CN202706962U - Blowout wrecking device for mechanically installing plug valve - Google Patents

Blowout wrecking device for mechanically installing plug valve Download PDF

Info

Publication number
CN202706962U
CN202706962U CN 201220343911 CN201220343911U CN202706962U CN 202706962 U CN202706962 U CN 202706962U CN 201220343911 CN201220343911 CN 201220343911 CN 201220343911 U CN201220343911 U CN 201220343911U CN 202706962 U CN202706962 U CN 202706962U
Authority
CN
China
Prior art keywords
blowout
plug valve
well
control device
support rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220343911
Other languages
Chinese (zh)
Inventor
范玉斌
霍延春
张建国
吕书栋
李扬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Downhole Operation Co of Sinopec Shengli Oilfield Co
Original Assignee
Downhole Operation Co of Shengli Petroleum Administration
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Downhole Operation Co of Shengli Petroleum Administration filed Critical Downhole Operation Co of Shengli Petroleum Administration
Priority to CN 201220343911 priority Critical patent/CN202706962U/en
Application granted granted Critical
Publication of CN202706962U publication Critical patent/CN202706962U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Mechanically-Actuated Valves (AREA)

Abstract

The utility model relates to a blowout wrecking device for mechanically installing a plug valve. The technical scheme is that the blowout wrecking device is movably connected on one side of a well mouth or a well repairing blowout preventer flange and mainly composed of a support rod sleeve, a fastening handle, a support spring, a movable support rod, a cross hand wheel, a cross guiding sleeve, a rotating handle, a rotating short section, a central support and the plug valve. The upper end of the support rod sleeve is connected with the movable support rod through the support spring and the fastening handle, the cross guiding sleeve is fixed at the top of the movable support rod, the cross hand wheel is arranged at one end of the cross guiding sleeve, the central support is connected at the other end of the cross guiding sleeve, the rotating short section and the rotating handle are arranged at the top of the central support, and the plug valve is movably connected at the bottom of the central support. The blowout wrecking device has the advantages that during workover treatment of an oil field, when the pressure in a well rises suddenly and blowout occurs, the plug valve can be installed fast, forcefully and mechanically, liquid gas in the well can be prevented from ejecting outwards through an oil pipe, and the problem that the plug valve cannot be installed easily without any supporting reference substance during traditional manual removing is solved.

Description

Mechanical erection plug valve blowout control device
Technical field
The utility model relates to a kind of oil well repairing operation device, particularly a kind of mechanical erection plug valve blowout control device.
Background technology
At present, no matter in oil field overhaul or light maintenance operation team, all be furnished with the running string plug valve, during use, traditional mode of operation generally all is with the mode of upward detaining manually it to be installed in the top of running string; This traditional mode of operation, in the situation that blowout does not occur in Oil/gas Well, it is than more smoothly that traditional plug valve is installed, but, when Oil/gas Well really blowout occurs, when robbing the dress plug valve with this artificial mode again, following situation can occur: the one, if blowout pressure is little, the constructing operation personnel not great strength of membership dues just can rob and load onto plug valve, but cause potential harm can for the well head operating personnel; The 2nd, in the situation that blowout pressure increases gradually, because well head pressure is larger, the well head operating personnel are just difficult to be robbed plug valve on the tubing string that is contained in well head with traditional manual mode, even load onto strength and the long time that also can cost a lot of money.
Sign in above situation, for the in time generation of Prevention of blowout accident, the device of Fast Installation Prevention of blowout occurs to have behind the gas blowout accident with the well site, on-the-spot need a kind of can be safe, simple, convenient and rapid, installation, the reliable blowout control device of flexible adjustment, solve the on-the-spot problem that exists.
Summary of the invention
The purpose of this utility model is exactly in view of the foregoing defects the prior art has, provide a kind of be specifically designed to rob be sprayed in the well workover trip-out process when blowout occurs, the mechanical erection plug valve blowout control device of plug valve is installed by force.
Its technical scheme is: the side at well head or well-repairing blowout preventor flange is flexibly connected blowout control device, described blowout control device is mainly by the support bar cover, fastening handle, support spring, movable branching rod, horizontal handwheel, horizontal fairlead, rotary handle, rotating short-knot, center bearing bracket, plug valve forms, support spring is passed through in the upper end of described support bar cover, fastening handle connects movable branching rod, horizontal fairlead is fixed at the top of movable branching rod, one end of horizontal fairlead is provided with horizontal handwheel, the other end connects center bearing bracket, the top of center bearing bracket is provided with rotating short-knot, rotary handle, the bottom is flexibly connected plug valve.
Above-mentioned blowout control device is connected to a side of well head or well-repairing blowout preventor flange by base for supporting, U-shaped groove, fixed pin shaft, active pin shaft, described base for supporting is fixed on a side of well head or well-repairing blowout preventor flange, and base for supporting is provided with U-shaped groove.
Operating principle of the present utility model is: base for supporting is passed through set bolt, nut is fixed on two corresponding on 250 well heads or well-repairing blowout preventor flange bolts hole, behind set bolt and nut screwing clamping, plug valve has been installed on the rotating short-knot in advance, then by the center of rotation support and regulate horizontal handwheel centering tubing coupling center, then being rotated counterclockwise vertical release handle drops on plug valve in the tubing coupling in the button, clockwise rotate again rotating short-knot, so just plug valve tightly can be tightened in the tubing coupling, last cut-out tap valve can be finished and rob spray.
The beneficial effects of the utility model are: mainly adopt first support to be installed on wellhead flange, then use on the handwheel of blowout control device itself and detain, be used for the oil well repairing operation process, if borehole pressure raises suddenly, when blowout occurs, can be fast the blowout control device of mechanical erection plug valve by force, to prevent that liquid gas sprays by the oil pipe inner chamber in the well outward, solved and unloaded plug valve on the Traditional Man without the problem that supports object of reference and be not easy to install.
Description of drawings
Accompanying drawing 1 is structural representation of the present utility model;
Among the upper figure: base for supporting 1, U-shaped groove 2, fixed pin shaft 3, active pin shaft 4, support bar cover 5, fastening handle 6, support spring 7, movable branching rod 8, horizontal handwheel 9, horizontal fairlead 10, set bolt 11, rotary handle 12, rotating short-knot 13, center bearing bracket 14, spacer pin 15, plug valve 16; Box cupling A, tubing string elevator B, well head big four C.
The specific embodiment
By reference to the accompanying drawings 1, the utility model will be further described:
Side at well head or well-repairing blowout preventor flange is flexibly connected blowout control device, described blowout control device is mainly by support bar cover 5, fastening handle 6, support spring 7, movable branching rod 8, horizontal handwheel 9, horizontal fairlead 10, rotary handle 12, rotating short-knot 13, center bearing bracket 14, plug valve 16 forms, the upper end of described support bar cover 5 is by support spring 7, fastening handle 6 connects movable branching rod 8, horizontal fairlead 10 is fixed at the top of movable branching rod 8, one end of horizontal fairlead 10 is provided with horizontal handwheel 9, and fixing by set bolt 11, the other end connects center bearing bracket 14 by spacer pin 15, the top of center bearing bracket 14 is provided with rotating short-knot 13, rotary handle 12, the bottom is flexibly connected plug valve 16.
Wherein, blowout control device is connected to a side of well head or well-repairing blowout preventor flange by base for supporting 1, U-shaped groove 2, fixed pin shaft 3, active pin shaft 4, described base for supporting 1 is fixed on a side of well head or well-repairing blowout preventor flange, and base for supporting 1 is provided with U-shaped groove 2.
The utility model is installed on the wellhead flange by base for supporting 1, without the blowout situation time, can be installed in advance operation wellhead and fall by U-shaped groove 2, fixed pin shaft 3, active pin shaft 4 and place near the well head; In when, in the well blowout situation occuring when, can prop up fast this device, insert active pin shaft 4 and align well head.Center bearing bracket 14 is rotated around movable branching rod 8, make center bearing bracket 14 misalignment well head centers, plug valve 16 is installed on center bearing bracket 14, then the center of rotation support 14, make the centrally aligned well head center of plug valve 16, namely illustrating the center of tubing coupling A, is tubing string elevator B, well head big four C below the box cupling A; When plug valve 16 and well head box cupling A keep off up and down, can press down fast movable branching rod 8 plug valve 16 is contacted with the well head box cupling, then rotate rotary handle 12, plug valve 16 moves down with box cupling and docks; If can rotate horizontal handwheel 9 when plug valve 16 and well head box cupling lateral separation are kept off this moment, make its horizontal alignment; At last, continue turning handle 12, the tubing thread that plug valve 16 is connected with box cupling tightens, and has finished the process of robbing dress plug valve 16, and then the cut-out tap valve 16, finish the blowout prevention of oil pipe inner chamber.

Claims (2)

1. mechanical erection plug valve blowout control device, it is characterized in that: the side at well head or well-repairing blowout preventor flange is flexibly connected blowout control device, described blowout control device is mainly by support bar cover (5), fastening handle (6), support spring (7), movable branching rod (8), horizontal handwheel (9), horizontal fairlead (10), rotary handle (12), rotating short-knot (13), center bearing bracket (14), plug valve (16) forms, the upper end of described support bar cover (5) is by support spring (7), fastening handle (6) connects movable branching rod (8), horizontal fairlead (10) is fixed at the top of movable branching rod (8), one end of horizontal fairlead (10) is provided with horizontal handwheel (9), the other end connects center bearing bracket (14), the top of center bearing bracket (14) is provided with rotating short-knot (13), rotary handle (12), the bottom is flexibly connected plug valve (16).
2. mechanical erection plug valve blowout control device according to claim 1, it is characterized in that: described blowout control device is connected to a side of well head or well-repairing blowout preventor flange by base for supporting (1), U-shaped groove (2), fixed pin shaft (3), active pin shaft (4), described base for supporting (1) is fixed on a side of well head or well-repairing blowout preventor flange, and base for supporting (1) is provided with U-shaped groove (2).
CN 201220343911 2012-07-17 2012-07-17 Blowout wrecking device for mechanically installing plug valve Expired - Fee Related CN202706962U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220343911 CN202706962U (en) 2012-07-17 2012-07-17 Blowout wrecking device for mechanically installing plug valve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220343911 CN202706962U (en) 2012-07-17 2012-07-17 Blowout wrecking device for mechanically installing plug valve

Publications (1)

Publication Number Publication Date
CN202706962U true CN202706962U (en) 2013-01-30

Family

ID=47587271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220343911 Expired - Fee Related CN202706962U (en) 2012-07-17 2012-07-17 Blowout wrecking device for mechanically installing plug valve

Country Status (1)

Country Link
CN (1) CN202706962U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625974A (en) * 2014-10-29 2016-06-01 中国石油化工股份有限公司 Water well head master gate rush-spraying device
CN112081540A (en) * 2020-10-26 2020-12-15 中国石油天然气集团有限公司 Pressurized type tubular column internal blowout prevention valve installing method
CN113370154A (en) * 2020-03-10 2021-09-10 中国石油天然气股份有限公司 Auxiliary plug valve installation device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625974A (en) * 2014-10-29 2016-06-01 中国石油化工股份有限公司 Water well head master gate rush-spraying device
CN113370154A (en) * 2020-03-10 2021-09-10 中国石油天然气股份有限公司 Auxiliary plug valve installation device
CN112081540A (en) * 2020-10-26 2020-12-15 中国石油天然气集团有限公司 Pressurized type tubular column internal blowout prevention valve installing method

Similar Documents

Publication Publication Date Title
CN202706962U (en) Blowout wrecking device for mechanically installing plug valve
AU2012346673A1 (en) A method and an apparatus for rigging up intervention equipment in a lifting arrangement utilized on a floating vessel
CN101793155A (en) Convenient and fast constant-resistance type temporary support strut
CN104863538A (en) Setting blowout preventer device with pressed plug
CN205154079U (en) Stand alone type area is pressed operation plug valve emergency and is robbed dress device
CN106369236A (en) Vertical clamp type connector for underwater manifold
CN200955373Y (en) Oil-water well first-aid injection apparatus
CN102303817B (en) Screwing-in anchoring device for crane
CN110043208B (en) Pulse neutron oxygen activation water absorption profile testing device in offshore platform and construction process
CN202202835U (en) Multifunctional wellhead device used for down-hole operation in oil-gas well
CN204627551U (en) Offshore petroleum drilling function flexible pipe connects and emergency release
CN106761525A (en) Rob gusher mouthful and rob spray method
CN2923987Y (en) Sucker rod wellhead device
CN201902190U (en) Blowout prevention pressure testing device
CN202265333U (en) Screwing-in anchoring device for crane
CN206144562U (en) Major diameter push pipe stopping device
CN209145547U (en) A kind of Integral type well-mouth sealing device and casing hanger one floor run structure
CN201606087U (en) Convenient constant-resistance temporary support prop
CN204532211U (en) A kind of anti-channeling jig
CN209163580U (en) A kind of rotatable lift monitoring bar
CN2900770Y (en) Oil pipe elelator well seal grab spray device
CN202832357U (en) Blowout preventer for rod breakage of screw pump well
CN202228015U (en) A hydraulic drive remote control track motion type hydraulic oil pipe wrench
CN204492701U (en) Test lubricator stands up device
RU2805701C1 (en) Method for installing preventer on support flange of wellhead assembly and constant tripping out two-lift arrangement of downhole equipment from well and device for its implementation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130130

Termination date: 20130717