CN202627017U - 预制装配整体式风力发电机基础 - Google Patents

预制装配整体式风力发电机基础 Download PDF

Info

Publication number
CN202627017U
CN202627017U CN 201220298691 CN201220298691U CN202627017U CN 202627017 U CN202627017 U CN 202627017U CN 201220298691 CN201220298691 CN 201220298691 CN 201220298691 U CN201220298691 U CN 201220298691U CN 202627017 U CN202627017 U CN 202627017U
Authority
CN
China
Prior art keywords
foundation
cast
core cylinder
cover plate
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220298691
Other languages
English (en)
Inventor
张晓晶
袁金西
李育玲
叶祖林
袁铁柱
戚俊峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Wind Power Engineering Consultant Co Ltd
Original Assignee
Xinjiang Wind Power Engineering Consultant Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Wind Power Engineering Consultant Co Ltd filed Critical Xinjiang Wind Power Engineering Consultant Co Ltd
Priority to CN 201220298691 priority Critical patent/CN202627017U/zh
Application granted granted Critical
Publication of CN202627017U publication Critical patent/CN202627017U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Wind Motors (AREA)

Abstract

本实用新型涉及一种采用预制构件与现浇构件相结合的预制装配整体式风力发电机基础,由核心圆柱、外环梁、斜梁、基础底板、联接节点、预制盖板和现浇盖板构成圆形筏板式基础,整体埋设在基坑内,基坑底面浇筑圆形基础底板,基础底板中心处为核心圆柱。外环梁沿基础底板的外圆周分为多段布设,在外环梁与核心圆柱间呈轴对称布设斜梁,斜梁一端与两段外环梁交接处设联接节点。在两两斜梁顶部设预制盖板,预制盖板顶面浇筑现浇盖板。在核心圆柱内嵌固有基础环,基础环由基础环支架支撑。本实用新型适应性强、施工方便,且可缩短施工周期、降低造价、减少现场投入人工及机械、减少建筑垃圾、提高工程质量、没有板式基础大体积混凝土水化热高的问题。

Description

预制装配整体式风力发电机基础
技术领域
 本实用新型涉及一种风力发电机基础,尤其涉及一种采用预制构件与现浇构件相结合的预制装配整体式风力发电机基础。
背景技术
目前风力发电行业中,风力发电机基础一般采用现浇板式钢筋混凝土基础,这种基础是利用基础混凝土及基坑回填土的自重和板下地基土的反力,来平衡高耸的风力机塔筒及叶片因风荷载产生的弯矩作用。这种基础因混凝土与土壤接触面积小,在基础混凝土耐久性等方面有一定优势。但是该基础的埋深受到塔筒预埋在基础内的基础环高度限制,基础环高度一般约为2m左右,基础环露出地面高度约为0.5m,预埋在基础内的高度约为1.5m,如上部荷载偏大、地基土的上部土层承载力较小,基础需要加大埋深,只能靠增加板厚来实现,而基础平面尺寸相对固定,最终导致基础消耗的混凝土及钢筋工程量较大,造价提高;且板式基础属于大体积混凝土,施工现场混凝土凝固时产生的水化热问题难以解决,过高水化热导致混凝土表面开裂较严重。
板式基础所有构件的钢筋绑扎、模板支设、混凝土浇筑均在现场由人工操作完成,工期非常长,人工、机械消耗量大;风电场的选址一般在人烟稀少的戈壁及荒漠地带,施工用水、用电、人员技术力量都得不到有效保证,且施工条件受天气影响很大,最终导致工期及工程质量受到影响。
本实用新型在基础工程中,尤其是风力发电机基础行业还未见应用及报道。
发明内容
本实用新型的目的在于提出一种适应性强、造价低、装配快捷,可大幅缩短施工周期的预制装配整体式风力发电机基础。
本实用新型的目的是这样实现的:预制装配整体式风力发电机基础由核心圆柱、外环梁、斜梁、基础底板、联接节点、预制盖板和现浇盖板构成圆形筏板式基础,整体埋设在地面下的基坑内,基坑底面进行抄平作业,浇筑混凝土,形成圆形基础垫层,基础垫层顶面做圆形基础底板,基础底板中心处为核心圆柱。外环梁沿基础底板的外圆周分为多段布设,在外环梁与核心圆柱间呈轴对称布设斜梁,斜梁一端与两段外环梁交接处设联接节点。在两两斜梁顶部设置预制盖板,预制盖板顶面浇筑现浇盖板。在核心圆柱内嵌固有基础环,基础环由基础环支架支撑。
本实用新型把主要受力构件一部分交由工厂或特定的加工场地预制生产,运送至现场安装就位后,将连接部分现场现浇而形成一个整体结构。它结合了整体式结构和装配式结构这两者的优点。这种结构在确保结构整体性不受削弱的条件下,其优势在于:对于各种不同地基的适应性强、基础混凝土总的工程量比板式基础可减少约50%,施工方便,且可缩短施工周期、降低造价、减少现场投入人工及机械、减少建筑垃圾、提高工程质量、没有板式基础大体积混凝土水化热高的问题等。符合国家建筑工程工厂化的发展方向及节能减排要求,是工程中一种较理想的结构。
附图说明:本实用新型的具体结构由以下的附图和实施例给出:
图1是预制装配整体式风力发电机基础俯视结构示意图;
图2是预制装配整体式风力发电机基础俯视结构示意图的A—A剖视图;
图3是预制装配整体式风力发电机基础俯视结构示意图的B—B剖视图。
图例:1、外环梁,2、斜梁,3、联接节点,4、核心圆柱,5、基础环,6、现浇盖板,7、基础底板,8、地面,9、预制盖板,10、基础环支架,11、基础垫层。
具体实施方式:
本实用新型不受下述实施例的限制,可根据本实用新型的技术方案与实际情况来确定具体的实施方式。
实施例:如图1—3所示,预制装配整体式风力发电机基础由核心圆柱4、外环梁1、斜梁2、基础底板7、联接节点3、预制盖板9和现浇盖板6构成圆形筏板式基础。基础底板7、核心圆柱4、联接节点3、现浇盖板6均为现浇钢筋混凝土构件。斜梁2、外环梁1、预制盖板9为预制钢筋混凝土构件。基础环5、基础环支架10均由风机厂家提供。本实用新型基础埋设在地面8下的基坑内,基坑底面进行抄平作业,浇筑混凝土,形成圆形基础垫层11,基础垫层11顶面做圆形基础底板7,基础底板7中心处为核心圆柱4。外环梁1沿基础底板7的外圆周分为多段布设,在外环梁1与核心圆柱4间呈轴对称布设斜梁2,斜梁2一端与两段外环梁1交接处设联接节点3。在两两斜梁2顶部设置预制盖板9,预制盖板9顶面浇筑现浇盖板6。在核心圆柱4内嵌固有基础环5,基础环5由基础环支架10支撑。
以上技术特征构成了本实用新型的最佳实施例,可根据实际情况增减本实用新型的非必要技术特征,以满足实际需要。

Claims (3)

1.一种预制装配整体式风力发电机基础,由核心圆柱、外环梁、斜梁、基础底板、联接节点、预制盖板和现浇盖板构成圆形筏板式基础,整体埋设在地面下的基坑内,基坑底面进行抄平作业,浇筑混凝土,形成圆形基础垫层,其特征在于:基础垫层顶面做圆形基础底板,基础底板中心处为核心圆柱,外环梁沿基础底板的外圆周分为多段布设,在外环梁与核心圆柱间呈轴对称布设斜梁,斜梁一端与两段外环梁交接处设联接节点,在两两斜梁顶部设置预制盖板,预制盖板顶面浇筑现浇盖板,在核心圆柱内嵌固有基础环,基础环由基础环支架支撑。
2.如权利要求1所述的预制装配整体式风力发电机基础,其特征在于:基础底板、核心圆柱、联接节点、现浇盖板均为现浇钢筋混凝土构件。
3.如权利要求1所述的预制装配整体式风力发电机基础,其特征在于:斜梁、外环梁、预制盖板为预制钢筋混凝土构件。
CN 201220298691 2012-06-25 2012-06-25 预制装配整体式风力发电机基础 Expired - Fee Related CN202627017U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220298691 CN202627017U (zh) 2012-06-25 2012-06-25 预制装配整体式风力发电机基础

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220298691 CN202627017U (zh) 2012-06-25 2012-06-25 预制装配整体式风力发电机基础

Publications (1)

Publication Number Publication Date
CN202627017U true CN202627017U (zh) 2012-12-26

Family

ID=47380228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220298691 Expired - Fee Related CN202627017U (zh) 2012-06-25 2012-06-25 预制装配整体式风力发电机基础

Country Status (1)

Country Link
CN (1) CN202627017U (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147454A (zh) * 2013-03-01 2013-06-12 江苏九鼎环球建设科技集团有限公司 一种钢结构厂房预制基础结构
CN103912007A (zh) * 2014-03-14 2014-07-09 中国水电顾问集团西北勘测设计研究院有限公司 预留基础环孔和桩窝环孔的预制混凝土承台及基于该承台的装配式多桩基础的安装方法
CN103912006A (zh) * 2014-03-14 2014-07-09 中国水电顾问集团西北勘测设计研究院有限公司 一种装配式多桩基础结构及其承建方法
CN104674839A (zh) * 2015-02-26 2015-06-03 北海和思科技有限公司 一种风力发电机基础结构
CN106958259A (zh) * 2017-05-24 2017-07-18 中国航空规划设计研究总院有限公司 一种混凝土塔柱基础及其施工方法
CN108005099A (zh) * 2017-11-24 2018-05-08 国网江苏省电力公司南京供电公司 一种杆塔预制装配式混凝土阶梯形基础及其拼装方法
WO2020174334A1 (de) * 2019-02-28 2020-09-03 Holcim Technology Ltd Fundament für eine windkraftanlage
WO2022252754A1 (zh) * 2021-06-03 2022-12-08 中国华能集团清洁能源技术研究院有限公司 一种预制装配与现浇砼组合式风机基础

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147454A (zh) * 2013-03-01 2013-06-12 江苏九鼎环球建设科技集团有限公司 一种钢结构厂房预制基础结构
CN103912007A (zh) * 2014-03-14 2014-07-09 中国水电顾问集团西北勘测设计研究院有限公司 预留基础环孔和桩窝环孔的预制混凝土承台及基于该承台的装配式多桩基础的安装方法
CN103912006A (zh) * 2014-03-14 2014-07-09 中国水电顾问集团西北勘测设计研究院有限公司 一种装配式多桩基础结构及其承建方法
CN103912007B (zh) * 2014-03-14 2016-05-25 中国电建集团西北勘测设计研究院有限公司 预留基础环孔和桩窝环孔的预制混凝土承台及基于该承台的装配式多桩基础的安装方法
CN104674839A (zh) * 2015-02-26 2015-06-03 北海和思科技有限公司 一种风力发电机基础结构
CN106958259A (zh) * 2017-05-24 2017-07-18 中国航空规划设计研究总院有限公司 一种混凝土塔柱基础及其施工方法
CN106958259B (zh) * 2017-05-24 2019-01-15 中国航空规划设计研究总院有限公司 一种混凝土塔柱基础及其施工方法
CN108005099A (zh) * 2017-11-24 2018-05-08 国网江苏省电力公司南京供电公司 一种杆塔预制装配式混凝土阶梯形基础及其拼装方法
CN108005099B (zh) * 2017-11-24 2023-08-15 国网江苏省电力公司南京供电公司 一种杆塔预制装配式混凝土阶梯形基础及其拼装方法
WO2020174334A1 (de) * 2019-02-28 2020-09-03 Holcim Technology Ltd Fundament für eine windkraftanlage
WO2022252754A1 (zh) * 2021-06-03 2022-12-08 中国华能集团清洁能源技术研究院有限公司 一种预制装配与现浇砼组合式风机基础

Similar Documents

Publication Publication Date Title
CN202627017U (zh) 预制装配整体式风力发电机基础
CN105735325B (zh) 一种集约化的永久支护装配式地下室结构体系及施工方法
CN103867019B (zh) 装配式体外预应力活性粉末混凝土风电塔架
CN203755778U (zh) 装配式体外预应力活性粉末混凝土风电塔架
CN103046575B (zh) 一种陆上四叶梅型的风机扩展基础结构
CN102995655A (zh) 筒型结构与群桩组合式海上风力机地基基础
CN105544593A (zh) 基础预制预应力梁板式风力发电塔基础
CN109295994B (zh) 一种全装配式组合结构风电塔筒基础
CN102720207A (zh) 一种塔架基础及风力发电机的塔架
CN201865084U (zh) 组合连拱式钢构坝
CN112012238A (zh) 一种带预制混凝土压块的吸力桶基础
CN106381886A (zh) 一种部分预制拼装钢混凝土组合地下综合管廊
CN109024661A (zh) 风力发电机组基础加固系统
CN102359118B (zh) 地下连续墙环形基础及其建造方法
CN203640084U (zh) 一种可恢复功能的叠合板式剪力墙
CN208039265U (zh) 一种预制装配式组合结构支撑
CN113463664A (zh) 一种干连接蜂窝状装配式格梁护坡结构
CN112575797A (zh) 一种用于基坑支护的装配式型钢-混凝土支撑杆件
CN112575789A (zh) 斜拉式空间桁架基坑内支撑体系
CN202247719U (zh) 对应形波纹预应力抗沉降桥梁涵管
CN201981549U (zh) 预制电杆桩
CN115928785A (zh) 适用于山地区域的风电阶梯型装配式基础及其装配方法
CN201620330U (zh) 一种瓦片型急流槽
CN204023774U (zh) 一种装配式复合结构抗震墙
CN210766887U (zh) 一种永临结合地下槽型结构

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121226

Termination date: 20210625