CN202559231U - Assembled steel trestle for oil depot - Google Patents
Assembled steel trestle for oil depot Download PDFInfo
- Publication number
- CN202559231U CN202559231U CN2012201708907U CN201220170890U CN202559231U CN 202559231 U CN202559231 U CN 202559231U CN 2012201708907 U CN2012201708907 U CN 2012201708907U CN 201220170890 U CN201220170890 U CN 201220170890U CN 202559231 U CN202559231 U CN 202559231U
- Authority
- CN
- China
- Prior art keywords
- bridge
- steel trestle
- steel
- assembled
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Abstract
The utility model relates to an assembled steel trestle for an oil depot. The assembled steel trestle is formed by vertical columns, a bridge frame, bridge deck slabs, guardrails and inclined ladders which are combined together through bolt connection pieces, wherein the vertical columns are of a double-row symmetrical structure, the lower ends of the vertical columns are fixed on a ground concrete foundation, the upper ends of the vertical columns are provided with the bridge frame, the bridge frame is of a rectangular frame structure, the bridge deck slabs are arranged on the frame of the bridge frame and are made of hot-dip galvanizing steel grid plates, the guardrails are arranged on the two sides of the bridge frame, the inclined ladders are arranged at the two ends of the bridge frame, the lower ends of the inclined ladders are fixed on the ground concrete foundation through concrete, and all the components are fastened by the bolt connection pieces. The bridge deck of the assembled steel trestle disclosed by the utility model is made of the hot-dip galvanizing steel grid plates, thus avoiding accumulation of water and snow, achieving an anti-skidding effect and ensuring safety; as the steel trestle adopts an assembled structure, the construction of the steel trestle is safe, quick and convenient, and the steel components are prefabricated in a factory and then are conveyed to the oil depot to be connected and assembled through the bolt connection pieces; and a welding (fire) operation is avoided, so that the construction safety is ensured.
Description
Technical field
The utility model relates to a kind of oil depot with assembly type steel trestle,
Background technology
At present, general loading and unloading rack is a concrete structure, and investment is big, long construction period, skids easily.Particularly northern, sleety weather, bridge floor is very sliding after freezing, and very easily causes and falls people's fallen accident.Also have and adopt the welding type metallic trestle, but get angry in the oil depot district (welding) construct, danger is very big; Must handle the formality of getting angry, need pass on to different levels for approval and handle the formality of getting angry, formality is loaded down with trivial details especially; Simultaneously, welding (getting angry) construction in the oil depot district, is the maximum potential safety hazard of oil depot.
Summary of the invention
The purpose of the utility model is to overcome above-mentioned defective, provide a kind of can be anti-skidding, produce in factory, scene be convenient to install, the oil depot of short construction period is with assembly type steel trestle.
The utility model technical solution: A depot with assembled steel trestle, characterized in that said that the steel trestle by the column, bridge, bridge deck, fence and inclined ladders bolted joints through a combination of the column for double raft symmetrical structure, the lower end of the column fixed to the ground on a concrete foundation, column upper end of the bridge, the bridge is a rectangular frame structure, the bridge panel to set the frame of the bridge, the bridge deck is hot dip galvanized steel grating deck made , the bridge side guardrails, both ends of the inclined ladder tray, inclined ladder lower concrete foundation fixed to the ground, between the respective components used in all fastening bolts.
The integral body of this assembly type steel trestle adopts lightweight steel construction, few, the short construction period of steel using amount, and the trestle bridge floor adopts the galvanizing steel grating, not ponding, accumulated snow not, non-skid property is good especially, has solved anti-skidding problem, has guaranteed safety; Effectively solve and fall people's fallen accident.Simultaneously, we adopt modular construction, and construction safety, quick and easy is promptly all good with the steel element precast in factory, transport to oil depot and assemble with bolt and get final product.Need not weld (getting angry), guarantee construction safety.
Description of drawings
Fig. 1 is the main TV structure sketch map of the utility model;
Fig. 2 is the left TV structure sketch map of the utility model;
Fig. 3 is the plan structure sketch map of the utility model;
Among the figure; The 1-column, 2-crane span structure, 3-guardrail, 4-inclined ladder, 5-bridge deck (galvanizing steel grating).
The specific embodiment
Referring to the drawings, one kind of depot assembled with steel trestle, characterized in that said that the steel trestle by a uniform uprights 1, tray 2, guardrail 3, 4 and inclined ladders bolted deck 5 Piece Set from the column for the two raft symmetrical structure, fixed to the lower end of the column 1 on the concrete foundation in the ground, the upper end of column 1 tray 2, the tray 2 is a rectangular frame structure, the bridge panel 5 is disposed on the frame 2 on the bridge, the bridge Panel 5 is hot dip galvanized steel grating produced deck, bridge two sides guardrails 3, both ends of the bridge two inclined ladder 4, the lower end of inclined ladders four concrete foundation fixed on the ground, between the various components used in all of the bolts connections tightened.
The integral body of this assembly type steel trestle adopts lightweight steel construction, and the trestle bridge floor adopts the galvanizing steel grating, and ponding, accumulated snow have not solved anti-skidding problem, have guaranteed safety; Adopt modular construction, construction safety, quick and easy, promptly all that the steel element precast is good in factory, transport to oil depot and assemble with bolt and get final product.Need not weld (getting angry), guarantee construction safety.
Claims (1)
1 A depot with assembled steel trestle, wherein the column of the steel trestle (1), bridge (2), rails (3), inclined ladders (4) and the bridge deck (5) through bolting combination, the column for the two symmetrical structure raft, column (1) fixed to the lower end of a concrete foundation on the ground, the column (1) upper end of the tray (2), the tray (2) is a rectangular frame structure, bridge deck (5) disposed in the bridge (2) of the frame, the bridge deck (5) for the hot dip galvanized steel grating produced deck, bridge (2) on both sides of fence (3), bridge (2) ends Set inclined ladder (4), inclined ladder (4) fixed to the lower end of a concrete foundation on the ground, between the respective components used in all fastening bolts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012201708907U CN202559231U (en) | 2012-04-20 | 2012-04-20 | Assembled steel trestle for oil depot |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012201708907U CN202559231U (en) | 2012-04-20 | 2012-04-20 | Assembled steel trestle for oil depot |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202559231U true CN202559231U (en) | 2012-11-28 |
Family
ID=47208901
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012201708907U Expired - Lifetime CN202559231U (en) | 2012-04-20 | 2012-04-20 | Assembled steel trestle for oil depot |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202559231U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103061799A (en) * | 2012-12-19 | 2013-04-24 | 三一重型装备有限公司 | Passing through device and hydraulic support group with passing through device |
CN104810771A (en) * | 2015-05-13 | 2015-07-29 | 国网辽宁省电力有限公司盘锦供电公司 | Insulated gap bridge for bus sleeves |
CN106284393A (en) * | 2015-05-27 | 2017-01-04 | 北京清城睿现数字科技研究院有限公司 | Visit plank road basis, runis park |
CN106593471A (en) * | 2016-12-22 | 2017-04-26 | 中铁五局集团有限公司 | Moveable trestle with stepping type self-walking truss structure for large-section tunnel invert construction |
-
2012
- 2012-04-20 CN CN2012201708907U patent/CN202559231U/en not_active Expired - Lifetime
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103061799A (en) * | 2012-12-19 | 2013-04-24 | 三一重型装备有限公司 | Passing through device and hydraulic support group with passing through device |
CN103061799B (en) * | 2012-12-19 | 2015-03-18 | 三一重型装备有限公司 | Passing through device and hydraulic support group with passing through device |
CN104810771A (en) * | 2015-05-13 | 2015-07-29 | 国网辽宁省电力有限公司盘锦供电公司 | Insulated gap bridge for bus sleeves |
CN106284393A (en) * | 2015-05-27 | 2017-01-04 | 北京清城睿现数字科技研究院有限公司 | Visit plank road basis, runis park |
CN106593471A (en) * | 2016-12-22 | 2017-04-26 | 中铁五局集团有限公司 | Moveable trestle with stepping type self-walking truss structure for large-section tunnel invert construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202559231U (en) | Assembled steel trestle for oil depot | |
CN101775907A (en) | Space truss structure aerial pairing integral slide installation method | |
CN104372961A (en) | Anti-seismic integrated lightweight steel construction house | |
CN206768611U (en) | Bridge pier hanging basket mounting operation platform | |
CN101858139A (en) | Concrete casting platform | |
CN201962965U (en) | Cadge ladder for construction of deep base pit | |
CN201786008U (en) | Automatic follow-up unloading platform for outer climb frame | |
US20170159304A1 (en) | Apparatus includes overhead hoarding assembly for scaffolding assembly | |
CN102287045A (en) | Square steel tube lifting outside scaffold | |
JP5678077B2 (en) | Decomposable modular platform for garbage disposal facilities | |
CN204311776U (en) | A kind of integrated lightweight steel construction room of antidetonation | |
CN105257034A (en) | Method of building garage | |
CN102587601A (en) | Multistage connection cage-type staircase | |
CN202559618U (en) | Multi-step connection type cage staircase | |
CN205296892U (en) | A merogenesis stair and up -downgoing passageway for deep foundation pit construction is current from top to bottom | |
CN202808127U (en) | Platform frame-free external construction elevator | |
CN201274686Y (en) | Reinforced concrete booth frame | |
CN203475920U (en) | Flange assembled type power transformation framework column | |
CN208668601U (en) | A kind of environment-friendly and energy-efficient steel plant structure | |
CN207277373U (en) | A kind of riding track being used in foundation pit construction | |
CN201843089U (en) | Vertical lifting bin for overhauling overpass ramp bridge | |
CN205674190U (en) | A kind of dedicated platform adjusting the maintenance of seepage pump house cucurbit and installation for underground workshop tail | |
CA2914072C (en) | Apparatus includes overhead hoarding assembly for scaffolding assembly | |
RU154730U1 (en) | RAILWAY PLATFORM | |
CN204531232U (en) | Prefabricated reinforced concrete quakeproof stair |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20121128 |
|
CX01 | Expiry of patent term |