CN202648445U - Low emission sintered ore cooling system - Google Patents
Low emission sintered ore cooling system Download PDFInfo
- Publication number
- CN202648445U CN202648445U CN2012202019704U CN201220201970U CN202648445U CN 202648445 U CN202648445 U CN 202648445U CN 2012202019704 U CN2012202019704 U CN 2012202019704U CN 201220201970 U CN201220201970 U CN 201220201970U CN 202648445 U CN202648445 U CN 202648445U
- Authority
- CN
- China
- Prior art keywords
- cooling system
- sintered ore
- air outlet
- air
- heat exchanger
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P10/00—Technologies related to metal processing
- Y02P10/25—Process efficiency
Landscapes
- Manufacture And Refinement Of Metals (AREA)
Abstract
The utility model relates to the field of raw material sintered ores, in particular to a sintered ore cooling system. A low emission sintered ore cooling system comprises a circular cooling air blower, a circular cooling air box, a circular cooling machine trolley and a seal cover, the seal cover is arranged at the top of the circular cooling machine trolley and completely seals and covers the circular cooling machine trolley, the low emission sintered ore cooling system further comprises a heat exchanger, a dust remover and a booster fan, an air outlet is mounted at the top of the seal cover, the air outlet of the seal cover is connected with an air inlet of the heat exchanger through a heat exchange pipeline, an air outlet of the heat exchanger is connected with an air inlet of the dust remover through a circulation pipeline, and an air outlet of the dust remover is pressurized by the booster fan to be communicated with an air inlet of the circular cooling air blower through a pipeline. According to the low emission sintered ore cooling system, waste heat is recycled by the heat exchanger, then dusty gas is fed into the dust remover to be dedusted, the dedusted gas is circulated back to the circular cooling air blower by the booster fan, balance air quantity can be achieved, zero emission in the surrounding environment can be achieved, the system is energy-saving and environment-friendly, and simultaneously the construction land is not required to be added.
Description
Technical field
The utility model relates to raw material sintering deposit field, relates in particular to a kind of sintered ore cooling system.
Background technology
Cold sinter production is one of important feature of domestic and international sintering process, because cold sinter can carry out sieving under the groove, but reinforcing blast furnace is smelted, reducing coke ratio and prolongation top charging equipment life-span and sintering deposit can transport and material loading with belt feeder, simplify charging equipment, improve the BF Area environment, thereby promoted widely the development of sintering deposit cooling technology.
Can be divided into the exhausting cooling according to the mode of cooling airflow by the thermal sintering ore bed and air blast is cooled off two types to the cooling of sintering deposit.Press Refrigerator structure, can be divided into again and the type such as cool off on belt, ring type, form, tower, disc type, vibration cooled and the machine.Since the sixties in last century, abroad ring type in vogue and two kinds of coolers of belt are cooled to the master with air blast again simultaneously.
Existing a kind of forced-air blast formula annular cooler, circular cooler trolley is driven by the drive unit that motor, reductor, friction roller and friction plate etc. form.Its body is comprised of cooling chassis and walking rails, slewing frame, dust gathering arrester and bellows etc.Also have to give in addition, discharge trough, cooler stand, blast pipe, the ore deposit that falls reclaim equipment and the members such as powder conveyer, plate belt feeder, cooling blower, consisted of whole annular cooler.By the heat sinter after the thermal crusher fragmentation, by sending in the circular cooler trolley for the ore deposit chute.The chassis that is designed to the three-point support structure moves at circuit orbit, the cooling blast that is bloated by cooling blower, enter the sintering ore bed through bellows and chassis stage ventilation grate plate, make heat sinter be cooled to be lower than 150 ℃, cooled sintering deposit is discharged into apron conveyor from discharge trough and transports, and then is transported to whole grain workshop by belt conveyor.
In the air blast cooling procedure, from chassis ventilation grate plate institute powder downstairs, by wind box branch pipe acceptance, be discharged on the drag conveyor through the pneumatic type Double-deck cinder discharge valve, transported by rubber conveyer at last.In addition, be provided with the high-temp waste gas waste-heat recovery device for ore deposit section.Original central cooler adopts preferably seal closure of closure in high temperature section, install at the seal closure semi-open-type that middle low-temperature zone adopts, existing cooling system as shown in Figure 1, on the air inlet of ring cold-blast machine 2 muffler 1 is housed, the air outlet of ring cold-blast machine 2 is connected with ring packaged air conditioner 3 by pipeline, ring packaged air conditioner 3 is arranged on the bottom of circular cooler trolley 4, and seal closure 5 covers on the top of circular cooler trolley 4.In order to guarantee in maximum efficiency heat of cooling sintering deposit of cold wind that blower fan bloats; the ring air-cooler can be purged to a large amount of sintering deposit particles or the breeze that does not burn till in the atmosphere in the running; cause environmental pollution; even no matter be to adopt the chev(e)ron seal cover or adopt whole circle door type cover structure; all can only reduce the bulky grain ore and fly into amount in the atmosphere, also can't avoid the discharging of fine particle dust.
Summary of the invention
Technical problem to be solved in the utility model provides a kind of low emission sintered ore cooling system, by behind the heat exchanger recovery waste heat dusty gas being sent into dedusting in the deduster, in the recycling booster fan circulation winding cold-blast machine, realize the zero-emission to surrounding environment.
The utility model is achieved in that a kind of low emission sintered ore cooling system, comprise ring cold-blast machine, the ring packaged air conditioner, circular cooler trolley and seal closure, described ring cold-blast machine air outlet is connected with the ring packaged air conditioner by pipeline, described ring packaged air conditioner is arranged on the bottom of circular cooler trolley, described seal closure is arranged on the circular cooler trolley top and seals cover circular cooler trolley fully, this cooling system also comprises heat exchanger, deduster and booster fan, described seal closure top is provided with air outlet, the air outlet of seal closure links to each other with the air inlet of heat exchanger by heat exchanging pipe, the air outlet of described heat exchanger links to each other with the air inlet of deduster by circulation line, and the air outlet of deduster is communicated with the air inlet of ring cold-blast machine after by the booster fan supercharging by pipeline.
Be parallel with the bleeder road on the described circulation line, described bleeder is provided with stop valve on the road.
Described deduster is bag dust collector.
Described seal closure is door type seal closure
The utility model low emission sintered ore cooling system is sent dusty gas into dedusting in the deduster after by the heat exchanger recovery waste heat, in the recycling booster fan circulation winding cold-blast machine, reach the balance of air quantity, and can play the zero-emission purpose to surrounding environment, need not the construction land that increases newly in the time of energy-conserving and environment-protective, improvement cost is very low, has widely application value.
Description of drawings
Fig. 1 is existing sintered ore cooling system structural representation;
Fig. 2 is the utility model low emission sintered ore cooling system pipeline schematic diagram.
Among the figure: 1 muffler, 2 ring cold-blast machines, 3 ring packaged air conditioners, 4 circular cooler trolleys, 5 seal closures, 6 heat exchangers, 7 stop valves, 8 dedusters, 9 booster fans, 10 circulation lines.
The specific embodiment
Below in conjunction with specific embodiment, further set forth the utility model.Should be understood that these embodiment only are used for explanation the utility model and are not used in the scope of the present utility model that limits.Should be understood that in addition those skilled in the art can make various changes or modifications the utility model after the content of having read the utility model statement, these equivalent form of values fall within the application's appended claims limited range equally.
As shown in Figure 2, a kind of low emission sintered ore cooling system, comprise ring cold-blast machine 2, ring packaged air conditioner 3, circular cooler trolley 4 and seal closure 5, described ring cold-blast machine 2 air outlets are connected with ring packaged air conditioner 3 by pipeline, described ring packaged air conditioner 3 is arranged on the bottom of circular cooler trolley 4, described seal closure 5 is arranged on circular cooler trolley 4 tops and seals cover circular cooler trolley 4 fully, this cooling system also comprises heat exchanger 6, deduster 8 and booster fan 9, described seal closure 5 tops are provided with air outlet, the air outlet of seal closure 5 links to each other by the air inlet of heat exchanging pipe with heat exchanger 6, the air outlet of described heat exchanger 6 links to each other with the air inlet of deduster 8 by circulation line 10, and the air outlet of deduster 8 is communicated with the air inlet that encircles cold-blast machine 2 after by booster fan 9 superchargings by pipeline; In the present embodiment, described deduster 8 is bag dust collector, and described seal closure 5 is door type seal closure.
The utility model can further describe into, be parallel with the bleeder road on the described circulation line 10, described bleeder is provided with stop valve 7 on the road.
This cooling system when work, carry out waste heat recovery by heat exchanger 6, reclaim thermal source and can produce the mixing that hot water about 80 ℃ is used for sintering feed, take full advantage of waste heat, the gas temperature that enters in the deduster 8 is reduced, can the scaling loss filter bag etc. equipment.The stop valve 7 that arranges on the bleeder road, generally close stop valve 7, the dusty gas that door type seal closure is discharged is got back in the central cooler air blast by bag dust collector and booster fan, reaches the balance of air quantity, and can play the zero-emission purpose to surrounding environment.
The air quantity of booster fan 9 is used for compensation because the loss such as the resistance of the bed of material, filter bag resistance damage on the circular cooler trolley 4 also can prevent surge and the turbulent flow vibration of cooling blast.
In addition, the dust that bag dust collector produces is rich in ferro element, can return the stock yard utilization, and bag dust collector and booster fan can be arranged on the inner existing vacant lot of central cooler, can not increase for the construction land of the cold project of whole sintered ring.
Claims (4)
1. low emission sintered ore cooling system, comprise ring cold-blast machine (2), ring packaged air conditioner (3), circular cooler trolley (4) and seal closure (5), described ring cold-blast machine (2) air outlet is connected with ring packaged air conditioner (3) by pipeline, described ring packaged air conditioner (3) is arranged on the bottom of circular cooler trolley (4), it is characterized in that: described seal closure (5) is arranged on circular cooler trolley (4) top and seals cover circular cooler trolley (4) fully, this cooling system also comprises heat exchanger (6), deduster (8) and booster fan (9), described seal closure (5) top is provided with air outlet, the air outlet of seal closure (5) links to each other by the air inlet of heat exchanging pipe with heat exchanger (6), the air outlet of described heat exchanger (6) links to each other with the air inlet of deduster (8) by circulation line (10), and the air outlet of deduster (8) is communicated with the air inlet that encircles cold-blast machine (2) after by booster fan (9) supercharging by pipeline.
2. low emission sintered ore cooling system as claimed in claim 1, it is characterized in that: described circulation line is parallel with the bleeder road on (10), is provided with stop valve (7) on the described bleeder road.
3. low emission sintered ore cooling system as claimed in claim 1 or 2, it is characterized in that: described deduster (8) is bag dust collector.
4. low emission sintered ore cooling system as claimed in claim 1 or 2 is characterized in that: described seal closure (5) is a door type seal closure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012202019704U CN202648445U (en) | 2012-05-08 | 2012-05-08 | Low emission sintered ore cooling system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012202019704U CN202648445U (en) | 2012-05-08 | 2012-05-08 | Low emission sintered ore cooling system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202648445U true CN202648445U (en) | 2013-01-02 |
Family
ID=47417542
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012202019704U Expired - Lifetime CN202648445U (en) | 2012-05-08 | 2012-05-08 | Low emission sintered ore cooling system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202648445U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103557172A (en) * | 2013-11-13 | 2014-02-05 | 灌阳县贵达有色金属有限公司 | Control device for annular cooling blower |
-
2012
- 2012-05-08 CN CN2012202019704U patent/CN202648445U/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103557172A (en) * | 2013-11-13 | 2014-02-05 | 灌阳县贵达有色金属有限公司 | Control device for annular cooling blower |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103934082A (en) | Novel mineral slag grinding system | |
CN105021049B (en) | Vertical type cooling tower and sintering waste heat utilization system | |
CN203862359U (en) | Novel slag grinding system | |
CN202853402U (en) | High-efficient heat recovery type sinter mine cooling system | |
CN105066718B (en) | Comprehensive utilization system for sintering waste heat | |
CN203454809U (en) | Cylindrical cooling device for thermal-state mineral blocky-shaped particles | |
CN205014851U (en) | Sintering deposit shows heat reclamation device | |
CN107883776B (en) | Cooling machine and cooling method for efficient composite vertical cement calcination clinker | |
CN108007219A (en) | A kind of hot ore deposit cooling and residual neat recovering system | |
CN204902609U (en) | System is used multipurposely to sintering waste heat | |
CN202648445U (en) | Low emission sintered ore cooling system | |
CN204923908U (en) | System is used multipurposely to sintering cooling tower and sintering waste heat | |
CN209960986U (en) | Closed three-stage vertical cold sinter cooling system | |
CN201007613Y (en) | Improved circle-cooling machine | |
CN201495233U (en) | Cooling tank for high-temperature solid slag particles | |
CN206862143U (en) | A kind of vertical ore deposit black furnace | |
CN107300327A (en) | A kind of drying and preheating new method of pelletizing production | |
CN209877658U (en) | Waste heat efficient recovery and comprehensive utilization system of rotary vertical type cooler for sintered ore | |
CN103789535B (en) | Recovery system and method of magnetized cinder of high-Fe sulfuric acid | |
CN201619189U (en) | Novel inclined groove type cement cooling device | |
CN203700451U (en) | Recovering system for high iron sulfuric acid magnetized slag | |
CN101774771A (en) | Novel oblique slot type cement cooling device | |
CN102374821B (en) | Rectification and guidance combined forced air cooling multi-tube cooler | |
CN205095923U (en) | Powder device is received to chrome iron ore low temperature drying grind gradings that ally oneself with more | |
CN219244300U (en) | Vertical cooling waste heat recovery production system for pellets |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20130102 |
|
CX01 | Expiry of patent term |