CN202520353U - Air volume distribution controller for tunnel construction ventilation pipeline - Google Patents

Air volume distribution controller for tunnel construction ventilation pipeline Download PDF

Info

Publication number
CN202520353U
CN202520353U CN2012201543444U CN201220154344U CN202520353U CN 202520353 U CN202520353 U CN 202520353U CN 2012201543444 U CN2012201543444 U CN 2012201543444U CN 201220154344 U CN201220154344 U CN 201220154344U CN 202520353 U CN202520353 U CN 202520353U
Authority
CN
China
Prior art keywords
air volume
groove
air
air quantity
volume distribution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN2012201543444U
Other languages
Chinese (zh)
Inventor
曹会芹
王新民
邓华军
刘贵兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority to CN2012201543444U priority Critical patent/CN202520353U/en
Application granted granted Critical
Publication of CN202520353U publication Critical patent/CN202520353U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Images

Landscapes

  • Ventilation (AREA)

Abstract

The utility model specifically discloses an air volume distribution controller for a tunnel construction ventilation pipeline, which is used for solving the problems of prolonging of ventilation time, waste of energy consumption and delay of the construction period caused by unreasonable distribution of air volume on working surfaces on both sides of the conventional tunnel construction ventilation pipeline. The bottom of a three-way joint is provided with a columnar groove; an air volume distribution barrel is placed into the groove; the side wall of the air volume distribution barrel is provided with four air outlet holes consisting of a small air volume air outlet hole and a large air volume air outlet hole formed on front and back parts, and two medium air volume air outlet holes formed on left and right parts; a revolving shaft is fixed in the center of the bottom of the air volume distribution barrel; a guide pipe fixed below the bottom of the groove is sleeved on the revolving shaft; an operating handle rotating upwards and downwards around the revolving shaft is connected below the revolving shaft; and four operating handle fixing snap rings which are arranged uniformly along the axis of the groove and correspond to the air outlet hole positions are fixed below the bottom of the groove. The air volume distribution controller is reasonable and reliable structural design, has the advantages of economic efficiency, rationality and saving in energy, and contributes to saving a part of equipment purchasing costs and daily energy consumption cost.

Description

Construction ventilation of tunnel pipeline control for air distribution
Technical field
The utility model relates to the constructing tunnel air quantity controller, is specially a kind of construction ventilation of tunnel pipeline control for air distribution.
Background technology
In the constructing tunnel process, in order fresh air, the harmful dust concentration of dilution to be provided in the hole and to reduce environment temperature in the hole, palpus employing high-power blower to the air-supply of excavation operation face, is referred to as construction ventilation through pipeline.Constructing tunnel often adopts accessory channels such as inclined shaft, horizontal hole to increase positive hole excavation operation face, and utilizing a circuits is that two scope of operations provide ventilation simultaneously, abbreviates the one drag two air vent mode as.
The one drag two air vent mode; Mainly form by the connecting tube between high-power blower, trunk line, branch pipe(tube), master, the branch pipe(tube) (threeway) outside the hole etc.; Blower fan adopts tandem two-shipper unit more, can need according to air quantity in the hole, adopts unit air feed or two-shipper air feed; Main, branch pipe(tube) adopts flexible wind sleeve more, during ventilation under the effect of blast wind sleeve expand and form passage, blast disappears during shutdown, wind sleeve is sagging naturally.The trunk line diameter is generally 1.5~1.8m, and the branch pipe(tube) diameter is generally 1.2~1.4m; Connecting tube generally is connected firmly trunk line and branch pipe(tube).
During construction ventilation of tunnel; Be divided into intensified ventilation and continue the two kinds of citation forms that ventilate; When operations such as explosion, muck removal, sprayed mortar were constructed, work plane was seriously polluted, air worsens, and needs to adopt the intensified ventilation of big air quantity; In time the concentration of pernicious gas and dust in the dilution hole is improved the air quality condition of operating area; When other operation construction,, adopt the lasting ventilation of little air quantity, to satisfy the demand of constructor to fresh air owing to do not produce pollution.Intensified ventilation needs two blower fan air feeds, but the time is shorter, and lasting ventilation only needs single blower fan air feed, but the air feed time is longer.
All can open up two scope of operations simultaneously behind tunnel inclined shaft, the horizontal hole driving certain-length; Can artificially control and adjust the construction speed of two work planes,, cause to continue the waste of ventilation operation face air quantity when a work plane need continue to ventilate and another work plane when needing intensified ventilation; And the intensified ventilation face air volume is not enough; The intensified ventilation time lengthening influences the normal linking of operation, and wastes energy consumption, delay duration.
Summary of the invention
The utility model can not get reasonable distribution and causes ventilation time to prolong and the waste energy consumption, incur loss through delay the problem of duration in order to solve existing tunnel construction ventilation pipeline both sides work plane institute required airflow, and a kind of construction ventilation of tunnel pipeline control for air distribution is provided.
The utility model is to adopt following technical scheme to realize: construction ventilation of tunnel pipeline control for air distribution; Comprise tee junction; Tee junction bottom is provided with corresponding with its top sub position and to the cylindrical recesses of lower convexity; Be placed with the air quantity distribution drum in the groove; Air quantity distribution drum sidewall has four exhaust vents that are uniformly distributed with setting along its axis; The little air quantity exhaust vent that four exhaust vents are positioned on the same horizontal plane by axis and front and back are provided with, strong wind amount exhaust vent and about two apoplexy amount exhaust vents being provided with forms, air quantity distribution drum bottom centre is fixed with the rotating shaft that passes bottom portion of groove, is with the guide pipe that is fixed on below the bottom portion of groove in the rotating shaft; Rotating shaft below is connected with the control handle that rotates up and down around it, and the bottom portion of groove below is fixed with to be uniformly distributed with along its axis and is provided with and the fixing snap ring of four control handles corresponding with the exhaust vent position.
When construction ventilation of tunnel pipeline two work planes are lasting the ventilation; Adopt single blower fan air-supply; The apoplexy amount exhaust vent of rotation control handle to air quantity distribution drum is positioned at the left and right sides (and left and right joint one side of the tee junction in connecting branch road); Then control handle is stuck in control handle fixedly in the snap ring, prevents that the air quantity distribution drum is rotated by the effect of blast, guarantee that two work planes satisfy the needs that replenish fresh air.
When the either side of construction ventilation of tunnel pipeline two work planes carries out explosion, muck removal or sprayed mortar operation; Adopt two blower fan air-supplies; And the strong wind amount exhaust vent of air quantity distribution drum aimed at this work plane, little air quantity air outlet is aimed at the opposite side work plane, realizes that two work planes, one side intensified ventilation, opposite side continue the requirement of ventilating; Suitably reduce power of fan and dwindle the trunk line diameter, practice thrift the equipment input cost.
Gap location between the top sub inwall of air quantity distribution drum external wall of upper portion and tee junction is provided with rubber seal, under the effect of blast, forces rubber seal that air quantity distribution drum and tee junction is closely connected, reaches to prevent the purpose of leaking out.
The utility model reasonable in design is reliable; Realize the reasonable distribution of constructing tunnel one drag two ventilation both sides work plane institute required airflow, and can rationally adjust under the prerequisite of Design of ventilation, suitably reduced the power of ventilation equipment; The elasticity system that can realize the tunnel slope construction is simultaneously ventilated; Be the lasting ventilation of explosion, muck removal, the intensified ventilation of sprayed mortar operation period and other operation period, have economy, reasonable, energy-saving advantages, save equipment component acquisition expenses and daily energy consumption cost.
Description of drawings
Fig. 1 is the structural representation of the utility model.
Among the figure: the 1-tee junction, the 2-groove, 3-air quantity distribution drum, the little air quantity exhaust vent of 4-, 5-strong wind amount exhaust vent, 6-apoplexy amount exhaust vent, the 7-rotating shaft, the 8-guide pipe, the 9-control handle, the 10-control handle is snap ring fixedly, the 11-rubber seal.
The specific embodiment
Construction ventilation of tunnel pipeline control for air distribution; Comprise tee junction 1; Tee junction 1 bottom is provided with corresponding with its top sub position and to the cylindrical recesses 2 of lower convexity; Be placed with air quantity distribution drum 3 in the groove 2, air quantity distribution drum 3 sidewalls have four exhaust vents that are uniformly distributed with setting along its axis, the little air quantity exhaust vent 4 that four exhaust vents are positioned on the same horizontal plane by axis and front and back are provided with, strong wind amount exhaust vent 5 and about two apoplexy amount exhaust vents 6 being provided with form; Air quantity distribution drum 3 bottom centre are fixed with the rotating shaft 7 that passes groove 2 bottoms; Be with the guide pipe 8 that is fixed on groove 2 bottoms belows in the rotating shaft 7, rotating shaft 7 belows are connected with around its control handle that rotates up and down 9, and below, groove 2 bottoms is fixed with to be uniformly distributed with along its axis and is provided with and the fixing snap ring 10 of four control handles corresponding with the exhaust vent position.Gap location between the top sub inwall of air quantity distribution drum 3 external wall of upper portion and tee junction 1 is provided with rubber seal 11.
In the practical implementation process; Air quantity distribution drum 3 is to be rolled by steel sheet to form; Little air quantity exhaust vent 4, strong wind amount exhaust vent 5 and apoplexy amount exhaust vent 6 are the sizes according to the size control air quantity of exhaust vent diameter; Control handle fixedly snap ring 10 is to be processed by the flexure strip that two relative side correspondence positions have the semicircle shape groove, and control handle 9 lifts and can be pressed into control handle fixedly in the groove of snap ring 10, and the position of air quantity distribution drum 3 is fixed.

Claims (2)

1. construction ventilation of tunnel pipeline control for air distribution; Comprise tee junction (1); It is characterized in that: tee junction (1) bottom is provided with corresponding with its top sub position and to the cylindrical recesses (2) of lower convexity; Be placed with air quantity distribution drum (3) in the groove (2); Air quantity distribution drum (3) sidewall has four exhaust vents that are uniformly distributed with setting along its axis; The little air quantity exhaust vent (4) that four exhaust vents are positioned on the same horizontal plane by axis and front and back are provided with, strong wind amount exhaust vent (5) with about two apoplexy amount exhaust vents (6) of being provided with forms, air quantity distribution drum (3) bottom centre is fixed with the rotating shaft (7) that passes groove (2) bottom, is with the guide pipe (8) below being fixed on bottom the groove (2) in the rotating shaft (7); Rotating shaft (7) below is connected with around its control handle that rotates up and down (9), and below, groove (2) bottom is fixed with to be uniformly distributed with along its axis and is provided with and the fixing snap ring (10) of four control handles corresponding with the exhaust vent position.
2. construction ventilation of tunnel pipeline control for air distribution according to claim 1 is characterized in that: the gap location between the top sub inwall of air quantity distribution drum (3) external wall of upper portion and tee junction (1) is provided with rubber seal (11).
CN2012201543444U 2012-04-13 2012-04-13 Air volume distribution controller for tunnel construction ventilation pipeline Withdrawn - After Issue CN202520353U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012201543444U CN202520353U (en) 2012-04-13 2012-04-13 Air volume distribution controller for tunnel construction ventilation pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012201543444U CN202520353U (en) 2012-04-13 2012-04-13 Air volume distribution controller for tunnel construction ventilation pipeline

Publications (1)

Publication Number Publication Date
CN202520353U true CN202520353U (en) 2012-11-07

Family

ID=47103306

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012201543444U Withdrawn - After Issue CN202520353U (en) 2012-04-13 2012-04-13 Air volume distribution controller for tunnel construction ventilation pipeline

Country Status (1)

Country Link
CN (1) CN202520353U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635384A (en) * 2012-04-13 2012-08-15 中铁十七局集团第三工程有限公司 Air distribution controller for tunnel construction air duct
CN103195461A (en) * 2013-02-20 2013-07-10 广东安元矿业技术服务有限公司 Application condition and method for achieving saving and clean production by replacing roadway with pipeline for ventilation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635384A (en) * 2012-04-13 2012-08-15 中铁十七局集团第三工程有限公司 Air distribution controller for tunnel construction air duct
CN102635384B (en) * 2012-04-13 2014-03-26 中铁十七局集团第三工程有限公司 Air distribution controller for tunnel construction air duct
CN103195461A (en) * 2013-02-20 2013-07-10 广东安元矿业技术服务有限公司 Application condition and method for achieving saving and clean production by replacing roadway with pipeline for ventilation
CN103195461B (en) * 2013-02-20 2015-09-30 广东安元矿业勘察设计有限公司 Pipeline substitutes the method that dash realizes cleaner production

Similar Documents

Publication Publication Date Title
CN100595420C (en) Pressure regulating and distributing chamber ventilation construction method inside tunnel assist drift heading hole
CN205109836U (en) Breaker metallic foreign object separator
CN202520353U (en) Air volume distribution controller for tunnel construction ventilation pipeline
CN102635384B (en) Air distribution controller for tunnel construction air duct
CN101786061B (en) Spraying technology and special device for outer wall of wind power tower
CN204902998U (en) Noise monitoring device
CN204532403U (en) Mine efficient circulation ventilation system
CN202280470U (en) Iron made wind distributing device
CN202942760U (en) Novel obliquely-inserted filter cartridge deduster
CN214466272U (en) High-pressure hard sealing ball valve with high stability
CN204900293U (en) Solar energy scavenger fan
CN207525688U (en) Civil engineering smoothing machine
CN202451196U (en) Mine return air after-heat recovery heat exchanger
CN204051279U (en) A kind of rotary full angle dust arrester for J. sigillate
CN206600287U (en) A kind of centrifugal blower
CN206309623U (en) A kind of building energy conservation ventilation blower
CN205714964U (en) A kind of rectifier type air-introduced machine
CN204268645U (en) The fresh breeze device of intelligent building
CN204182661U (en) Ash system inhaled by a kind of tunnel cave carborundum tank
CN204429802U (en) One can Automatic clearance type pulverizing grading machine stepped pipeline
CN202900797U (en) Annular silencing device for large air cooling fan
CN202204096U (en) Intelligent energy-saving fresh air system for base station
CN203973729U (en) A kind of new concrete Construction of Continuous Box Beam ventilating system
CN204079822U (en) A kind of horizontal spiral stirring-type straw compost generation equipment
CN212250111U (en) Local ventilation conversion dust collector

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 050080 Zhongshan West Road Hebei city of Shijiazhuang province (Village) No. 979

Patentee after: China Railway No.17 Bureau Group Third Engineering Co., Ltd.

Address before: 030006 No. 84, Pingyang Road, Taiyuan, Shanxi

Patentee before: China Railway No.17 Bureau Group Third Engineering Co., Ltd.

AV01 Patent right actively abandoned

Granted publication date: 20121107

Effective date of abandoning: 20140326

AV01 Patent right actively abandoned

Granted publication date: 20121107

Effective date of abandoning: 20140326

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned