CN202577334U - Pouring straining beam structure of pile foundation cushion cap - Google Patents

Pouring straining beam structure of pile foundation cushion cap Download PDF

Info

Publication number
CN202577334U
CN202577334U CN 201220209597 CN201220209597U CN202577334U CN 202577334 U CN202577334 U CN 202577334U CN 201220209597 CN201220209597 CN 201220209597 CN 201220209597 U CN201220209597 U CN 201220209597U CN 202577334 U CN202577334 U CN 202577334U
Authority
CN
China
Prior art keywords
straining beam
pile foundation
preformed groove
support table
foundation support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220209597
Other languages
Chinese (zh)
Inventor
陆欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN 201220209597 priority Critical patent/CN202577334U/en
Application granted granted Critical
Publication of CN202577334U publication Critical patent/CN202577334U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a pouring straining beam structure of a pile foundation cushion cap, which comprises the pile foundation cushion cap (1) and a straining beam (2), wherein the straining beam is a precasting beam, the straining beam is internally provided with reinforcing steel bars (3), and the reinforcing steel bars extend out from both ends of the straining beam; a preformed groove (4) is arranged on the pile foundation cushion cap, and the straining beam is overlapped with both ends of the preformed groove; the preformed groove is internally provided with preformed steel dowels (5), the preformed steel dowels are connected with the reinforcing steel bars extending outside the straining beam, and the preformed groove is internally poured with concrete (6). The integral structure of pile foundation cushion cap and straining beam which is integrally poured on site is converted into the manner that the pile foundation cushion cap is firstly poured and then the preformed straining beam is integrally poured with the pile foundation cushion cap; and therefore, the construction difficulty is greatly reduced under the condition of ensuring the strength of the straining beam.

Description

Pile foundation support table is built the straining beam structure
Technical field
the utility model relates to a kind of pile foundation support table and builds the straining beam structure, belongs to the building structure technology field.
Background technology
are in pile foundation engineering, because of the straining beam that is connected with pile foundation support table need bear bigger pulling force and moment of flexure, so present straining beam generally all is a continuous beam.Straining beam is built moulding with the pile foundation support table disposable integral in the construction, and this job practices need be set up full hall scaffold, constructional difficulties.
Summary of the invention
The purpose of the utility model is, provides a kind of pile foundation support table to build the straining beam structure.Change whole straining beam into segmental structure,, overcome the deficiency of prior art to reduce difficulty of construction.
The technical scheme of the utility model:
a kind of pile foundation support table is built the straining beam structure, comprises pile foundation support table and straining beam, and said straining beam is the beam of precoating, and is provided with reinforcing bar in the straining beam, and reinforcing bar stretches out from the straining beam two ends; Pile foundation support table is provided with preformed groove, straining beam and preformed groove overlap joint; Be provided with the reservation joint bar in the preformed groove, reserve joint bar and be connected, built concrete in the preformed groove with the overhanging reinforcing bar of straining beam.
aforementioned pile foundation support table is built in the straining beam structure, and the width of said preformed groove equals the width of straining beam, and the degree of depth of preformed groove equals the height of straining beam, and the straining beam top of overlap joint in preformed groove is concordant with the pile foundation support table top.
aforementioned pile foundation support table is built in the straining beam structure, reinforcing bar welding or bind in said reservation joint bar and the straining beam.
aforementioned pile foundation support table is built in the straining beam structure, and the reinforcing bar in the material of said reservation joint bar and diameter and the straining beam is identical.
aforementioned pile foundation support table is built in the straining beam structure, and said reservation joint bar is one group of whole reinforcing bar.
compared with prior art; The utility model has made to build earlier the one pile foundation support table and the straining beam structure of on-the-spot monobloc cast into pile foundation support table, when building pile foundation support table; Reservation is used for the preformed groove that is connected with straining beam, is provided with the reservation joint bar in the preformed groove; Prefabricated straining beam rides in the preformed groove in advance then; The reinforcing bar that the lacing wire outside of overlap joint in preformed groove exposed reservation joint bar in the pre-buried pile foundation support table when building pile foundation support table welds together; Make pile foundation support table reserve joint bar and connect into integral body with prefabricated straining beam exposed steel bar in advance, at last with concreting in preformed groove, prefabricated straining beam and pile foundation support table built be integral; Under the situation of guaranteeing straining beam intensity, reduced difficulty of construction greatly.
Description of drawings
Fig. 1 is the structural representation of the utility model;
Fig. 2 is the sectional view of Fig. 1;
Fig. 3 is the sketch map of pile foundation support table;
Fig. 4 is the sketch map of prefabricated straining beam.
Being labeled as in accompanying drawing: the 1-pile foundation support table, the 2-straining beam, the 3-reinforcing bar, the 4-preformed groove, 5-reserves joint bar, 6-concrete.
The specific embodiment
are done further to specify to the utility model below in conjunction with accompanying drawing and embodiment, but not as any restriction to the utility model.
embodiment.
the utility model is as depicted in figs. 1 and 2.A kind of pile foundation support table is built the straining beam structure, comprises pile foundation support table 1 and straining beam 2, and said straining beam 2 is the beam of precoating, and is provided with reinforcing bar 3 in the straining beam 2, and reinforcing bar 3 stretches out from straining beam 2 two ends; Pile foundation support table 1 is provided with preformed groove 4, straining beam 2 and preformed groove 4 overlap joints; Be provided with in the preformed groove 4 and reserve joint bar 5, reserving joint bar 5 is one group of whole reinforcing bar.Reserve joint bar 5 and weld or binds, built concrete 6 in the preformed groove 4 with straining beam 2 overhanging reinforcing bars 3.The width of said preformed groove 4 equals the width of straining beam 2, and the degree of depth of preformed groove 4 equals the height of straining beam 2, and straining beam 2 tops of overlap joint in preformed groove 4 are concordant with pile foundation support table 1 top.The material of said reservation joint bar 5 and diameter are identical with reinforcing bar 3 in the straining beam 2.
The concrete work progress and the principle of the utility model
are as shown in Figure 1, build pile foundation support table as shown in Figure 31 earlier, when building pile foundation support table, reserve and to be used for the preformed groove 4 that is connected with straining beam, and preformed groove is divided into two sections and is symmetrical set, and is provided with in the preformed groove to reserve joint bar 5; Prefabricated straining beam 2 rides in the preformed groove in advance then, and straining beam is as shown in Figure 4, when prefabricated straining beam, in straining beam, is embedded with reinforcing bar 3, and stretch out from the straining beam two ends at the two ends of reinforcing bar.The reservation joint bar 5 that the reinforcing bar that the lacing wire outside of overlap joint in preformed groove exposed is embedded in the pile foundation support table when building pile foundation support table welds together; Make pile foundation support table reserve joint bar and connect into integral body with prior prefabricated straining beam exposed steel bar; Use concreting at last in preformed groove; Prefabricated straining beam and pile foundation support table built be integral, under the situation of guaranteeing straining beam intensity, reduced difficulty of construction greatly.

Claims (5)

1. a pile foundation support table is built the straining beam structure, comprises pile foundation support table (1) and straining beam (2), and it is characterized in that: said straining beam (2) is the beam of precoating, and is provided with reinforcing bar (3) in the straining beam (2), and reinforcing bar (3) stretches out from straining beam (2) two ends; Pile foundation support table (1) is provided with preformed groove (4), straining beam (2) and preformed groove (4) overlap joint; Be provided with in the preformed groove (4) and reserve joint bar (5), reserve joint bar (5) and be connected, built concrete (6) in the preformed groove (4) with the overhanging reinforcing bar (3) of straining beam (2).
2. build the straining beam structure according to the said pile foundation support table of claim 1; It is characterized in that: the width of said preformed groove (4) equals the width of straining beam (2); The degree of depth of preformed groove (4) equals the height of straining beam (2), and straining beam (2) top of overlap joint in preformed groove (4) is concordant with pile foundation support table (1) top.
3. build the straining beam structure according to the said pile foundation support table of claim 1, it is characterized in that: said reservation joint bar (5) and interior reinforcing bar (3) welding or the bind of straining beam (2).
4. build the straining beam structure according to the said pile foundation support table of claim 1, it is characterized in that: the reinforcing bar (3) in the material of said reservation joint bar (5) and diameter and the straining beam (2) is identical.
5. build the straining beam structure according to the said pile foundation support table of claim 1, it is characterized in that: said reservation joint bar (5) is one group of whole reinforcing bar.
CN 201220209597 2012-05-11 2012-05-11 Pouring straining beam structure of pile foundation cushion cap Expired - Fee Related CN202577334U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220209597 CN202577334U (en) 2012-05-11 2012-05-11 Pouring straining beam structure of pile foundation cushion cap

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220209597 CN202577334U (en) 2012-05-11 2012-05-11 Pouring straining beam structure of pile foundation cushion cap

Publications (1)

Publication Number Publication Date
CN202577334U true CN202577334U (en) 2012-12-05

Family

ID=47246763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220209597 Expired - Fee Related CN202577334U (en) 2012-05-11 2012-05-11 Pouring straining beam structure of pile foundation cushion cap

Country Status (1)

Country Link
CN (1) CN202577334U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484280A (en) * 2015-12-30 2016-04-13 安徽上能管桩混凝土有限公司 Corrosion-resistance industrial factory building concrete cup opening prefabricated bearing platform
CN109339087A (en) * 2018-10-08 2019-02-15 贺州通号装配式建筑有限公司 A kind of foundation structure system of low-rise building
CN109339088A (en) * 2018-10-08 2019-02-15 贺州通号装配式建筑有限公司 A kind of low-rise building

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484280A (en) * 2015-12-30 2016-04-13 安徽上能管桩混凝土有限公司 Corrosion-resistance industrial factory building concrete cup opening prefabricated bearing platform
CN109339087A (en) * 2018-10-08 2019-02-15 贺州通号装配式建筑有限公司 A kind of foundation structure system of low-rise building
CN109339088A (en) * 2018-10-08 2019-02-15 贺州通号装配式建筑有限公司 A kind of low-rise building
CN109339088B (en) * 2018-10-08 2023-10-27 贺州通号装配式建筑有限公司 Low-rise building
CN109339087B (en) * 2018-10-08 2023-10-27 贺州通号装配式建筑有限公司 Infrastructure system of low-rise building

Similar Documents

Publication Publication Date Title
CN104746422B (en) A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method
CN103790379B (en) In contrary sequence method without the construction method of connected node between beam slab and cap
CN205531315U (en) Can dismantle steel bar truss building carrier plate support system
CN107327030A (en) The plate-column structure node and its cap prefabricated components and construction method of a kind of steel column
CN108677685A (en) A kind of ultra-high performance concrete-part girder steel combination bent cap and its construction method
CN102704603A (en) Concrete superposed beam
CN202466845U (en) Middle-layer node connecting structure for steel tube concrete column and steel reinforced concrete beam
CN202577334U (en) Pouring straining beam structure of pile foundation cushion cap
CN206174195U (en) Assembled concrete shear force wall split, assemble connection structure
CN109183628A (en) A kind of ultra-large type variable cross-section Sarasota reinforcing bar component production method
CN108104505A (en) The reinforced construction method of concrete floor
CN103669720A (en) Precast beam and reinforced concrete structure with tenon anchor system
CN106638686A (en) Comprehensive pipe gallery with corrugated steel plate shear walls and construction method of comprehensive pipe gallery
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN209556195U (en) Fabricated Beam-Slab connection structure
CN202466844U (en) Top layer node connecting structure for concrete-filled steel tube column and steel reinforced concrete beam
CN102704602A (en) Concrete superposed heat preservation edge beam
CN208293400U (en) A kind of ultra-high performance concrete-part girder steel combination bent cap
CN207812181U (en) Track, track girder and its crane beam
CN109537775A (en) The method for preparing assembly concrete shear wall using local corrugated thin-wall steel pipe
CN203034353U (en) Connection structure of bridge support padstone and abutment
CN101845862B (en) Manufacture method of ribbed superposed prestress reinforced concrete precast slab
CN104047223A (en) Light composite structure bridge and construction method thereof
CN203924484U (en) A kind of precast beam and there is the reinforced concrete structure of tenon anchor system
CN102092096B (en) Method for fixing pre-stressed hose of precast beam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121205

Termination date: 20150511

EXPY Termination of patent right or utility model