CN202518194U - Power matching network recovery service standardization tool box - Google Patents

Power matching network recovery service standardization tool box Download PDF

Info

Publication number
CN202518194U
CN202518194U CN2012201854585U CN201220185458U CN202518194U CN 202518194 U CN202518194 U CN 202518194U CN 2012201854585 U CN2012201854585 U CN 2012201854585U CN 201220185458 U CN201220185458 U CN 201220185458U CN 202518194 U CN202518194 U CN 202518194U
Authority
CN
China
Prior art keywords
work tool
die cavity
lower floor
tool die
matching network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012201854585U
Other languages
Chinese (zh)
Inventor
马玉良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi new Huaan Electric Power Engineering Co., Ltd.
Original Assignee
马玉良
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 马玉良 filed Critical 马玉良
Priority to CN2012201854585U priority Critical patent/CN202518194U/en
Application granted granted Critical
Publication of CN202518194U publication Critical patent/CN202518194U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a power matching network recovery service standardization tool box, comprising a case; the top end of the case is in flexible connection with a movable case cover; a plurality of first partition boards for partitioning the lower space inside the case into a plurality of lower tool cavities are arranged at the lower part inside the case; a tray is arranged at the upper part inside the case; the tray is internally provided with a plurality of second partition boards for partitioning the space inside the tray into a plurality of upper tool cavities; and the shape of each tool cavity is respectively matched with the shape of a placed power matching network recovery service tool. The power matching network recovery service standardization tool box is reasonable in design, convenient to process and manufacture, convenient and fast to use and operate, and is capable of reducing the damage of recovery service tool, thereby improving the quality and efficiency of recovery service; and the power matching network recovery service standardization tool box is beneficial to realize the standardization of recovery service procedure, field operation, equipment and tool configuration, and has high practicability and high popularization and application values.

Description

Power matching network repairing normalisation Work tool case
Technical field
The utility model belongs to electrical technology field, relates to a kind of power matching network rush repair equipment, especially relates to a kind of power matching network repairing normalisation Work tool case.
Background technology
At present, power matching network is rushed to repair as distribution production routine property important process, has round-the-clock failure response, direct characteristics such as, operating environment complicacy various in the face of user, failure condition.The tool box design and the manufacturer's standard that are used for device power matching network repairing Work tool at present differ, and functions of use is uneven, can't realize in good order the putting of Work tool of various repairing job requirements.Because many, the operation dispersion of job, equipment is numerous and diverse, fault type is different; In maintenance work, repairing process; Often do not cause entirely and need to come and go the phenomenon of taking Work tool back and forth several times because of being equipped with construction Work tool, standby redundancy, cause the repairing time expand, electric power feeding time is delayed virtually; On the other hand; Power matching network of the prior art repairing Work tool case is because of can't rushing to repair the Work tool fixation with power matching network, after power matching network rushed to repair the Work tool case and be placed on the recovery vehicle; Power matching network repairing Work tool obtains destroying in the recovery vehicle driving process virtually; Also do not meet safety standard requirements, the damage of instrument is directly influence construction both, increases cost again.The problems referred to above have directly influenced the lifting of power supply reliability index, and for guaranteeing carrying out in order of breakdown repair work, power supply department has consumed great amount of manpower and material resources and financial resources.
The utility model content
The utility model technical matters to be solved is to above-mentioned deficiency of the prior art, and a kind of power matching network repairing normalisation Work tool case is provided, and it is reasonable in design; Processing and fabricating is convenient; Use simple operation, can reduce the damage of repairing Work tool, improve repairing quality and efficient; Practical, application value is high.
For solving the problems of the technologies described above; The technical scheme that the utility model adopts is: a kind of power matching network repairing normalisation Work tool case; Comprise casing; It is characterized in that: the top of said casing is connected with removable box cover, and said box house below is provided with first dividing plate that polylith is used for box house below spatial is divided into a plurality of lower floors Work tool die cavity, and said box house top is provided with pallet; Be provided with the second partition that polylith is used for the spatial in the pallet is divided into a plurality of upper stratas Work tool die cavity in the said pallet, the shape of each said Work tool die cavity is complementary with the shape of the power matching network placed repairing Work tool respectively.
Above-mentioned power matching network repairing normalisation Work tool case; It is characterized in that: the bottom of said casing is a rectangular shape; The middle part shape of cross section of said casing is for falling echelon form; Be symmetrical set on the upper inner wall of said casing and be useful on the step fixing with carrying the car side board, said step is to casing outside protrusion, and said step is provided with a plurality of being used for said power matching network repairing normalisation Work tool case is fixed on the fixed orifice that carries on the car.
Above-mentioned power matching network repairing normalisation Work tool case is characterized in that: the fall echelon form of the shape of cross section of said pallet for matching with casing middle part shape of cross section.
Above-mentioned power matching network repairing normalisation Work tool case, it is characterized in that: said casing is provided with lock buckling groove, the snap close head that said removable box cover is provided with handle and matches with lock buckling groove.
Above-mentioned power matching network repairing normalisation Work tool case, it is characterized in that: said removable box cover flexibly connects through the top of hinge and casing.
Above-mentioned power matching network repairing normalisation Work tool case is characterized in that: be connected with the strut bar that is used to regulate the removable box cover open angle between said casing and the removable box cover.
Above-mentioned power matching network repairing normalisation Work tool case; It is characterized in that: the quantity of said first dividing plate is nine, and the quantity of said lower floor Work tool die cavity is ten and is respectively first lower floor's Work tool die cavity, second lower floor's Work tool die cavity, the 3rd lower floor's Work tool die cavity, the 4th lower floor's Work tool die cavity, the 5th lower floor's Work tool die cavity, the 6th lower floor's Work tool die cavity, the 7th lower floor's Work tool die cavity, the 8th lower floor's Work tool die cavity, the 9th lower floor's Work tool die cavity and the tenth lower floor's Work tool die cavity.
Above-mentioned power matching network repairing normalisation Work tool case; It is characterized in that: the quantity of said second partition is two, and the quantity of said upper strata Work tool die cavity is three and is respectively the first upper strata Work tool die cavity, the second upper strata Work tool die cavity and the 3rd upper strata Work tool die cavity.
The utility model compared with prior art has the following advantages:
1, the utility model is simple in structure, and is reasonable in design, and processing and fabricating is convenient, realizes that cost is low.
2, the use simple operation of the utility model, the power matching network repairing Work tool that is placed in the utility model is complete, puts clean and tidy; And pick and place conveniently, accelerated the speed of going out, help to increase work efficiency; Can also avoid helping to practice thrift cost because of putting the improper damage that causes.
3, the utility model can be realized the fixation of power matching network repairing Work tool, can not cause the destruction of power matching network repairing Work tool in the recovery vehicle driving process, meets the requirement of safety standard.
4, the utility model can be realized in good order the putting of power matching network repairing Work tool; Help to realize rushing to repair the unified and standard and normalisation of flow process, field operation, equipment and Work tool configuration; For improving repairing quality and efficient; Shorten the repairing time to greatest extent, promote power supply reliability and good service level, have crucial meaning.
5, the utility model is practical, and long service life is convenient to promote the use of.
In sum, the utility model is reasonable in design, and processing and fabricating is convenient, uses simple operation, can reduce the damage of repairing Work tool, improves repairing quality and efficient, and is practical, and application value is high.
Through accompanying drawing and embodiment, the technical scheme of the utility model is done further detailed description below.
Description of drawings
Structural representation when Fig. 1 opens for the utility model removable box cover.
Structural representation when Fig. 2 holds up for the utility model pallet.
Fig. 3 is the box inner structure scheme drawing of the utility model except that pallet.
Description of reference numerals:
The 1-casing; The 2-removable box cover; The 3-pallet;
The 3-1-first upper strata Work tool die cavity; The 3-2-second upper strata Work tool die cavity;
3-3-the 3rd upper strata Work tool die cavity; The 4-second partition; The 5-step;
The 5-1-fixed orifice; The 6-1-lock buckling groove; 6-2-snap close head;
The 7-handle; 8-first dividing plate; 8-1-first lower floor's Work tool die cavity;
8-2-second lower floor's Work tool die cavity; 8-3-the 3rd lower floor's Work tool die cavity;
8-4-the 4th lower floor's Work tool die cavity; 8-5-the 5th lower floor's Work tool die cavity;
8-6-the 6th lower floor's Work tool die cavity; 8-7-the 7th lower floor's Work tool die cavity;
8-8-the 8th lower floor's Work tool die cavity; 8-9-the 9th lower floor's Work tool die cavity;
8-10-the tenth lower floor's Work tool die cavity; The 9-strut bar.
The specific embodiment
Like Fig. 1, Fig. 2 and shown in Figure 3; The utility model comprises casing 1; The top of said casing 1 is connected with removable box cover 2; Said casing 1 inner below is provided with first dividing plate 8 that polylith is used for casing 1 inner below spatial is divided into a plurality of lower floors Work tool die cavity; Said box house 2 tops are provided with pallet 3, are provided with the second partition 4 that polylith is used for the spatial in the pallet 3 are divided into a plurality of upper stratas Work tool die cavity in the said pallet 3, and the shape of each said Work tool die cavity is complementary with the shape of the power matching network repairing Work tool of being placed respectively.
Like Fig. 1, Fig. 2 and shown in Figure 3; In the present embodiment; The bottom of said casing 1 is a rectangular shape, and the middle part shape of cross section of said casing 1 is for falling echelon form, be symmetrical set on the upper inner wall of said casing 1 to be useful on the step 5 fixing with carrying the car side board; Said step 5 is to casing 1 outside protrusion, and said step 5 is provided with a plurality of being used for said power matching network repairing normalisation Work tool case is fixed on the fixed orifice 5-1 that carries on the car.The fall echelon form of the shape of cross section of said pallet 3 for matching with casing 1 middle part shape of cross section.
Like Fig. 1, Fig. 2 and shown in Figure 3, in the present embodiment, said casing 1 is provided with lock buckling groove 6-1, the snap close head 6-2 that said removable box cover 2 is provided with handle 7 and matches with lock buckling groove 6-1.Said removable box cover 2 flexibly connects through the top of hinge and casing 1.Be connected with the strut bar 9 that is used to regulate removable box cover 2 open angles between casing 1 and the removable box cover 2.The quantity of said first dividing plate 8 is nine, and the quantity of said lower floor Work tool die cavity is ten and is respectively the first Work tool die cavity 8-1 of lower floor, the second Work tool die cavity 8-2 of lower floor, the 3rd Work tool die cavity 8-3 of lower floor, the 4th Work tool die cavity 8-4 of lower floor, the 5th Work tool die cavity 8-5 of lower floor, the 6th Work tool die cavity 8-6 of lower floor, the 7th Work tool die cavity 8-7 of lower floor, the 8th Work tool die cavity 8-8 of lower floor, the 9th Work tool die cavity 8-9 of lower floor and the tenth Work tool die cavity 8-10 of lower floor.The quantity of said second partition 4 is two, and the quantity of said upper strata Work tool die cavity is three and is respectively the first upper strata Work tool die cavity 3-1, the second upper strata Work tool die cavity 3-2 and the 3rd upper strata Work tool die cavity 3-3.
During use; Through fixed orifice 5-1 and hook bolt this power matching network repairing normalisation Work tool case is fixed on year car side board; Place corresponding power tool according to concrete power matching network repairing homework type in the casing 1, can satisfy seven kinds of different power matching network repairing job requirements.Specific as follows:
(1) operation is changed in the backguy of 10KV distribution circuit
The casing 1 inner side space down that is arranged in pallet 3 belows is placed safety precaution and field operation Work tool; Particularly, place safe fence among the first Work tool die cavity 8-1 of lower floor, place safety cap among the second Work tool die cavity 8-2 of lower floor; Place high voltage electroscope and low pressure voltage detector among the 3rd Work tool die cavity 8-3 of lower floor; Place personality kit among the 4th Work tool die cavity 8-4 of lower floor, place the instrument of ascending a height among the 5th Work tool die cavity 8-5 of lower floor, place the UT bolt among the 6th Work tool die cavity 8-6 of lower floor; Place safety strap and safety rope among the 7th Work tool die cavity 8-7 of lower floor; Place steel strand rope and turnbuckle among the 8th Work tool die cavity 8-8 of lower floor, place wedge clamp among the 9th Work tool die cavity 8-9 of lower floor, place warning sign among the tenth Work tool die cavity 8-10 of lower floor.
Place insulating boot among the first upper strata Work tool die cavity 3-1 in the pallet 3, place the low pressure grounding jumper among the second upper strata Work tool die cavity 3-2, place the high-voltage earthing line among the 3rd upper strata Work tool die cavity 3-3.
(2) the 10KV distribution circuit is removed operation
The casing 1 inner side space down that is arranged in pallet 3 belows is placed safety precaution and field operation Work tool; Place safe fence and wire clipper among the first Work tool die cavity 8-1 of lower floor; Place safety cap among the second Work tool die cavity 8-2 of lower floor, place high voltage electroscope and low pressure voltage detector among the 3rd Work tool die cavity 8-3 of lower floor, place personality kit among the 4th Work tool die cavity 8-4 of lower floor; Place the instrument of ascending a height among the 5th Work tool die cavity 8-5 of lower floor; Place wire clipper among the 6th Work tool die cavity 8-6 of lower floor, place safety strap and abaca rope among the 7th Work tool die cavity 8-7 of lower floor, place turnbuckle among the 8th Work tool die cavity 8-8 of lower floor; Place steel rope among the 9th Work tool die cavity 8-9 of lower floor, place warning sign among the tenth Work tool die cavity 8-10 of lower floor.
Place insulating boot among the first upper strata Work tool die cavity 3-1 in the pallet 3, place the low pressure grounding jumper among the second upper strata Work tool die cavity 3-2, place the high-voltage earthing line among the 3rd upper strata Work tool die cavity 3-3.
(3) distribution transformer is changed operation on the 10KV post
The casing 1 inner side space down that is arranged in pallet 3 belows is placed safety precaution and field operation Work tool; Place safe fence among the first Work tool die cavity 8-1 of lower floor; Place safety cap among the second Work tool die cavity 8-2 of lower floor, place high voltage electroscope among the 3rd Work tool die cavity 8-3 of lower floor, place personality kit among the 4th Work tool die cavity 8-4 of lower floor; Place the instrument of ascending a height among the 5th Work tool die cavity 8-5 of lower floor; Place the low pressure voltage detector among the 6th Work tool die cavity 8-6 of lower floor, place safety strap among the 7th Work tool die cavity 8-7 of lower floor, place the insulation megger among the 8th Work tool die cavity 8-8 of lower floor; Place the grounding resistance megger among the 9th Work tool die cavity 8-9 of lower floor, place warning sign among the tenth Work tool die cavity 8-10 of lower floor.
Place insulating boot among the first upper strata Work tool die cavity 3-1 in the pallet 3, place the low pressure grounding jumper among the second upper strata Work tool die cavity 3-2, place the high-voltage earthing line among the 3rd upper strata Work tool die cavity 3-3.
(4) 10KV ring main unit, box change and distribution box are changed operation
The casing 1 inner side space down that is arranged in pallet 3 belows is placed safety precaution and field operation Work tool; Place safe fence among the first Work tool die cavity 8-1 of lower floor; Place safety cap among the second Work tool die cavity 8-2 of lower floor, place high voltage electroscope and low pressure voltage detector among the 3rd Work tool die cavity 8-3 of lower floor, place personality kit among the 4th Work tool die cavity 8-4 of lower floor; Place the instrument of ascending a height among the 5th Work tool die cavity 8-5 of lower floor; Place multi-meter and secondary nuclear phase instrument among the 6th Work tool die cavity 8-6 of lower floor, place safety strap among the 7th Work tool die cavity 8-7 of lower floor, place insulation megger and cable terminal annex among the 8th Work tool die cavity 8-8 of lower floor; Place the grounding resistance megger among the 9th Work tool die cavity 8-9 of lower floor, place warning sign among the tenth Work tool die cavity 8-10 of lower floor.
Place insulating boot among the first upper strata Work tool die cavity 3-1 in the pallet 3, place the low pressure grounding jumper among the second upper strata Work tool die cavity 3-2, place the high-voltage earthing line among the 3rd upper strata Work tool die cavity 3-3.
(5) 10KV cable fault repairing operation
The casing 1 inner side space down that is arranged in pallet 3 belows is placed safety precaution and field operation Work tool; Place safe fence among the first Work tool die cavity 8-1 of lower floor; Place safety cap among the second Work tool die cavity 8-2 of lower floor, place high voltage electroscope and low pressure voltage detector among the 3rd Work tool die cavity 8-3 of lower floor, place personality kit among the 4th Work tool die cavity 8-4 of lower floor; Place the instrument of ascending a height among the 5th Work tool die cavity 8-5 of lower floor; Place multi-meter and electric cable failure detector among the 6th Work tool die cavity 8-6 of lower floor, place safety strap among the 7th Work tool die cavity 8-7 of lower floor, place insulation megger and poisonous gas detection instrument among the 8th Work tool die cavity 8-8 of lower floor; Place the grounding resistance megger among the 9th Work tool die cavity 8-9 of lower floor, place warning sign among the tenth Work tool die cavity 8-10 of lower floor.
Place insulating boot among the first upper strata Work tool die cavity 3-1 in the pallet 3, place the low pressure grounding jumper among the second upper strata Work tool die cavity 3-2, place the high-voltage earthing line among the 3rd upper strata Work tool die cavity 3-3.
(6) 10KV on-pole switch kind equipment is changed operation
The casing 1 inner side space down that is arranged in pallet 3 belows is placed safety precaution and field operation Work tool; Place safe fence among the first Work tool die cavity 8-1 of lower floor; Place safety cap among the second Work tool die cavity 8-2 of lower floor, place high voltage electroscope and low pressure voltage detector among the 3rd Work tool die cavity 8-3 of lower floor, place personality kit among the 4th Work tool die cavity 8-4 of lower floor; Place the instrument of ascending a height among the 5th Work tool die cavity 8-5 of lower floor; Place multi-meter and secondary nuclear phase instrument among the 6th Work tool die cavity 8-6 of lower floor, place safety strap among the 7th Work tool die cavity 8-7 of lower floor, place the insulation megger among the 8th Work tool die cavity 8-8 of lower floor; Place the grounding resistance megger among the 9th Work tool die cavity 8-9 of lower floor, place warning sign among the tenth Work tool die cavity 8-10 of lower floor.
Place insulating boot among the first upper strata Work tool die cavity 3-1 in the pallet 3, place the low pressure grounding jumper among the second upper strata Work tool die cavity 3-2, place the high-voltage earthing line among the 3rd upper strata Work tool die cavity 3-3.
(7) the 10KV fuse switch is changed operation
The casing 1 inner side space down that is arranged in pallet 3 belows is placed safety precaution and field operation Work tool; Place safe fence among the first Work tool die cavity 8-1 of lower floor; Place safety cap among the second Work tool die cavity 8-2 of lower floor, place high voltage electroscope among the 3rd Work tool die cavity 8-3 of lower floor, place personality kit among the 4th Work tool die cavity 8-4 of lower floor; Place the instrument of ascending a height among the 5th Work tool die cavity 8-5 of lower floor; Place the low pressure voltage detector among the 6th Work tool die cavity 8-6 of lower floor, place safety strap among the 7th Work tool die cavity 8-7 of lower floor, place warning sign among the 8th Work tool die cavity 8-8 of lower floor.
Place insulating boot among the first upper strata Work tool die cavity 3-1 in the pallet 3, place the low pressure grounding jumper among the second upper strata Work tool die cavity 3-2, place the high-voltage earthing line among the 3rd upper strata Work tool die cavity 3-3.
In sum, the utility model is practical, widely applicable; Can realize in good order the putting of power matching network repairing Work tool; Help to realize rushing to repair the unified and standard and normalisation of flow process, field operation, equipment and Work tool configuration,, shorten the repairing time to greatest extent for improving repairing quality and efficient; Promote power supply reliability and good service level, have crucial meaning.
The above; It only is the preferred embodiment of the utility model; Be not that the utility model is done any restriction; Everyly any simple modification that above embodiment did, change and equivalent structure are changed, all still belong in the protection domain of the utility model technical scheme according to the utility model technical spirit.

Claims (8)

1. a power matching network is rushed to repair normalisation Work tool case; Comprise casing (1); It is characterized in that: the top of said casing (1) is connected with removable box cover (2); The inner below of said casing (1) is provided with first dividing plate (8) that polylith is used for the inner below of casing (1) spatial is divided into a plurality of lower floors Work tool die cavity; Said box house (2) top is provided with pallet (3), is provided with the second partition (4) that polylith is used for the spatial in the pallet (3) is divided into a plurality of upper stratas Work tool die cavity in the said pallet (3), and the shape of each said Work tool die cavity is complementary with the shape of the power matching network repairing Work tool of being placed respectively.
2. according to the described power matching network repairing of claim 1 normalisation Work tool case; It is characterized in that: the bottom of said casing (1) is a rectangular shape; The middle part shape of cross section of said casing (1) is for falling echelon form; Be symmetrical set on the upper inner wall of said casing (1) and be useful on the step (5) fixing with carrying the car side board; Said step (5) is to casing (1) outside protrusion, and said step (5) is provided with a plurality of being used for said power matching network repairing normalisation Work tool case is fixed on the fixed orifice (5-1) that carries on the car.
3. according to the described power matching network repairing of claim 2 normalisation Work tool case, it is characterized in that: the fall echelon form of the shape of cross section of said pallet (3) for matching with casing (1) middle part shape of cross section.
4. according to claim 1,2 or 3 described power matching network repairing normalisation Work tool casees; It is characterized in that: said casing (1) is provided with lock buckling groove (6-1), the snap close head (6-2) that said removable box cover (2) is provided with handle (7) and matches with lock buckling groove (6-1).
5. according to claim 1,2 or 3 described power matching network repairing normalisation Work tool casees, it is characterized in that: said removable box cover (2) flexibly connects through the top of hinge and casing (1).
6. according to claim 1,2 or 3 described power matching network repairing normalisation Work tool casees, it is characterized in that: be connected with the strut bar (9) that is used to regulate removable box cover (2) open angle between said casing (1) and the removable box cover (2).
7. according to claim 1,2 or 3 described power matching network repairing normalisation Work tool casees; It is characterized in that: the quantity of said first dividing plate (8) is nine, and the quantity of said lower floor Work tool die cavity is ten and is respectively first lower floor's Work tool die cavity (8-1), second lower floor's Work tool die cavity (8-2), the 3rd lower floor's Work tool die cavity (8-3), the 4th lower floor's Work tool die cavity (8-4), the 5th lower floor's Work tool die cavity (8-5), the 6th lower floor's Work tool die cavity (8-6), the 7th lower floor's Work tool die cavity (8-7), the 8th lower floor's Work tool die cavity (8-8), the 9th lower floor's Work tool die cavity (8-9) and the tenth lower floor's Work tool die cavity (8-10).
8. according to claim 1,2 or 3 described power matching network repairing normalisation Work tool casees; It is characterized in that: the quantity of said second partition (4) is two, and the quantity of said upper strata Work tool die cavity is three and is respectively the first upper strata Work tool die cavity (3-1), the second upper strata Work tool die cavity (3-2) and the 3rd upper strata Work tool die cavity (3-3).
CN2012201854585U 2012-04-27 2012-04-27 Power matching network recovery service standardization tool box Expired - Fee Related CN202518194U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012201854585U CN202518194U (en) 2012-04-27 2012-04-27 Power matching network recovery service standardization tool box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012201854585U CN202518194U (en) 2012-04-27 2012-04-27 Power matching network recovery service standardization tool box

Publications (1)

Publication Number Publication Date
CN202518194U true CN202518194U (en) 2012-11-07

Family

ID=47101156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012201854585U Expired - Fee Related CN202518194U (en) 2012-04-27 2012-04-27 Power matching network recovery service standardization tool box

Country Status (1)

Country Link
CN (1) CN202518194U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103308732A (en) * 2013-07-10 2013-09-18 国家电网公司 Electrical testing device
CN105655920A (en) * 2016-03-25 2016-06-08 国网山东省电力公司东明县供电公司 Multifunctional air-ground dual-purpose electric unmanned aerial vehicle

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103308732A (en) * 2013-07-10 2013-09-18 国家电网公司 Electrical testing device
CN105655920A (en) * 2016-03-25 2016-06-08 国网山东省电力公司东明县供电公司 Multifunctional air-ground dual-purpose electric unmanned aerial vehicle

Similar Documents

Publication Publication Date Title
CN204407893U (en) For the harmonic reactive compensating apparatus of Standard type
CN202518194U (en) Power matching network recovery service standardization tool box
CN202631598U (en) Distribution transforming monitoring metering box
CN103683268A (en) Portable charging-and-feedback integrated direct-current power supply
CN206148822U (en) Portable centrally connected power source switching box
CN106710954A (en) Outdoor high-voltage vacuum circuit breaker
CN204497637U (en) A kind of photovoltaic generation integral type transformer station
CN204495857U (en) The portable test connection platform of high-potting
CN203632235U (en) Portable charging and feedback integrated direct current power supply
CN202471779U (en) High voltage prepaying metering control box
CN202949188U (en) Cable busbar connector insulation protective device
CN201975704U (en) Lower earthing switch room of floor type alternating current high-voltage intelligent switch cabinet
CN201289967Y (en) Distribution box for base station
CN204010906U (en) A kind of transformer protector
CN203415837U (en) General anti-dropping grounding wire for transformer substation
CN207200110U (en) The cable of different voltage class and switch difference the service of connection devices
CN203352018U (en) Convenient wiring and removing device for buried transformer substation
CN204497580U (en) A kind of cable branch box
CN202534960U (en) Terminal-type box-type power transformation system
CN203014362U (en) 10 kV inlet wire protection and monitor apparatus
CN206501092U (en) A kind of detection case of intelligent power supply system
CN202059071U (en) Low-voltage integrated power distribution box
CN210515555U (en) Novel cable anti-theft device
CN202676766U (en) Novel ammeter case
CN219937890U (en) Ground cable junction box of submersible electric pump well

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Shaanxi Hua'an Electrical Technology Co., Ltd.

Assignor: Ma Yuliang

Contract record no.: 2013610000032

Denomination of utility model: Power matching network recovery service standardization tool box

Granted publication date: 20121107

License type: Exclusive License

Record date: 20130506

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180226

Address after: 710089 Shaanxi Xi'an city Yanliang District National Aviation high tech industrial base blue sky Road No. 5 Plant No. 6

Patentee after: Xi'an Zhongjiaxin Avionic Co., Ltd.

Address before: 710048 the 20 layer of Western power business center, Xi'an, Xi'an City, Shaanxi

Patentee before: Ma Yuliang

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180425

Address after: 710018 20-A, block A, Ya ho central building, Weiyang Road, Xi'an economic and Technological Development Zone, Shaanxi.

Patentee after: Shaanxi new Huaan Electric Power Engineering Co., Ltd.

Address before: 710089 6, No. 5 Lantian Road, National Aviation hi tech industrial base, Yanliang District, Xi'an, Shaanxi

Patentee before: Xi'an Zhongjiaxin Avionic Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121107

Termination date: 20190427