30 after cold wind stream 10 heats through the heating room and enters the down-hole with cold air 20 mixing match.The mode of heating of heating in the room mostly is heat sink format, the origin of heat of these radiators in the boiler room of burning coal, the mode such as use electric heating piece.Because northern China is very long winter, so will produce huge energy consumption, and the problem such as generation environmental pollution.For energy savings consumption reduction, also have at present water source, air source heat pump technology, be about in the underground gushing water, the heat of mine return air in distinguished and admirable enter in the heating system after cementing out by heat pump techniques recycling again.The equal Shortcomings of above technology, 1. the mine air temperature regulation mechanism can only provide heat energy to solve the low problem of Minepit environment temperature in winter, however when summer, the mine ambient temperature was higher, the heating room but can not play the effect of cooling.2. water source heat pump technology can not obtain more heat energy in the little mine of inflow rate of mine water.3. air source heat pump is the heat energy of drawing in the mine return air mostly, but less in temperature and the environment temperature temperature difference outside the mine of mine return air well outlet in summer, then the effect of air source heat pump is just very not obvious.4. the concentration of energy that reclaims can only be arrived certain place when above-mentioned two kinds of heat pump techniques use in mine, and then be delivered to the heating room or be delivered to thermally point of other usefulness of ground, the thermal energy transfer system that this process need is comparatively complicated, and difficulty is transmitted utilization in complicated tunnel, down-hole.
For the problems referred to above, the utility model proposes a large amount of anchor poles that use in down-hole are made into heat pipe anchor pole form, fully absorb in the winter time the heat from subterranean strata, reach the purpose that helps the tunnel to heat up; Absorb the heat of air in the tunnel in summer, reach the purpose of cooling down, can save mass energy.
The utility model content
The technical problems to be solved in the utility model is to overcome existing defective, and a kind of heat pipe anchor pole aircondition of simple in structure, good heat conductivity is provided.
In order to solve the problems of the technologies described above, the utility model provides following technical scheme:
Heat pipe anchor pole aircondition, comprise anchor pole, supporting plate, heat pipe, described anchor pole one end is provided with threaded end, the end that described anchor pole is provided with threaded end inwardly is fixed on the supporting plate, and the described anchor pole other end is fixed in country rock, is provided with cavity in the described anchor pole, in the described cavity heat pipe is installed, described heat pipe comprises the body of rod, vacuum cavity, liquid-sucking core, and described body of rod inwall is equipped with netted liquid-sucking core, and described liquid-sucking core inside is vacuum cavity.
Be divided into evaporator section, adiabatic section, condensation segment in the described body of rod.
The coefficient of conductivity of described anchor pole is 80000W/ (m ℃).
Compared with prior art, the utlity model has following beneficial effect:
The utility model heat pipe anchor structure is simple, the on-the-spot simple installation in the down-hole, take full advantage of the down-hole everywhere visible anchor pole be aircondition, the temperature of directly regulating air under the mine, efficient are relatively higher.According to the temperature difference of atmospheric temperature and zone of constant temperature, stratum, use the heat pipe anchor pole of coefficient of conductivity 80000W/ (m ℃), automatically regulate the temperature in the mine, reach adjusting purpose cool in summer and warm in winter, reduced the consumption of the energy.Utilize the shallow surface thermal source no matter all applicable at the mine of condition.
Description of drawings
Fig. 1 is the operation principle schematic diagram of existing heat pipe;
Fig. 2 is the schematic diagram in heating room;
Fig. 3 is the installation diagram of the utility model heat pipe anchor pole aircondition;
Fig. 4 is the structural representation of the utility model heat pipe anchor pole;
The specific embodiment
Below in conjunction with accompanying drawing preferred embodiment of the present utility model is described, should be appreciated that preferred embodiment described herein only is used for description and interpretation the utility model, and be not used in restriction the utility model.
Such as Fig. 1, Fig. 3, shown in Figure 4, heat pipe anchor pole aircondition comprises anchor pole, supporting plate 1, heat pipe 3, is provided with threaded end 2 at anchor pole one end, passes supporting plate and is fixed on the supporting plate 1, and the anchor pole other end is fixed on the country rock 12 in tunnel or the tunnel.The coefficient of conductivity of anchor pole is 80000W/ (m ℃).Be provided with cavity in the anchor pole, heat pipe 3 is installed in this cavity, heat pipe 3 comprises the body of rod 4, vacuum cavity 5, liquid-sucking core 6, and the body of rod 4 inwalls are equipped with netted liquid-sucking core 6, and liquid-sucking core 6 inside are vacuum cavity 5.Be divided into evaporator section 7, adiabatic section 8, condensation segment 9 in the body of rod 4.Heat pipe package adopts metal tube, and shut at the heat pipe shell two ends, shuts frontly will to vacuumize in the pipe first, pours into an amount of working solution 11.
The winter environment temperature is lower than zone of constant temperature, stratum temperature, the end of heat pipe anchor pole in casing working solution 11 evacuator bodies that are heated move to tunnel 13 1 ends along anchor pole, when its heat after cold air absorbs in by the tunnel, the working solution condensation becomes liquid, under the effect of liquid-sucking core, get back to an end in the rock stratum, again be subjected to thermal evaporation, constantly circulation is taken the heat in the rock stratum in the tunnel to, reaches the purpose of heating tunnel air.
In summer, environment temperature is higher than zone of constant temperature, stratum temperature, the be heated hydraulic fluid evaporation of the end of heat pipe anchor pole in the tunnel moves to an end in the rock stratum along anchor pole, after its heat is absorbed by the rock stratum, working solution is condensate under the effect of liquid-sucking core and gets back to an end in the tunnel, again be subjected to thermal evaporation, constantly circulation in the rock stratum, reaches the purpose of cooling tunnel air with the transfer of heat in the tunnel.
The utility model is intended to heat pipe for thermal conductivity technology and anchor pole are combined, so that anchor pole not only has anchorage effect, also has simultaneously good heat conductivility, regulates temperature for mine, has realized heating winter the refrigeration in summer, can save mass energy.
The above only is explanation embodiment of the present utility model; be not limited to the utility model; for a person skilled in the art; all within spirit of the present utility model and principle; any modification of doing, be equal to replacement, improvement etc., all should be included within the protection domain of the present utility model.

Claims (3)

1. heat pipe anchor pole aircondition, it is characterized in that: comprise anchor pole, supporting plate, heat pipe, described anchor pole one end is provided with threaded end, the end that described anchor pole is provided with threaded end inwardly is fixed on the supporting plate, and the described anchor pole other end is fixed in country rock, is provided with cavity in the described anchor pole, in the described cavity heat pipe is installed, described heat pipe comprises the body of rod, vacuum cavity, liquid-sucking core, and described body of rod inwall is equipped with netted liquid-sucking core, and described liquid-sucking core inside is vacuum cavity.
2. heat pipe anchor pole aircondition as claimed in claim 1 is characterized in that: be divided into evaporator section, adiabatic section, condensation segment in the described body of rod.
3. heat pipe anchor pole aircondition as claimed in claim 1, it is characterized in that: the coefficient of conductivity of described anchor pole is 80000W/ (m ℃).
CN 201220498247 2012-09-26 2012-09-26 Heat pipe anchor rod air conditioning device Expired - Fee Related CN202792330U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220498247 CN202792330U (en) 2012-09-26 2012-09-26 Heat pipe anchor rod air conditioning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220498247 CN202792330U (en) 2012-09-26 2012-09-26 Heat pipe anchor rod air conditioning device

Publications (1)

Publication Number Publication Date
CN202792330U true CN202792330U (en) 2013-03-13

Family

ID=47819584

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220498247 Expired - Fee Related CN202792330U (en) 2012-09-26 2012-09-26 Heat pipe anchor rod air conditioning device

Country Status (1)

Country Link
CN (1) CN202792330U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103062854A (en) * 2012-09-26 2013-04-24 新疆大学 Heat pipe anchor rod air conditioning device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103062854A (en) * 2012-09-26 2013-04-24 新疆大学 Heat pipe anchor rod air conditioning device
CN103062854B (en) * 2012-09-26 2016-08-03 新疆大学 Heat pipe anchor rod air-conditioning device

Similar Documents

Publication Publication Date Title
CN110455099A (en) A kind of pile foundation pipe laying earth source heat pump double pipe heat exchanger
CN104236165A (en) Solar energy storage cold and heat source wind energy tower heat pump system
CN103062854B (en) Heat pipe anchor rod air-conditioning device
CN106152334A (en) A kind of for subway tunnel inner capillary tube wall heat exchanger
CN202792330U (en) Heat pipe anchor rod air conditioning device
CN202066108U (en) Solar heat conducting heating device
CN103912999A (en) Phase-change heat storage solar water heater with novel heat dissipation structure
CN203478600U (en) Novel air-energy water heater device
CN203413847U (en) Phase change heat storage solar water heater with overheat protection device
CN203177290U (en) Vacuum tube solar energy and terrestrial heat complementation combined type heat supply system
CN204043241U (en) Solar energy accumulation Cooling and Heat Source wind-energy tower heat pump
CN203464510U (en) Household solar energy circulatory temperature-regulating system
CN205300021U (en) Novel absorption formula refrigerating system of solar project pipe thermal -arrest
CN204535158U (en) A kind of for solar water heater new heat pipe defroster
CN103307782A (en) Phase-change heat-accumulation solar water heater provided with overheating protection device
CN209147317U (en) A kind of earth's surface heat energy water air-conditioning
CN203177291U (en) Heating system with light board solar energy and terrestrial heat combined complementarily
CN206504390U (en) A kind of air source heat pump ceiling radiant heating plant
CN105937814A (en) Building passive cooling and solar hot water comprehensive utilization device
CN206581334U (en) It is a kind of based on solar powered intelligent air water drawing device
CN203489521U (en) Solar energy and ground source heat pump combined energy saving system
CN203083012U (en) Solar heat storage system
CN205783245U (en) A kind of solar energy, air can ground source heating cooling systems
CN203595172U (en) Solar auxiliary heating device based on oscillation heat pipe technique
CN202470537U (en) Novel city cold and heat united supply device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130313

Termination date: 20140926

EXPY Termination of patent right or utility model