CN202577138U CN201220257650.0U CN201220257650U CN202577138U CN 202577138 U CN202577138 U CN 202577138U CN 201220257650 U CN201220257650 U CN 201220257650U CN 202577138 U CN202577138 U CN 202577138U
Authority
CN
China
Prior art keywords
steel plate
bearing
conjuncted
integrated
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201220257650.0U
Other languages
Chinese (zh)
Inventor
朱波
黄锦源
刘晓苹
吴刚
周成
钟小军
卢兴
丁佳元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Co ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Co ltd filed Critical Shanghai Urban Construction Design Research Institute Co ltd
Priority to CN201220257650.0U priority Critical patent/CN202577138U/en
Application granted granted Critical
Publication of CN202577138U publication Critical patent/CN202577138U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses an integrated support suitable for mounting precast beams, comprising an integrated steel plate, wherein a plurality of upper locating connection members fixedly connected with the precast beams are arranged at the upper side of the integrated steel plate; the lower side of the integrated steel plate is fixedly connected with a first support main body through a first upper steel plate and is fixedly connected with a second support main body through a second upper steel plate; the upper locating connection members are located between the first support main body and the second support main body; a first lower steel plate is further fixedly arranged below the first support main body; a second lower steel plate is further fixedly arranged below the second support main body; and a plurality of lower locating connection members fixedly connected with pier capping beams are respectively arranged on the first lower steel plate and the second lower steel plate. The integrated steel plate on the integrated support and the precast beam are integrated into a whole, thus the integrated support is more durable, close contact among the integrated support, the upper-part precast beams and the lower-part pier capping beams can be guaranteed by construction of cast-in-situ cushion blocks; and the integrated support suitable for mounting the precast beams has the advantages of firm connection, convenience for construction and the like.

Description

Be applicable to the conjuncted bearing that precast beam is installed
Technical field
The utility model relates to road and bridge building technology field, relates in particular to a kind of conjuncted bearing that is applicable to that precast beam is installed.
Background technology
The bearing that is installed at present at the bottom of the precast beam adopts patterns such as common laminated rubber bearing, pot rubber bearing, ball shaped steel bearing, lead core rubber support usually.
The carrying tonnage of common laminated rubber bearing is less; Frictionally and upper and lower part structure interrelate, and lean on the shear strain of himself to adapt to the flexible of bridge, but can not resist bigger horizontal force and distortion demand; Owing to reasons such as material agings, service life is short, durability is relatively poor.
The bearing of forms such as pot rubber bearing, ball shaped steel bearing, lead core rubber support, service life is long, durability is better, the bearing tonnage is bigger, in overhead road of city bridge and highway bridge, uses comparatively general.These bearings all carry positioning bolt, can stretch into the beam that is positioned at its top and be positioned at the bridge bent cap of its underpart, thereby can guarantee the reliable connection between the structure of upper and lower part.
But when superstructure was precast beam, the construction technique of these bearings can be very complicated.Common mounting method is: when the bridge pier bent cap of cast-in-place bottom, reserve bearing positioning bolt hole at the top of bent cap, the while is pre-buried connection steel plate at the bottom of the beam of the precast beam on top; Positioning bolt with the bearing bottom inserts in the reserving hole on the bridge pier bent cap of reserving then; And the hole of positioning bolt taked grouting treatment; When treating that the beam lifting is set up, with basin steel plate welding on steel plate and the bearing at the bottom of the beam of top beam, make bearing be connected in aggregates again with the upper and lower part structure.
According to the requirement of existing highway bridge and culvert standard, when bearing is arranged on the great slope, should between at the bottom of abutment surface and the beam, the bearing cushion block be set, make bearing maintenance level.No matter adopt the bearing of any type, need the bearing cushion block to be set at the bottom of beam when all existing the gradient big so that the problem of bearing maintenance level.In order to satisfy aforesaid technical requirements, when making precast beam, the cushion block according on the prefabricated bearing of the vertical and horizontal gradient of bridge sticks on Liang Dishang usually.But this technical scheme still is 4 supports on the one hand, is difficult to adapt to the natural law of three faces, is difficult for closely connected, discontinuity with bearing at the bottom of the precast beam, the noise in the time of can increasing driving.On the other hand, along with the increase of cushion block kind, quantity, all bring great difficulty for construction cost, management, quality control.
Therefore, those skilled in the art be devoted to develop a kind of fit tight, stressed evenly, construction is applicable to the conjuncted bearing that precast beam is installed easily.
The utility model content
Because the above-mentioned defective of prior art, the utility model technical problem to be solved provide a kind of fit tight, stressed evenly, construction is applicable to the conjuncted bearing that precast beam is installed easily.
For realizing above-mentioned purpose, the utility model provides a kind of conjuncted bearing that is applicable to that precast beam is installed, and comprises a conjuncted steel plate; The upside of said conjuncted steel plate is provided with a plurality of positioning links of going up that are fixedly connected with precast beam; The downside of said conjuncted steel plate is fixedly connected with first support body through first upper steel plate, is fixedly connected with second support body through second upper steel plate; The said positioning link of going up is between said first support body and said second support body; The below of said first support body also is set with first lower steel plate, and the below of said second support body also is set with second lower steel plate; Be respectively arranged with a plurality of positioning links down that are fixedly connected with the bridge pier bent cap on said first lower steel plate, said second lower steel plate.
Preferably, said first upper steel plate, said second upper steel plate are fixedly connected with said conjuncted steel plate through connecting bolt respectively.
Preferably, said upward positioning link, said positioning link down are connecting bolt.
The beneficial effect of the utility model is:
Conjuncted steel plate and precast beam on the conjuncted bearing of the utility model unify; Has better durability; And can guarantee closely connected contact the between the bridge pier bent cap of precast beam, bottom on conjuncted bearing and top through the construction of cast-in-place cushion block, have the advantage that is connected firmly.Simultaneously, the utility model has also solved the problem of the prefabricated cushion block execution control difficulty of bringing of a great variety, has the beneficial effect easily of constructing.
Below will combine accompanying drawing that the technique effect of design, concrete structure and the generation of the utility model is described further, with purpose, characteristic and the effect of understanding the utility model fully.
Description of drawings
Fig. 1 is the structural representation of a specific embodiment of the utility model.
Fig. 2 is the local structure for amplifying sketch map in concrete application the embodiment illustrated in fig. 1.
The specific embodiment
Like Fig. 1, shown in Figure 2, a specific embodiment that is applicable to the conjuncted bearing that precast beam is installed of the utility model mainly comprises a conjuncted steel plate 3, and the upside of conjuncted steel plate 3 is provided with a plurality of positioning links 31 of going up that are fixedly connected with precast beam 4.The downside of conjuncted steel plate 3 is fixedly connected with first support body 1 through first upper steel plate 11, is fixedly connected with second support body 2 through second upper steel plate 21.
The special character of the utility model is that last positioning link 31 is between first support body 1 and second support body 2.Last positioning link 31 is arranged between first support body 1 and second support body 2 (centre position that also is the precast beam 4 of later stage lifting) rather than is arranged on both sides, and the precast beam 4 that can avoid top is arranged on the prestressing with bond steel bundle and the ground tackle of both sides.
The below that the below of first support body 1 also is set with first lower steel plate, 12, the second support body 2 also is set with second lower steel plate 22.Be respectively arranged with a plurality of positioning links 13,23 down that are fixedly connected with bridge pier bent cap 5 on first lower steel plate 12, second lower steel plate 22.
First upper steel plate 11, second upper steel plate 21 are fixedly connected with conjuncted steel plate 3 through connecting bolt 32 respectively.
Last positioning link 31, positioning link 13,23 is connecting bolt down.
The construction technology of the conjuncted bearing of the utility model below is described:
Accomplish the making that is applicable to the conjuncted bearing that precast beam is installed of the utility model in bearing factory, and be transported to the job site.
Synchronously, accomplish the making of precast beam, reserve the installing space 42 of the last positioning link 31 on the conjuncted bearing on the precast beam 4 at the precasting yard of precast beam 4, and reservation pouring hole 41.This precast beam 4 is transported to the job site.
Step 1 is built bridge pier bent cap 5 at the construction field (site), when building with first support body 1 of conjuncted bearing through first lower steel plate 12, positioning link 13 is installed in the top of bridge pier bent cap 5 down; With second support body 2 of conjuncted bearing through second lower steel plate 22, positioning link 23 is installed in the top of bridge pier bent cap 5 down.
To having the bridge pier bent cap 5 of constant slope, can level up through leveling pinner 51.
Step 2, through connecting bolt 32 together with first upper steel plate 11, second upper steel plate 21 and conjuncted steel plate 3 crab-bolts, forms conjuncted, and on installation on the conjuncted steel plate 3 is a plurality of positioning link 31.
Step 3 is provided with temporary support in conjuncted bearing both sides.
Step 4, precast beam 4 is set up in lifting, is shelved on precast beam 4 on the temporary support earlier when setting up; A plurality of positioning links 31 of going up are placed in the installing space 42 of precast beam 4.
Step 5 is built cast-in-situ concrete from the pouring hole 41 at precast beam 4 tops, fills up installing space 42, utilizes grouting material concrete to form bearing cushion block 43.
Step 6, treat that cast-in-situ concrete reaches design strength after, remove temporary support; After 43 moulding of bearing cushion block, conjuncted bearing is fixedly connected with the precast beam 4 on top.
In the construction technology of the utility model, last positioning link 31 is a cast in situs grouting material concrete with the connected mode of the precast beam 4 on top.Be specially: when the precast beam 4 on prefabricated top; With conjuncted bearing on positioning link 31 correspondence positions; Offer the pouring hole 41 of 150 millimeters of diameters; The vertical elongated layout of this pouring hole 41 precast beam 4 along top, and reaming forms installing space 42 in one section altitude range at the bottom of beam, so that cast-in-situ concrete can be contained a plurality of scopes that go up positioning links 31.
Utilize grouting material concrete casting building technology, conjuncted bearing that level shelves and the bearing cushion block 43 on the conjuncted bearing are fitted tightly.Be specially: between the conjuncted steel plate 3 and top precast beam 4 of conjuncted bearing, on vertically, reserve the height (realizing) of bearing cushion block 43 through temporary support.Around conjuncted steel plate 3, according to the construction size of bearing cushion block 43 template is set, thereby makes the grouting material concrete that from the pouring hole 41 at precast beam 4 tops, injects flow into the position of bearing cushion block 43 and moulding naturally.
In practical implementation, the conjuncted steel plate 3 that the top of conjuncted bearing is provided with also can be used as the bed die of bearing cushion block 43, is convenient to the construction of bearing cushion block 43.
The bearing cushion block 43 of conjuncted bearing adopts grouting material concrete cast-in-situ, thereby guarantees conjuncted bearing integral level, has the beneficial effect of reliable in quality, easy construction.
Reserve the last positioning link 31 in the installing space 42 that stretches into precast beam 4 on the conjuncted steel plate 3 at conjuncted bearing top, be connected with top precast beam 4 through grouting material concrete, solid and reliable.
Conjuncted bearing can also carry dismountable anchor bolt (being connecting bolt 32), is convenient to the maintenance and the replacing of conjuncted bearing.
Conjuncted steel plate and precast beam on the conjuncted bearing of the utility model unify; Has better durability; And can guarantee closely connected contact the between the bridge pier bent cap of precast beam, bottom on conjuncted bearing and top through the construction of cast-in-place cushion block, have the advantage that is connected firmly.Simultaneously, the utility model has also solved the problem of the prefabricated cushion block execution control difficulty of bringing of a great variety, has the beneficial effect easily of constructing.
More than describe the preferred embodiment of the utility model in detail.Should be appreciated that those of ordinary skill in the art need not creative work and just can make many modifications and variation according to the design of the utility model.Therefore, all technician in the art according to the design of the utility model on the basis of existing technology through the available technical scheme of logical analysis, reasoning, or a limited experiment, all should be in determined protection domain by claims.

Claims (3)

1. a conjuncted bearing that is applicable to that precast beam is installed is characterized in that: comprise a conjuncted steel plate; The upside of said conjuncted steel plate is provided with a plurality of positioning links of going up that are fixedly connected with precast beam; The downside of said conjuncted steel plate is fixedly connected with first support body through first upper steel plate, is fixedly connected with second support body through second upper steel plate; The said positioning link of going up is between said first support body and said second support body; The below of said first support body also is set with first lower steel plate, and the below of said second support body also is set with second lower steel plate; Be respectively arranged with a plurality of positioning links down that are fixedly connected with the bridge pier bent cap on said first lower steel plate, said second lower steel plate.
2. conjuncted bearing as claimed in claim 1 is characterized in that: said first upper steel plate, said second upper steel plate are fixedly connected with said conjuncted steel plate through connecting bolt respectively.
3. conjuncted bearing as claimed in claim 1 is characterized in that: said upward positioning link, said positioning link down are connecting bolt.
CN201220257650.0U 2012-06-01 2012-06-01 Integrated support suitable for mounting precast beams Withdrawn - After Issue CN202577138U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220257650.0U CN202577138U (en) 2012-06-01 2012-06-01 Integrated support suitable for mounting precast beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220257650.0U CN202577138U (en) 2012-06-01 2012-06-01 Integrated support suitable for mounting precast beams

Publications (1)

Publication Number Publication Date
CN202577138U true CN202577138U (en) 2012-12-05

Family

ID=47246567

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220257650.0U Withdrawn - After Issue CN202577138U (en) 2012-06-01 2012-06-01 Integrated support suitable for mounting precast beams

Country Status (1)

Country Link
CN (1) CN202577138U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660921A (en) * 2012-06-01 2012-09-12 上海市城市建设设计研究总院 Connected support applicable to mounting precast beam
CN111119040A (en) * 2020-01-21 2020-05-08 郑州市公路工程公司 Bridge expansion joint position pier and bridge connecting member

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102660921A (en) * 2012-06-01 2012-09-12 上海市城市建设设计研究总院 Connected support applicable to mounting precast beam
CN111119040A (en) * 2020-01-21 2020-05-08 郑州市公路工程公司 Bridge expansion joint position pier and bridge connecting member

Similar Documents

Publication Publication Date Title
CN101424075B (en) Concrete box girder bridge widening and reinforced structure and construction method thereof
CN106245670B (en) Exposed steel column base construction method
CN103981803B (en) The combined gate pier of precast assembly and construction method thereof
CN102767141A (en) Construction method for huge capping beam utilizing reinforced concrete thin wall as permanent formwork
CN112941975B (en) Combined track slab, prefabricated slab track system and installation and construction method thereof
CN103009477A (en) Construction method for prefabricated components for prefabricated component factory
CN111502347A (en) Three-layer single-column assembled elevated station for rail transit
CN215947749U (en) Prefabricated assembled ballast bed
CN202577138U (en) Integrated support suitable for mounting precast beams
CN202247711U (en) Adjustable and controllable reinforced type bridge
CN202187285U (en) Basin type rubber support of cast-in-situ bridge
CN102660921B (en) Connected support applicable to mounting precast beam
CN215104790U (en) Reinforced structure for existing railway underpass frame bridge construction
CN215947748U (en) Prefabricated combined assembled ballast bed
CN215441397U (en) Groove-shaped vertical connecting device suitable for assembled pier and cover beam
CN112727695B (en) Precast concrete tower conversion section of wind generating set and construction method thereof
CN203878460U (en) Prefabricated assembly combined type portal pier
CN211769949U (en) Movable arm type tower crane underframe ballast type foundation
CN211229702U (en) Assembly structure for overhauling stand column and train overhauling platform
CN108330745A (en) The implementation of soft clay area tramcar assembled sub-rail foundation
CN209602942U (en) A kind of compound seismic reinforcing structure of V-type bridge pier
CN113073541A (en) Combined capping beam suitable for continuous bridge deck construction, bridge and construction process
CN112501973A (en) Concrete precast block for repairing cement road
CN220927943U (en) Underground station type steel column anchoring support structure
CN112012095A (en) Beam slab in-situ prefabricating and mounting system and construction method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20121205

Effective date of abandoning: 20140305

AV01 Patent right actively abandoned

Granted publication date: 20121205

Effective date of abandoning: 20140305

AV01 Patent right actively abandoned