CN202672726U - Splicing structure of fair-faced concrete pouring formworks - Google Patents

Splicing structure of fair-faced concrete pouring formworks Download PDF

Info

Publication number
CN202672726U
CN202672726U CN 201220278422 CN201220278422U CN202672726U CN 202672726 U CN202672726 U CN 202672726U CN 201220278422 CN201220278422 CN 201220278422 CN 201220278422 U CN201220278422 U CN 201220278422U CN 202672726 U CN202672726 U CN 202672726U
Authority
CN
China
Prior art keywords
angle bar
template
edge sealing
oblique pull
angle iron
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220278422
Other languages
Chinese (zh)
Inventor
陈伟
祝立锋
陈波
陶璐
金开建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongsha Construction Group Co Ltd
Original Assignee
Zhongsha Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongsha Construction Group Co Ltd filed Critical Zhongsha Construction Group Co Ltd
Priority to CN 201220278422 priority Critical patent/CN202672726U/en
Application granted granted Critical
Publication of CN202672726U publication Critical patent/CN202672726U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

A splicing structure of fair-faced concrete pouring formworks comprises a first formwork (1) and a second formwork (2). First edge sealing angle iron (3) and second edge sealing angle iron (5) are respectively fixed onto the first formwork (1) and the second formwork (2), first diagonal angle iron (4) and second diagonal angle iron (6) are respectively fixed onto the first edge sealing angle iron (3) and the second edge sealing angle iron (5), and two ends of a diagonal screw (7) respectively penetrate through preset holes on the first diagonal angle iron (4) and the second diagonal angle iron (6) and are screwed with nuts. The splicing structure has the advantages that corners can keep perpendicular, pouring slurry cannot seep from a joint of the two formworks, the quality of a project is guaranteed, and the attractiveness of the project is improved.

Description

A kind of splicing construction of pouring exposed concrete template
Technical field:
The utility model relates to technical field of building construction, more specifically to a kind of splicing construction of pouring exposed concrete template.
Background technology:
Clear-water concrete is exactly directly to utilize natural texture behind the concrete formation as the concrete work of finishing effect, therefore the pouring exposed concrete engineering requires higher to its surperficial aesthetics, this just so that the difficulty of formwork for placing splicing more strengthened, what existing formwork for placing splicing was generally adopted is the fixing mode of bolt, two formwork for placing adopt the direct dead mode of bolt so that can not be regulated, and in the process of building since stressed meeting so that two templates are no longer vertical, and the slit of the joint of two formwork for placing can enlarge, thereby this meeting is so that build mud and ooze out the corner distortion that causes pouring into a mould in the slit and affect workmanship and aesthetics.
The utility model content:
The purpose of this utility model is exactly the deficiency for prior art, and a kind of splicing construction of pouring exposed concrete template is provided, and it is so that the corner can keep vertically, and building mud can not ooze out from the joint of two templates, guarantee the quality of engineering, also improved simultaneously the aesthetics of engineering.
Technology solution of the present utility model is as follows:
A kind of splicing construction of pouring exposed concrete template, comprise the first template and the second template, the first edge sealing angle bar and the second edge sealing angle bar are separately fixed on the first template and the second template, the first oblique pull angle bar and the second oblique pull angle bar are separately fixed on the first edge sealing angle bar and the second edge sealing angle bar, and the two ends of oblique pull screw rod are passed respectively the default hole on the first oblique pull angle bar and the second oblique pull angle bar and are screwed onto with nut.
The joint of described the first template and the second template is filled with silica gel.
Described the first edge sealing angle bar and the second edge sealing angle bar are fixed on the first template and the second template by screw rod, and the first oblique pull angle bar and the second oblique pull angle bar are weldingly fixed on the first edge sealing angle bar and the second edge sealing angle bar.
The beneficial effects of the utility model are: it has guaranteed the quality of engineering so that the corner can keep vertically building mud and can not oozing out from the joint of two templates, has also improved simultaneously the aesthetics of engineering.
Description of drawings:
Fig. 1 is structural representation of the present utility model
Among the figure: 1, the first template; 2, the second template; 3, the first edge sealing angle bar; 4, the first oblique pull angle bar; 5, the second edge sealing angle bar; 6, the second oblique pull angle bar; 7, oblique pull screw rod.
The specific embodiment:
Embodiment: as shown in Figure 1, a kind of splicing construction of pouring exposed concrete template, comprise the first template 1 and the second template 2, the first edge sealing angle bar 3 and the second edge sealing angle bar 5 are separately fixed on the first template 1 and the second template 2, the first oblique pull angle bar 4 and the second oblique pull angle bar 6 are separately fixed on the first edge sealing angle bar 3 and the second edge sealing angle bar 5, and the two ends of oblique pull screw rod 7 are passed respectively the default hole on the first oblique pull angle bar 4 and the second oblique pull angle bar 6 and are screwed onto with nut.
The joint of described the first template 1 and the second template 2 is filled with silica gel.
Described the first edge sealing angle bar 3 and the second edge sealing angle bar 5 are fixed on the first template 1 and the second template 2 by screw rod, and the first oblique pull angle bar 4 and the second oblique pull angle bar 6 are weldingly fixed on the first edge sealing angle bar 3 and the second edge sealing angle bar 5.
Operating principle: the utility model can be regulated the nut that is screwed onto on the oblique pull screw rod 7 when building, so that the first formwork for placing 1 is in vertical state all the time with the second formwork for placing 2, this is just so that the slit of the first formwork for placing 1 and the second formwork for placing 2 joints is smaller, simultaneously be filled with silica gel at the first formwork for placing 1 and the second formwork for placing 2 joints, therefore building mud can not ooze out from the joint of two formwork for placing, guarantee the quality of engineering, also improved simultaneously the aesthetics of engineering.

Claims (3)

1. the splicing construction of a pouring exposed concrete template, comprise the first template (1) and the second template (2), it is characterized in that: the first edge sealing angle bar (3) and the second edge sealing angle bar (5) are separately fixed on the first template (1) and the second template (2), the first oblique pull angle bar (4) and the second oblique pull angle bar (6) are separately fixed on the first edge sealing angle bar (3) and the second edge sealing angle bar (5), and the two ends of oblique pull screw rod (7) are passed respectively the default hole on the first oblique pull angle bar (4) and the second oblique pull angle bar (6) and are screwed onto with nut.
2. the splicing construction of a kind of pouring exposed concrete template according to claim 1, it is characterized in that: the joint of the first template (1) and the second template (2) is filled with silica gel.
3. the splicing construction of a kind of pouring exposed concrete template according to claim 1, it is characterized in that: the first edge sealing angle bar (3) and the second edge sealing angle bar (5) are fixed on the first template (1) and the second template (2) by screw rod, and the first oblique pull angle bar (4) and the second oblique pull angle bar (6) are weldingly fixed on the first edge sealing angle bar (3) and the second edge sealing angle bar (5).
CN 201220278422 2012-06-08 2012-06-08 Splicing structure of fair-faced concrete pouring formworks Expired - Fee Related CN202672726U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220278422 CN202672726U (en) 2012-06-08 2012-06-08 Splicing structure of fair-faced concrete pouring formworks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220278422 CN202672726U (en) 2012-06-08 2012-06-08 Splicing structure of fair-faced concrete pouring formworks

Publications (1)

Publication Number Publication Date
CN202672726U true CN202672726U (en) 2013-01-16

Family

ID=47493636

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220278422 Expired - Fee Related CN202672726U (en) 2012-06-08 2012-06-08 Splicing structure of fair-faced concrete pouring formworks

Country Status (1)

Country Link
CN (1) CN202672726U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677531A (en) * 2016-12-29 2017-05-17 马鞍山万普实业发展有限公司 Multifunctional connecting tool for building frame
CN110792210A (en) * 2019-11-21 2020-02-14 河南朴之原建筑肌理研究院有限公司 Construction method for high-strength thin rammed earth wall with thickness of 40mm-100mm
CN112376905A (en) * 2020-11-27 2021-02-19 腾达建设集团股份有限公司 Connecting mechanism of stand column steel formwork

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677531A (en) * 2016-12-29 2017-05-17 马鞍山万普实业发展有限公司 Multifunctional connecting tool for building frame
CN110792210A (en) * 2019-11-21 2020-02-14 河南朴之原建筑肌理研究院有限公司 Construction method for high-strength thin rammed earth wall with thickness of 40mm-100mm
CN112376905A (en) * 2020-11-27 2021-02-19 腾达建设集团股份有限公司 Connecting mechanism of stand column steel formwork

Similar Documents

Publication Publication Date Title
CN202672726U (en) Splicing structure of fair-faced concrete pouring formworks
CN204040078U (en) A kind of alter-pouring strips mould plate installs structure
CN205955003U (en) Take prefabricated coincide wallboard of vertical moulding
CN201169916Y (en) T girder moulding board capable of adjusting wing edge falling gradient
CN104074354A (en) Plate-insertion type cast-in-place staircase template and use method of plate-insertion type cast-in-place staircase template
CN103410345A (en) Reinforced concrete column reinforcement device and method
CN202519586U (en) Steel-wood combination type clear water concrete bridge pier formwork structure
CN203129572U (en) Prefabricated concrete formwork and prefabricated building formed by same
CN205330152U (en) A steel form for concrete placement
CN206000154U (en) A kind of building pours uses template
CN204531420U (en) Concreting plate device
CN207513167U (en) The template system of the convex template component of arcuate building, concave template component and its composition
CN203769302U (en) Steel moulding plate component for shear wall
CN203188469U (en) Square column of steel structure
CN204780973U (en) Concrete chamfer construction tool
CN204450817U (en) Pin-connected panel small box girder core mold plate fixture
CN105317216A (en) Wall body reversed construction method and wall body and concrete framework casting structure
CN203594224U (en) Novel semi-fabricated formwork
CN202831248U (en) Connection structure of concrete steel pipe column and H-shaped steel beam
CN206070944U (en) A kind of new insert-type wooden decorative wallboard
CN203393936U (en) Multipurpose compound building member
CN202157540U (en) Support mold plate for hyperbolic reinforced concrete cooling tower
CN204899034U (en) Prefabricated wall post
CN203613793U (en) T-shaped column template
CN203626247U (en) Aluminum alloy formwork base for pouring upper-storey wall/column

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130116

Termination date: 20200608

CF01 Termination of patent right due to non-payment of annual fee