CN202731927U - 隧道施工装置 - Google Patents

隧道施工装置 Download PDF

Info

Publication number
CN202731927U
CN202731927U CN 201220359814 CN201220359814U CN202731927U CN 202731927 U CN202731927 U CN 202731927U CN 201220359814 CN201220359814 CN 201220359814 CN 201220359814 U CN201220359814 U CN 201220359814U CN 202731927 U CN202731927 U CN 202731927U
Authority
CN
China
Prior art keywords
tunnel
automatic
ground control
excavator
control station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220359814
Other languages
English (en)
Inventor
岑益南
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 201220359814 priority Critical patent/CN202731927U/zh
Application granted granted Critical
Publication of CN202731927U publication Critical patent/CN202731927U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本实用新型涉及一种隧道施工装置。本实用新型的隧道施工装置,包括若干个运输竖井,运输竖井在超长隧道线路上间隔设置,运输竖井的井口一侧设有地面控制站,地面控制站控制沿超长隧道线路挖掘的自动隧道挖掘机。本实用新型的有益效果是:采用运输竖井分段设置,从而将隧道施工段缩短到合理长度,通过地面控制站遥控自动隧道挖掘机,可以实现井下无人的作业,使现有技术无法实现的超长超深隧道工程得以实施,并且无需担心地下工作人员的生命安全,安全可靠。

Description

隧道施工装置
(一)        技术领域
本实用新型涉及隧道工程领域,特别涉及一种隧道施工装置。
(二)        背景技术
跨流域调水或修建交通道路,经常要绕过崇山峻岭,大大增加了工程量、工程支出,并且存在破坏生态环境的问题。但是现有隧道施工技术只能实施短程隧道的建设,对于千公里以上超长超深隧道,由于土渣外排困难,地下隧道工作人员的生命安全无法保障,至今仍无法实施。
(三)        发明内容
本实用新型为了弥补现有生产技术的不足,提供了一种能使超长超深隧道工程成功实施、井下无人作业、安全可靠的隧道施工装置。
本实用新型是通过如下技术方案实现的: 
一种隧道施工装置,包括若干个运输竖井,其特殊之处在于:运输竖井在超长隧道线路上间隔设置,运输竖井的井口一侧设有地面控制站,地面控制站控制沿超长隧道线路挖掘的自动隧道挖掘机。
本实用新型的隧道施工装置,自动隧道挖掘机设有隧道壁的铺设与安装装置。
本实用新型的隧道施工装置,自动隧道挖掘机还设有物料装载设备。
本实用新型的隧道施工装置,地面控制站通过电缆指挥自动隧道挖掘机。
本实用新型的有益效果是:采用运输竖井分段设置,从而将隧道施工段缩短到合理长度,通过地面控制站遥控自动隧道挖掘机,可以实现井下无人的作业,使现有技术无法实现的超长超深隧道工程得以实施,并且无需担心地下工作人员的生命安全,安全可靠。
(四)        附图说明
下面结合附图对本实用新型作进一步的说明。
图1为本实用新型的结构示意图;
图中,1地下岩层,2地面控制站,3待挖掘隧道,4自动隧道挖掘机,5已挖掘成的隧道,6运输竖井,7电缆,8工作掌面。
(五)        具体实施方式
根据现有隧道挖掘技术,对于超过1000m的超长超深隧道无法施工,基于此,本实用新型提供了一种隧道施工装置,包括若干个运输竖井6,运输竖井6在超长隧道线路上间隔设置,运输竖井6的井口一侧设有地面控制站2,地面控制站2控制沿超长隧道线路挖掘的自动隧道挖掘机4。自动隧道挖掘机4设有隧道壁的铺设与安装装置。所述的自动隧道挖掘机4还设有物料装载设备,便于往外排出土渣。地面控制站通过电缆7指挥自动隧道挖掘机4,自动隧道挖掘机4上无需工作人员,实现无人作业,保护工作人员的安全。
本实用新型适用于一种隧道施工方法,该方法包括以下步骤:
(1)超长隧道线路上间距设置若干个运输竖井6;
(2)在运输竖井6的井口一侧建设地面控制站2;
(3)将自动隧道挖掘机4置于运输竖井6的工作掌面8上;
(4)利用地面控制站2支配自动隧道挖掘机4沿超长隧道线路挖掘。
本实用新型的隧道施工方法,相邻的两个运输竖井6内的自动隧道挖掘机4分别沿超长隧道线路相对挖掘,即采用两运输竖井6对头挖进的方式利用自动隧道挖掘机4挖掘。通过自动隧道挖掘机4自动铺设安装隧道壁并自动装载物料。通过运输竖井6将自动隧道挖掘机4的部件运到井底的工作掌面8组装而成。
运输竖井6之间的距离根据自动隧道挖掘机4月挖进量及工期要求而定,运输竖井6的高度根据隧道海拔高度与地面地貌而定,选址,在可能深至地下岩层1的超长隧道线路上建若干个运输竖井6,在运输竖井6井口一侧设置地面控制站2,通过运输竖井6将自动隧道挖掘机4的部件运到井底工作掌面8上,组装成自动隧道挖掘机4,沿超长隧道线路工作,地面控制站2通过电缆7控制自动隧道挖掘机4,向一定的方位挖进,自动隧道挖掘机4具有隧道壁的铺设与安装功能,配有物料装载设备,自动隧道挖掘机4过后已挖掘成的隧道5成型,其物料装载设备便于装载挖掘过程中产生的土渣,自动隧道挖掘机4持续向待挖掘隧道3挖进,为了缩减工程,可以采用两运输竖井6对头掘进的方式。
本实用新型采用运输竖井6分段设置,从而将隧道施工段缩短到合理长度,通过地面控制站2遥控自动隧道挖掘机4,可以实现井下无人的作业,而该自动隧道挖掘机4能自动铺设与安装隧道壁,装载土渣,无需担心地下工作人员的生命安全,安全可靠,使现有技术无法实现的超长超深隧道工程得以实施。本实用新型是以西藏流域离境之水跨流域调入新疆为背景,实施该项目,可使我国增加可耕地十多亿亩,增产粮食五千多亿斤,能容纳一亿多人就业,中国的西部有了水,有了可持续发展的保障,中国西部气候经济都得到了改善,具有益效果,十分巨大。

Claims (4)

1.一种隧道施工装置,包括若干个运输竖井,其特征在于:运输竖井在超长隧道线路上间隔设置,运输竖井的井口一侧设有地面控制站,地面控制站控制沿超长隧道线路挖掘的自动隧道挖掘机。
2.根据权利要求1所述的隧道施工装置,其特征在于:自动隧道挖掘机设有隧道壁的铺设与安装装置。
3.根据权利要求2所述的隧道施工装置,其特征在于:自动隧道挖掘机还设有物料装载设备。
4.根据权利要求1或2或3 所述的隧道施工装置,其特征在于:地面控制站通过电缆指挥自动隧道挖掘机。
CN 201220359814 2012-07-24 2012-07-24 隧道施工装置 Expired - Fee Related CN202731927U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220359814 CN202731927U (zh) 2012-07-24 2012-07-24 隧道施工装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220359814 CN202731927U (zh) 2012-07-24 2012-07-24 隧道施工装置

Publications (1)

Publication Number Publication Date
CN202731927U true CN202731927U (zh) 2013-02-13

Family

ID=47657639

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220359814 Expired - Fee Related CN202731927U (zh) 2012-07-24 2012-07-24 隧道施工装置

Country Status (1)

Country Link
CN (1) CN202731927U (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102777187A (zh) * 2012-07-24 2012-11-14 岑益南 隧道施工装置及方法
CN108547628A (zh) * 2018-05-17 2018-09-18 中冶建工集团有限公司 上软下硬地层顶管工作井快速施工方法
CN108661651A (zh) * 2018-05-17 2018-10-16 中冶建工集团有限公司 硬质岩层顶管工作井快速施工方法
CN108678755A (zh) * 2018-05-17 2018-10-19 中冶建工集团有限公司 松软岩层顶管工作井快速施工方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102777187A (zh) * 2012-07-24 2012-11-14 岑益南 隧道施工装置及方法
CN108547628A (zh) * 2018-05-17 2018-09-18 中冶建工集团有限公司 上软下硬地层顶管工作井快速施工方法
CN108661651A (zh) * 2018-05-17 2018-10-16 中冶建工集团有限公司 硬质岩层顶管工作井快速施工方法
CN108678755A (zh) * 2018-05-17 2018-10-19 中冶建工集团有限公司 松软岩层顶管工作井快速施工方法
CN108547628B (zh) * 2018-05-17 2020-09-01 中冶建工集团有限公司 上软下硬地层顶管工作井快速施工方法

Similar Documents

Publication Publication Date Title
CN108222938B (zh) 一种大倾角煤层采空区组合注浆充填开采方法
CN104389606B (zh) 一种基于环境保护的矿山还原式多井联采方法
CN104775817B (zh) 全负压连采连充分步置换“三下”采煤法
CN103498696B (zh) 一种从顶板巷道注浆充填压实采空区充填体的方法
CN105298507A (zh) 一种上部明挖下部掘进机施工的地下管廊施工方法
CN103382844B (zh) 一种履带式液压组合支架临时支护与永久支护平行作业掘进工艺及设备
CN106121657A (zh) 一种多功能数控竖井掘进装置及施工方法
CN104532818A (zh) 一种露天矿采空区的治理方法
CN202731927U (zh) 隧道施工装置
CN104131829A (zh) 一种固体充填采煤液压支架撤架方法
CN104863592A (zh) 一种大结构分段凿岩阶段出矿嗣后充填采矿法
CN104847355A (zh) 中厚急倾斜矿体空场连续开采方法
US11377952B2 (en) Method for radially mining open-pit end slope pressed coal
CN104500070A (zh) 一种连续采煤机膏体充填开采方法
CN103726858A (zh) 地下大型洞库工程球柱组合体开挖方法
CN105201001A (zh) 一种岩溶地区大型溶洞的复合防渗结构及其施工方法
CN104074534A (zh) 一种综采/综放工作面的沿空留巷方法
GB2574331A (en) Method for laying out minefield suitable for fluidized mining of coal resources
CN102777187A (zh) 隧道施工装置及方法
CN105240012A (zh) 一种实现煤柱同采的f型区段采煤方法
CN205062827U (zh) 一种岩溶地区大型溶洞的复合防渗结构
CN204495211U (zh) 一种隧道明挖段的爆破炮孔布置系统
CN111364994B (zh) 一种综采转充填连续推进协同开采方法
CN104047607A (zh) 盾构机围护结构条件下吊出工法
CN110030001B (zh) 一种山岭隧道出洞的施工方法

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130213

Termination date: 20150724

EXPY Termination of patent right or utility model