CN202744956U - Movable protection platform for bridge construction - Google Patents

Movable protection platform for bridge construction Download PDF

Info

Publication number
CN202744956U
CN202744956U CN2012203066632U CN201220306663U CN202744956U CN 202744956 U CN202744956 U CN 202744956U CN 2012203066632 U CN2012203066632 U CN 2012203066632U CN 201220306663 U CN201220306663 U CN 201220306663U CN 202744956 U CN202744956 U CN 202744956U
Authority
CN
China
Prior art keywords
bridge
construction
protection platform
movable protection
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2012203066632U
Other languages
Chinese (zh)
Inventor
黄盛�
阮有力
赵伟
陶路
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Original Assignee
GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd filed Critical GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Priority to CN2012203066632U priority Critical patent/CN202744956U/en
Application granted granted Critical
Publication of CN202744956U publication Critical patent/CN202744956U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a movable protection platform for bridge construction. The movable protection platform is characterized in that truss structures (1) are connected with suspension trolleys (2) which are connected with a rail on the bottom of a bridge, a steel wire mesh (6) is arranged on the bottom of each truss structure (1), and protective railings (4) are arranged around the truss structures (1). The movable protection platform has the advantages of providing an operation platform for operation on the bottom of the bridge of constructors so as to facilitate the bridge construction, and also being capable of fully covering a whole construction area so as to ensure that the constructors can fall on the protection platform when accidently fall down in the construction process, thereby guaranteeing the life security of the constructors. The movable protection platform can advance synchronously along with the bridge construction in the construction process, and has the characteristics of being driven by power, simple to lock, convenient to operate, capable of shortening a construction period and guaranteeing the security, and the like.

Description

A kind of bridge is built mobile protective platform
Technical field
The utility model relates to a kind of bridge and builds mobile protective platform, belongs to technical field of bridge engineering.
Background technology
In the prior art; bridge is in construction process; usually only build platform; the space that provides the workman to operate meets accident in work progress for the constructor and to fall, and the safety that adopt are brought protection more; use trouble; even and the constructor falls the protection of safety belt arranged in the process, also run into easily the high equipment of sharp-pointed support or hardness etc., safe not.
The utility model content
The purpose of this utility model is, provides a kind of bridge to build mobile protective platform.Simple in structure, easy to operate, operating platform can be provided, play simultaneously the device of safety protection function, to remedy the deficiencies in the prior art.
The technical solution of the utility model.A kind of bridge is built mobile protective platform, connects on the trussed construction to hang chassis, hangs chassis and is connected with the track of bridge bottom, is provided with wire rope net in the trussed construction bottom, is provided with guard rail around trussed construction.
Described trussed construction connects hoist engine.
Described trussed construction is provided with the braking coaster that is fixedly connected with bridge.
Mobile protective platform of the present utility model has well solved in bridge construction: 1, for the constructor provides operating platform in the operation process of bridge bottom, make things convenient for the construction of bridge; 2, this moving protection platform has covered whole construction area comprehensively, and the constructor drops on the protective platform after meeting accident in work progress and falling, and has ensured constructor's life security.The utility model simultaneously can have power drive along with bridge construction is pushed ahead synchronously in work progress, locking is simple, and is easy to operate, accelerates the duration, and the characteristics such as ensure safety.
Description of drawings
Accompanying drawing 1 is structural representation of the present utility model;
Accompanying drawing 2 is the top view of accompanying drawing 1.
The specific embodiment
Embodiment of the present utility model.A kind of bridge is built mobile protective platform, as illustrated in fig. 1 and 2, build trussed construction 1, connect on the trussed construction 1 and hang chassis 2, hanging chassis 2 is connected with the track of bridge bottom, trussed construction 1 is suspended on the bridge bottom, wire rope net 6 is installed in trussed construction 1 bottom, guard rail 4 is installed around trussed construction 1.Trussed construction 1 is the main frame of mobile protective platform, and constructor's operation just stands on the trussed construction.Whole trussed construction 1 be installed in bridge under, the every side of the transverse width of trussed construction 1 generally should design above bridge width 3m, 2~3 sections that vertical width generally should be bridge are long, to make things convenient for personnel operation and to deposit construction tool, drop on outside the mobile protective platform when avoiding simultaneously personnel or instrument from bridge floor eminence accidental falling.Guard rail 4 surrounds whole mobile protective platform periphery, guarantees operating personnel's safety.Wire rope net 6 plays the overall protected effect of whole mobile protective platform, covers the zone of All Jobs comprehensively, the personnel's of preventing generation casualty accident of falling.
Trussed construction 1 connects hoist engine 3, and the cable wire end of hoist engine 3 ties up on the bridge, starting hoist engine 3, thus hoist engine 3 rope closings have realized moving forward of trussed construction 1.
The braking coaster 5 that is fixedly connected with bridge is installed on the trussed construction 1.Trussed construction 1 move in place after, by braking coaster 5 and bridge locking, can construct at trussed construction 1, until this workshop section's construction is complete.

Claims (3)

1. a bridge is built mobile protective platform, it is characterized in that: the upper connection of trussed construction (1) hung chassis (2), hanging chassis (2) is connected with the track of bridge bottom, be provided with wire rope net (6) in trussed construction (1) bottom, be provided with guard rail (4) on every side at trussed construction (1).
2. bridge according to claim 1 is built mobile protective platform, it is characterized in that: described trussed construction (1) connects hoist engine (3).
3. bridge according to claim 1 is built mobile protective platform, it is characterized in that: described trussed construction (1) is provided with the braking coaster (5) that is fixedly connected with bridge.
CN2012203066632U 2012-06-28 2012-06-28 Movable protection platform for bridge construction Expired - Lifetime CN202744956U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012203066632U CN202744956U (en) 2012-06-28 2012-06-28 Movable protection platform for bridge construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012203066632U CN202744956U (en) 2012-06-28 2012-06-28 Movable protection platform for bridge construction

Publications (1)

Publication Number Publication Date
CN202744956U true CN202744956U (en) 2013-02-20

Family

ID=47704379

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012203066632U Expired - Lifetime CN202744956U (en) 2012-06-28 2012-06-28 Movable protection platform for bridge construction

Country Status (1)

Country Link
CN (1) CN202744956U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747681A (en) * 2012-06-28 2012-10-24 贵州桥梁建设集团有限责任公司 Movable protection platform for constructing bridge
CN108468279A (en) * 2018-03-13 2018-08-31 苏州诚满信息技术有限公司 It is a kind of based on the smart bridge repair system rescued in water

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747681A (en) * 2012-06-28 2012-10-24 贵州桥梁建设集团有限责任公司 Movable protection platform for constructing bridge
CN108468279A (en) * 2018-03-13 2018-08-31 苏州诚满信息技术有限公司 It is a kind of based on the smart bridge repair system rescued in water

Similar Documents

Publication Publication Date Title
CN102381611B (en) Vertically-lifting hanging basket
CN203465079U (en) Multifunctional testing device
CN201826542U (en) Self-climbing protective screening
CN202744956U (en) Movable protection platform for bridge construction
CN104453201A (en) Automatic ascending and descending type material platform
CN203497883U (en) Safety lifting device convenient to use and used for operators of tower crane
CN204326493U (en) Unidirectional rising catching device
CN102747681A (en) Movable protection platform for constructing bridge
CN201843625U (en) Dismounting platform for underground hydraulic bracket
CN203060661U (en) Children development exploration device
CN205275061U (en) Semi -portal crane
CN204643664U (en) A kind of building tower crane
CN210246126U (en) Obstacle-crossing wiring aerodyne
CN203486809U (en) Falling protector of tower crane vertical ladder
CN207685680U (en) Pulley trolley system suitable for the installation of truss-type bridges accessory structure
CN202366352U (en) Movable safety belt suspension device
CN202704977U (en) Boring tower cage elevating mechanism
CN203794485U (en) Single-main-beam hook gantry crane
CN102976183A (en) Construction lift for building under construction
CN203158956U (en) Building for preventing ladder cage of construction lift from falling
CN203158962U (en) Anti-falling system of construction elevator
CN213681766U (en) Arch bridge arch ring overhauls lift work platform
CN204416829U (en) Construction elevator safety aid
CN204960938U (en) Vertical pit shaft construction platform sling pull formula work platform
CN202682599U (en) Anti-slipping safety belt

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130220