CN202766970U - Cast-in-place outer vertical face seamless seal anchor structure - Google Patents

Cast-in-place outer vertical face seamless seal anchor structure Download PDF

Info

Publication number
CN202766970U
CN202766970U CN201220464834.4U CN201220464834U CN202766970U CN 202766970 U CN202766970 U CN 202766970U CN 201220464834 U CN201220464834 U CN 201220464834U CN 202766970 U CN202766970 U CN 202766970U
Authority
CN
China
Prior art keywords
cast
sealing
covering anchorage
vertical face
outer vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201220464834.4U
Other languages
Chinese (zh)
Inventor
袁威
朱长亮
刘永福
刘从雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Roads & Bridges Co Ltd Of Cccec
Original Assignee
Roads & Bridges Co Ltd Of Cccec
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Roads & Bridges Co Ltd Of Cccec filed Critical Roads & Bridges Co Ltd Of Cccec
Priority to CN201220464834.4U priority Critical patent/CN202766970U/en
Application granted granted Critical
Publication of CN202766970U publication Critical patent/CN202766970U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a cast-in-place outer vertical face seamless seal anchor structure which comprises a box beam provided with an anchor port and a seal anchor template which is attached to the box beam through a plurality of tie pieces and covers the anchor port. A sleeve communicated with the anchor port is embedded at the top of the box beam, and a vibration rod is inserted into the sleeve. By means of a concentrator, the cast-in-place outer vertical face seamless seal anchor structure with strong uniformity between seal anchor concrete and an outer vertical face of whole box beam concrete is achieved. The cast-in-place outer vertical face seamless seal anchor structure has the advantages of avoiding manual filling decoration and being seamless and attractive.

Description

The outer seamless sealing off and covering anchorage structure of facade of Cast-in-situ Beam
Technical field
The utility model relates to a kind of sealing off and covering anchorage structure, the outer seamless sealing off and covering anchorage structure of facade of espespecially a kind of Cast-in-situ Beam.
Background technology
In bridge on highway, Urban Bridge and railroad bridge now; More use the prestressed concrete cast-in-situ box girder.Using in large quantities prestressing force is a trend of bridge development, but problem is that Cast-in-situ Beam is after using prestressing force, and particularly after using transverse prestress, its anchor mouth position is located at the outer facade of case beam often.Traditional sealing off and covering anchorage technique is to establish the concrete casting orifice in the upper end of sealing off and covering anchorage template, then can cause the template of sealing off and covering anchorage mouth can't once stand the top, from long-term Construction practices, this kind sealing off and covering anchorage method is vibrated because concrete can't adopt vibrating head, can only adopt artificial simple tamping, be difficult to guarantee the concrete quality of sealing off and covering anchorage; And since the template of sealing off and covering anchorage once Zhi Li put in place, need to reserve concrete pouring gate, its manually shutoff of sprue gate topmost, the concrete of sealing off and covering anchorage is difficult to accomplish smooth closely knit like this, the outer facade of whole case beam is difficult to keep apparent uniformity, have larger repairing vestige, there are larger defective in this and the bridge fair-faced concrete outward appearance that requires now.
Summary of the invention
The purpose of this utility model is to overcome the defective of prior art, and provide the seamless sealing off and covering anchorage structure of facade outside a kind of Cast-in-situ Beam, realized the outer seamless sealing off and covering anchorage structure of facade of Cast-in-situ Beam that the outer facade uniformity of a kind of sealing off and covering anchorage concrete and whole box beam concrete is strong, have and need not manually to fill up modification, seamless advantage attractive in appearance.
The technical scheme that realizes above-mentioned purpose is:
The outer seamless sealing off and covering anchorage structure of facade of a kind of Cast-in-situ Beam of the present utility model, comprise the case beam that offers the anchor mouth and by fit described case beam and cover the sealing off and covering anchorage template of described anchor mouth of a plurality of lacing wires, the sleeve pipe that a plurality of and described anchor mouth is communicated with is buried at the top of described case beam underground; Be inserted with respectively a vibrating head in the described sleeve pipe.
Described case beam upper surface is given prominence in the upper end of above-mentioned sleeve pipe, and the lower end of described sleeve pipe is charged in the described anchor mouth.
Above-mentioned sleeve pipe is bellows.
The utility model has been owing to adopted above technical scheme, makes it have following beneficial effect to be:
Because the employing of the sleeve pipe that is communicated with the anchor mouth of case beam, thereby realize anchor mouth concreting from case back section, need not on the sealing off and covering anchorage template, to offer in addition plug hole, realized case beam outward flat appearance and the uniformity of facade, need not to carry out follow-up repair procedure; The simultaneously employing owing to sleeve pipe can realize inserting the automatic stirring that vibrating head is realized mixed earth, thereby has reduced constructor's labour intensity, has guaranteed the mixing quality of mixed earth, has improved the efficiency of construction of engineering.
Description of drawings
Fig. 1 is the structural representation of the outer seamless sealing off and covering anchorage structure of facade of the utility model Cast-in-situ Beam.
The specific embodiment
The utility model is described in further detail below in conjunction with specific embodiment.
See also Fig. 1, the outer seamless sealing off and covering anchorage structure of facade of a kind of Cast-in-situ Beam of the present utility model, comprise the case beam 1 that offers anchor mouth 11 and by a plurality of lacing wire 2 applying case beams 1 and cover the sealing off and covering anchorage template 3 of anchor mouth 11, the top of case beam 1 is embedded with a plurality of sleeve pipes 4 that are communicated with anchor mouth 11; The sleeve pipe 4 interior vibrating heads 5 that are inserted with respectively.Case beam 1 upper surface is given prominence in the upper end of sleeve pipe 4, and the lower end of sleeve pipe 4 is charged in the anchor mouth 11.Sleeve pipe 4 is bellows.
Because the employing of the sleeve pipe 4 that case beam 1 is communicated with anchor mouth 11, thereby anchor mouth 11 concretings from case beam 1 top have been realized, need not on sealing off and covering anchorage template 3, to offer in addition plug hole, realized flat appearance and the uniformity of case beam 1 outer facade, need not to carry out follow-up repair procedure; The simultaneously employing owing to sleeve pipe 4 can realize inserting the automatic stirring that vibrating head 5 is realized mixed earth, thereby has reduced constructor's labour intensity, has guaranteed the mixing quality of mixed earth, has improved the efficiency of construction of engineering.
The utility model is based on satisfying under the prerequisite of impression quality of the concrete closely knit and guard box beam 1 outer facade of sealing off and covering anchorage as far as possible, the sealing off and covering anchorage template 3 at anchor mouth 11 positions once Zhi Li puts in place, form the cavity of sealing, need not reserve the filling concrete mouth, while pre-buried bellows in anchor mouth 11 upper tank beams 1 concrete roof, bellows is suitable for reading to be passed from case beam 1 end face; End opening inserts anchor mouth 11, forms the concrete passage of perfusion sealing off and covering anchorage; And utilizing this passage, vibrating head 5 stretches into anchor mouth 11 in bellows, carry out the concrete operation of vibrating.Can guarantee that like this sealing off and covering anchorage concrete once-cast puts in place, manually not fill up modification at needs, guarantee the uniformity of the outer facade of sealing off and covering anchorage concrete and whole case beam 1 concrete, guarantee as much as possible the impression quality of clear-water concrete.
Below embodiment has been described in detail the utility model by reference to the accompanying drawings, and those skilled in the art can make the many variations example to the utility model according to the above description.Thereby some details among the embodiment should not consist of restriction of the present utility model, and the scope that the utility model will define with appended claims is as protection domain of the present utility model.

Claims (3)

1. the outer seamless sealing off and covering anchorage structure of facade of a Cast-in-situ Beam, comprise the case beam that offers the anchor mouth and by fit described case beam and cover the sealing off and covering anchorage template of described anchor mouth of a plurality of lacing wires, it is characterized in that the top of described case beam is embedded with the sleeve pipe that a plurality of and described anchor mouth is communicated with; Be inserted with respectively a vibrating head in the described sleeve pipe.
2. the outer seamless sealing off and covering anchorage structure of facade of Cast-in-situ Beam according to claim 1 is characterized in that described case beam upper surface is given prominence in the upper end of described sleeve pipe, and the lower end of described sleeve pipe is charged in the described anchor mouth.
3. the outer seamless sealing off and covering anchorage structure of facade of Cast-in-situ Beam according to claim 1 and 2 is characterized in that described sleeve pipe is bellows.
CN201220464834.4U 2012-09-12 2012-09-12 Cast-in-place outer vertical face seamless seal anchor structure Expired - Lifetime CN202766970U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220464834.4U CN202766970U (en) 2012-09-12 2012-09-12 Cast-in-place outer vertical face seamless seal anchor structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220464834.4U CN202766970U (en) 2012-09-12 2012-09-12 Cast-in-place outer vertical face seamless seal anchor structure

Publications (1)

Publication Number Publication Date
CN202766970U true CN202766970U (en) 2013-03-06

Family

ID=47773553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220464834.4U Expired - Lifetime CN202766970U (en) 2012-09-12 2012-09-12 Cast-in-place outer vertical face seamless seal anchor structure

Country Status (1)

Country Link
CN (1) CN202766970U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104480858A (en) * 2014-10-20 2015-04-01 中建三局第二建设工程有限责任公司 Construction method for sealing anchorage of pre-stress concrete box girder and cross girder anchored troughs
CN107237263A (en) * 2017-06-15 2017-10-10 中交航局第工程有限公司 Mining under railways sealing off and covering anchorage skin hammers method of vibrating into shape

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104480858A (en) * 2014-10-20 2015-04-01 中建三局第二建设工程有限责任公司 Construction method for sealing anchorage of pre-stress concrete box girder and cross girder anchored troughs
CN107237263A (en) * 2017-06-15 2017-10-10 中交航局第工程有限公司 Mining under railways sealing off and covering anchorage skin hammers method of vibrating into shape
CN107237263B (en) * 2017-06-15 2019-04-16 中交一航局第一工程有限公司 Mining under railways sealing off and covering anchorage skin hammers method of vibrating into shape

Similar Documents

Publication Publication Date Title
CN103938864B (en) Infilled wall Constructional Col-umn Construction engineering method
CN203755334U (en) Single-pipe tower prefabricated spiral steel pipe pile foundation
CN102561402B (en) Treatment method for construction joint between top plate and wall of individual underground civil air defense project constructed by covered top-down excavation method
CN109024870A (en) The connection structure and its construction method of assembled underground structure vertical member
CN102808422B (en) Bonded post-tensioned prestressed construction method for cast-in-place reinforced concrete structure
CN105804410A (en) Sub-cabin pressure grouting method for vertical connection of prefabricated concrete structure
CN107196257B (en) House wiring structure and wiring method
CN109339238A (en) A kind of prefabricated assembled profile steel concrete column splicing node structure and its construction method
CN202766970U (en) Cast-in-place outer vertical face seamless seal anchor structure
CN104314050B (en) A kind of concrete works movement joint vertical sealing swaging die and construction method thereof
CN103015318A (en) Inner sleeve-type inclined guy cable main tower cable guide pipe and construction method thereof
CN106759563A (en) A kind of device for pile foundation repairing and reinforcing and the construction method using the device
CN101781935B (en) Method for substituting pre-embedded waterproof casing pipe in concrete structure
CN104746434B (en) Closure segment formwork system without dismantling outer formwork
CN209408833U (en) The structure of transvers plate of multiple building wire box precast concrete blocks can be made simultaneously
CN103334771A (en) Concrete pouring method of side wall and joint of middle plate and vault by means of underground excavation reverse construction method
CN207194001U (en) A kind of new overhead transmission line concrete precast pipe pile cushion cap foundation
CN203689815U (en) Teaching simulation body for tunnel micro-step method technology
CN206988597U (en) Compound plastic film precast concrete pipeline and its special prepare mould
CN103171052B (en) The disposable prefabricated construction engineering method of twin columns wave-breaking body
CN109778682A (en) Spreading structure and spreading method in the middle part of pier column
CN206143608U (en) Assembled T beam bridge hogging moment district anchorage sealing system
CN109056475A (en) The construction method of kerbstone mounting structure
CN205604287U (en) Highway tunnel portal wall
CN205918129U (en) A cast -in -place section template reinforced structure for prefabricated concrete structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20130306

CX01 Expiry of patent term