CN202657825U - Device for lifting guyed tower in integrally assembled mode - Google Patents

Device for lifting guyed tower in integrally assembled mode Download PDF

Info

Publication number
CN202657825U
CN202657825U CN 201220226140 CN201220226140U CN202657825U CN 202657825 U CN202657825 U CN 202657825U CN 201220226140 CN201220226140 CN 201220226140 CN 201220226140 U CN201220226140 U CN 201220226140U CN 202657825 U CN202657825 U CN 202657825U
Authority
CN
China
Prior art keywords
lifting
steel
tower
welded
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220226140
Other languages
Chinese (zh)
Inventor
王鹏
李江
吴高华
江宏
童庆望
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Hubei Electric Power Transmission and Distribution Engineering Co Ltd
Original Assignee
Hubei Electric Transmission & Transformation Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Electric Transmission & Transformation Engineering Co filed Critical Hubei Electric Transmission & Transformation Engineering Co
Priority to CN 201220226140 priority Critical patent/CN202657825U/en
Application granted granted Critical
Publication of CN202657825U publication Critical patent/CN202657825U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to a tool for lifting a transmission line tower, in particular to a device for lifting a guyed tower in an integrally assembled mode. The device comprises two I-steel beams which are parallelly arranged and buckled with each other, wherein welding plates are welded between the two I-steel beams in a clamping mode; the two ends of each welding plate stretch out of the I-steel beams; and shackles are fixedly arranged at the two ends of each welding plate and connected with steel wire ropes. The two parallel I-steel beams are welded together through a plurality of welding plates which are arranged at intervals, so that the stress points of a balance pulley for lifting can be moved to two sides during lifting, the axial pressure of a cross arm during lifting is reduced, the risk that the cross arm is broken during integral lifting is reduced, balance in the integral lifting process is fully ensured, and lifting safety is ensured.

Description

Crane integral assembly Guywire tower lifting appliance
Technical field
The utility model relates to the Work tool of electric power line pole tower lifting usefulness, is specifically related to crane integral assembly Guywire tower lifting appliance.
Background technology
LV40 tower overall height 43.5m ~ 49.5m, full tower net weight 25.4t ~ 26.9t belongs to high large-scale heavy tower, and conventional method is to adopt herringbone holding pole or the vertical mode of minute system of solutions to construct in the vertical process of group.Because Work tool is stressed very large, there is potential safety hazard in whole group tower scheme; Adopt minute system of solutions vertical, because the double tower body, whole stability is more difficult guaranteed.
Summary of the invention
The purpose of this utility model is to solve the technical matters of above-mentioned existence, and a kind of balance that improves whole lifting in the lifting process is provided, and guarantees the crane integral assembly Guywire tower lifting appliance of the safety of lifting.
To achieve these goals, the crane integral assembly Guywire tower lifting appliance that the utility model provides, comprise two steel I-beams that be arranged in parallel and mutually fasten, the interval is welded with welded plate between described two steel I-beams, steel I-beam is all stretched out at the two ends of described welded plate, the two ends of welded plate are fixed with respectively shackle, described unload to buckle be connected with steel rope.
The end that described welded plate stretches out two steel I-beams is respectively equipped with perforate, and bearing pin is installed in the perforate, and described shackle is welded on the bearing pin two ends.
The utility model welds two parallel steel I-beams together by the welded plate that a plurality of intervals arrange, can be with the stress point of balanced pulley of lifting usefulness more to two side shiftings during lifting, the longitudinal pressure of the cross-arm when reducing to lift by crane, the risk that cross-arm fractures when reducing integral lifting, guarantee fully the balance of whole lifting in the lifting process, guaranteed the safety of lifting.
Show by test, the utility model adopts two parallel steel I-beams, in LV40 type hoisting tower pole process, the situation that does not occur tilting and significantly rock, the situation of also being rolled over without the LV40 cross-arm, guaranteed the quality of LV40 type tower, strengthened the safety in the whole work progress, guaranteed to construct and carry out smoothly.
Description of drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 be among Fig. 1 A-A to view;
Among the figure: the 1-steel I-beam; The 2-welded plate; The 3-shackle; The 4-bearing pin; The 5-steel rope.
The specific embodiment
The utility model is described in further detail below in conjunction with embodiment and accompanying drawing.
As depicted in figs. 1 and 2, crane integral assembly Guywire tower lifting appliance comprises two steel I-beams 1 that be arranged in parallel and mutually fasten, the interval is welded with welded plate 2 between two steel I-beams 1, steel I-beam 1 is all stretched out at the two ends of welded plate 2, the two ends of welded plate 2 are fixed with respectively shackle 3, are connected with steel rope 5 in the shackle 3.
The end that welded plate 2 stretches out two steel I-beams 1 is respectively equipped with perforate, and bearing pin 4 is installed in the perforate, and shackle 3 is welded on bearing pin 4 two ends.
During use, crane is arranged in steel tower tower head direction, suspension hook naturally droops directly over the face of steel tower backguy hanging point place, and the suspension hook below is some rope system.Just crane principal arm and the arm width of cloth remain unchanged immediately, cross the suspension hook that hoisting cable 5 connects, and steel tower is slowly detached ground.At tower leg special-purpose pin holder is set, column foot and ground are isolated, both protected the tower material, prevent that also ground from being hauled out groove by column foot, protection of the environment.After tower leg is liftoff, reduce the arm width of cloth by the principal arm brachium that shortens crane, move to iron tower horizontal directly over the basis after, slowly descend hook to be about to steel tower in place to the basis, install again four steel tower backguys of steel tower, namely finish the group tower.Adopt lifting appliance of the present utility model, the required arm width of cloth of crane is minimum, uses the crane of less tonnage just can satisfy construction requirement, has controlled the lease expenses of crane.
Obviously, those skilled in the art can carry out various changes and modification to the utility model and not break away from spirit and scope of the present utility model.Can be another sidewall of casing 1 such as baffle plate 1.2, this type of is revised and modification belongs within the scope of the utility model claim and equivalent technologies thereof, and then the utility model also is intended to comprise these changes and modification interior.
The content that is not described in detail in this specification sheets belongs to the known prior art of this area professional and technical personnel.

Claims (2)

1. crane integral assembly Guywire tower lifting appliance, it is characterized in that: comprise two steel I-beams (1) that be arranged in parallel and mutually fasten, the interval is welded with welded plate (2) between described two steel I-beams (1), steel I-beam (1) is all stretched out at the two ends of described welded plate (2), the two ends of welded plate (2) are fixed with respectively shackle (3), are connected with steel rope (5) in the described shackle (3).
2. crane integral assembly Guywire tower lifting appliance according to claim 1, it is characterized in that: the end that described welded plate (2) stretches out two steel I-beams (1) is respectively equipped with perforate, bearing pin (4) is installed in the perforate, and described shackle (3) is welded on bearing pin (4) two ends.
CN 201220226140 2012-05-18 2012-05-18 Device for lifting guyed tower in integrally assembled mode Expired - Lifetime CN202657825U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220226140 CN202657825U (en) 2012-05-18 2012-05-18 Device for lifting guyed tower in integrally assembled mode

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220226140 CN202657825U (en) 2012-05-18 2012-05-18 Device for lifting guyed tower in integrally assembled mode

Publications (1)

Publication Number Publication Date
CN202657825U true CN202657825U (en) 2013-01-09

Family

ID=47452746

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220226140 Expired - Lifetime CN202657825U (en) 2012-05-18 2012-05-18 Device for lifting guyed tower in integrally assembled mode

Country Status (1)

Country Link
CN (1) CN202657825U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103171972A (en) * 2013-03-01 2013-06-26 上海振华重工集团(南通)有限公司 Tower frame assembling and lifting process
CN112374366A (en) * 2020-11-12 2021-02-19 湖南响箭重工科技股份有限公司 Hoisting system for assembling concrete pump truck supporting leg system and hoisting method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103171972A (en) * 2013-03-01 2013-06-26 上海振华重工集团(南通)有限公司 Tower frame assembling and lifting process
CN112374366A (en) * 2020-11-12 2021-02-19 湖南响箭重工科技股份有限公司 Hoisting system for assembling concrete pump truck supporting leg system and hoisting method thereof
CN112374366B (en) * 2020-11-12 2023-02-28 湖南响箭重工科技股份有限公司 Hoisting system for assembling concrete pump truck supporting leg system and hoisting method thereof

Similar Documents

Publication Publication Date Title
CN202785258U (en) Hoisting device for air overturn of large-sized steel column
CN201882763U (en) Special carrying pole type beam of double-machine lifting crane
CN206502579U (en) Power pole hoisting device
CN203372984U (en) Beam body pulley turnover device
CN103754775A (en) Arm detaching method for swing arm tower crane and auxiliary detaching device
CN202848940U (en) Chamber roof truss overall declining removal device of large gas chamber
CN201495051U (en) Crane jib for flat-top tower crane
CN202657825U (en) Device for lifting guyed tower in integrally assembled mode
CN204310693U (en) A kind of suspension hook being provided with Anti-hook releasing device
CN201737639U (en) Integral inverted hoist
CN103708360B (en) Movable arm tower crane and standard knot introduction system thereof and standard knot introduction method
CN203382365U (en) Lifting appliance system for lifting thin, long and thin-wall equipment integrally
CN202807040U (en) Suspension device for ship bull facade
CN202390116U (en) High-intensity small-tonnage hoist
CN202542743U (en) Auxiliary reeving mechanism for mounting tower crane
CN104942564A (en) Mounting method of large-tonnage pin on jib of offshore shipborne jib type crane
CN202924577U (en) Special hanger frame for small lid of electric furnace
CN202322137U (en) Telescopic hanger
CN202704912U (en) Rope guide device applied to well drilling winch
CN204038909U (en) Mobile hoisting suspension bracket equipment
CN201161868Y (en) Multifunctional lifted crane
CN206033062U (en) Shield constructs machine assembly and slags tap dual -purpose portal crane
CN203271161U (en) Super-high-rise building construction hoist
CN205151579U (en) Two horizontal arm hoists
CN209853545U (en) Hoisting device of desulfurizing tower

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20130326

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130326

Address after: Yang Yuansheng 430063 Hubei province Wuhan city Wuchang District Road No. 5

Patentee after: Hubei Electric Power Transmission & Distribution Engineering Co., Ltd.

Patentee after: State Grid Corporation of China

Address before: Yang Yuansheng 430063 Hubei province Wuhan city Wuchang District Road No. 5

Patentee before: Hubei Electric Transmission & Transformation Engineering Company

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130109