CN202454103U - Outward training and transmission line overhaul and hot-line work training integrated platform - Google Patents
Outward training and transmission line overhaul and hot-line work training integrated platform Download PDFInfo
- Publication number
- CN202454103U CN202454103U CN 201220041887 CN201220041887U CN202454103U CN 202454103 U CN202454103 U CN 202454103U CN 201220041887 CN201220041887 CN 201220041887 CN 201220041887 U CN201220041887 U CN 201220041887U CN 202454103 U CN202454103 U CN 202454103U
- Authority
- CN
- China
- Prior art keywords
- training
- transmission line
- power transmission
- transmission lines
- platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The utility model discloses an outward training and transmission line overhaul and hot-line work training integrated platform, which comprises a transmission line overhaul training device, wherein a standard climbing wall is arranged on the side of the transmission line overhaul training device; the top of the standard climbing wall is provided with a platform matched with a training operation platform of the transmission line overhaul training device, which is arranged in the air; and both the standard climbing wall and the transmission line overhaul training device are provided with safety devices. By adoption of the integrated platform, two kinds of different training modes are combined in a perfect mode, so that the comprehensive quality of trainees is improved; problems that high-altitude operation is not safe, and a trainer cannot conveniently train the trainees during professional transmission line training can be solved, and the trainer can guard and guide the trainees nearby; and land resources can be utilized in an intensified mode, so that the resource waste is reduced, and the comprehensive investment is saved. Besides, the whole equipment is simple in structure and can be conveniently, safely and reliably utilized.
Description
Technical field
The utility model relates to a kind of teaching and training equipment, relates in particular to the unified platform of a kind of outward bound and power transmission lines overhauling and hot line job training.
Background technology
Outward bound is the important step in the middle of the overall qualities training process in the electric system new staffs training, plays important effect aspect the sense of community conquering oneself, improve team spirit and strengthen.Simultaneously, in new staffs training, this professional training of transmission line of electricity and outward bound training have a lot of something in commons.A lot of high empty item and power transmission lines overhauling operation in the middle of the outward bound have something in common.In training in the past; Outward bound is as a kind of experience type training course; Purpose requires start-up's a series of through accomplishing (as grabbing thick stick, rock-climbing, aerial single-plank bridge etc. in the air) project exactly; Thereby improve new employee's team unity spirit, can in real work, overcome the mental handicape of oneself, conquer oneself.And power transmission lines overhauling training great majority all carry out in the high-altitude, need many people to carry out operation simultaneously, require them to work in coordination, the completion service work in the high-altitude of will conquering oneself simultaneously.In the training in the past, the two is separately independently to carry out, and is not occur simultaneously.Therefore, outward bound has become a kind of " recreation " in training process, and the power transmission lines overhauling training is comparatively uninteresting, also requires to accomplish in the high-altitude.
But present exercise equipment security is not high, the equipment that outward bound is not combined with power transmission lines overhauling, so training effect is not good, security can't ensure.
The utility model content
The purpose of the utility model is exactly in order to address the above problem; The unified platform of a kind of outward bound and power transmission lines overhauling and hot line job training is provided; It is rational in infrastructure; Security is good, and common outward bound equipment is combined with power transmission line maintenance exercise equipment, has improved training efficiency and training quality.
The purpose of the utility model realizes through following technical scheme:
The unified platform of a kind of outward bound and power transmission lines overhauling and hot line job training; It comprises the power transmission lines overhauling training set; Be provided with the standard climbing wall in power transmission lines overhauling training set side, be provided with platform at standard rock-climbing coping and match with the skyborne training operating platform of being provided with of power transmission lines overhauling training set; Standard climbing wall and power transmission lines overhauling training set are equipped with safety device.
Said power transmission lines overhauling training set also comprises the transmission line of electricity terminal bearing that is provided with on the training operating platform, and bearing is equipped with power transmission line at the transmission line of electricity terminal, is provided with the straight line insulator between power transmission line; Power transmission line is connected with the transmission line of electricity terminal tower that is provided with that keeps at a certain distance away, and on the transmission line of electricity terminal tower, also is provided with the training operating platform.
Said power transmission line is connected with the transmission line of electricity terminal tower through strain insulator.
Said safety device comprises that wire rope that the outward bound device is used and power transmission lines overhauling and hot line job training use by the safety rope or belt.
The unified platform of this outward bound and power transmission lines overhauling and hot line job training is made up of a cover steel construction combined bay.The outward bound device is formed safety system by wire rope, and power transmission lines overhauling and hot line job training set are formed safety system by safety rope (band).Two covering devices can be separately about, but also intercommunication.Every covering device all has independently High Altitude Platform, conveniently carries out training separately or that intersect.
The beneficial effect of the utility model is:
Can two kinds of different training and the perfect fusion of training method trainee's overall qualities have been promoted.Can solve the safety of transmission line of electricity professional training work high above the ground and the difficult problem that the trainer instructs, the trainer can guard and instruct at High Altitude Platform nearby.The use land resource that can intensify has reduced the wasting of resources and has saved the comprehensive method of investment.Entire equipment is simple in structure, and is easy to use, safe and reliable.
Description of drawings
Fig. 1 is the structural representation of the utility model.
Wherein, 1. standard climbing wall, 2. other outward bound device space capable of using, 3. straight line insulator, 4. strain insulator, 5. transmission line of electricity terminal bearing, 6. training operating platform, 7. transmission line of electricity terminal tower.
Embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is further specified.
Among Fig. 1, the outward bound device comprises standard climbing wall 1, and a side of it and power transmission lines overhauling training set links together; Top at standard climbing wall 1 is provided with platform, and this platform matches with the training operating platform 6 of power transmission lines overhauling training set, makes things convenient for personnel to climb rocks and changes the power transmission lines overhauling training set over to behind the top.On training operating platform 6, be provided with transmission line of electricity terminal bearing 5, transmission line of electricity terminal bearing 5 is provided with power transmission line, is provided with straight line insulator 3 between power transmission line, and power transmission line is connected through strain insulator 4 with transmission line of electricity terminal tower 7 at a distance.On transmission line of electricity terminal tower 7, also be provided with training operating platform 6.The space that transmission line of electricity terminal tower 7 and standard climbing wall are 1 is other outward bound device space 2 capable of using.
Standard climbing wall and power transmission lines overhauling training set are equipped with safety device, and said safety device comprises that wire rope that the outward bound device is used and power transmission lines overhauling and hot line job training use by the safety rope or belt.
Claims (4)
1. the unified platform of an outward bound and power transmission lines overhauling and hot line job training; It is characterized in that; It comprises the power transmission lines overhauling training set; Be provided with the standard climbing wall in power transmission lines overhauling training set side, be provided with platform at standard rock-climbing coping and match with the skyborne training operating platform of being provided with of power transmission lines overhauling training set; Standard climbing wall and power transmission lines overhauling training set are equipped with safety device.
2. the unified platform of outward bound as claimed in claim 1 and power transmission lines overhauling and hot line job training; It is characterized in that; Said power transmission lines overhauling training set also comprises the transmission line of electricity terminal bearing that is provided with on the training operating platform; Bearing is equipped with power transmission line at the transmission line of electricity terminal, is provided with the straight line insulator between power transmission line; Power transmission line is connected with the transmission line of electricity terminal tower that is provided with that keeps at a certain distance away, and on the transmission line of electricity terminal tower, also is provided with the training operating platform.
3. the unified platform of outward bound as claimed in claim 2 and power transmission lines overhauling and hot line job training is characterized in that, said power transmission line is connected with the transmission line of electricity terminal tower through strain insulator.
4. the unified platform of outward bound as claimed in claim 1 and power transmission lines overhauling and hot line job training; It is characterized in that said safety device comprises that wire rope that the outward bound device is used and power transmission lines overhauling and hot line job training use by the safety rope or belt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220041887 CN202454103U (en) | 2012-02-09 | 2012-02-09 | Outward training and transmission line overhaul and hot-line work training integrated platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201220041887 CN202454103U (en) | 2012-02-09 | 2012-02-09 | Outward training and transmission line overhaul and hot-line work training integrated platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202454103U true CN202454103U (en) | 2012-09-26 |
Family
ID=46869950
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201220041887 Expired - Fee Related CN202454103U (en) | 2012-02-09 | 2012-02-09 | Outward training and transmission line overhaul and hot-line work training integrated platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202454103U (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103258464A (en) * | 2013-04-19 | 2013-08-21 | 国家电网公司 | Double-circuit tension-resistant electric pole analog device for practical training of live working |
CN104091480A (en) * | 2014-05-26 | 2014-10-08 | 国家电网公司 | Transmission line condition-based maintenance simulation training method |
CN106373467A (en) * | 2016-10-18 | 2017-02-01 | 国网福建省电力有限公司 | Power transmission and transformation live line work training simulation platform training method |
CN106409085A (en) * | 2016-10-18 | 2017-02-15 | 国网福建省电力有限公司 | Power transmission and transformation live working practical-training simulation stand |
CN106781924A (en) * | 2017-01-23 | 2017-05-31 | 中国电力科学研究院 | Extra high voltage line livewire work actual training device |
CN106952514A (en) * | 2017-04-30 | 2017-07-14 | 国网江苏省电力公司职业技能训练基地 | It is a kind of to simulate the equipment that substation is operated every hotline maintenance |
CN110706544A (en) * | 2019-10-24 | 2020-01-17 | 国网山东省电力公司应急管理中心 | Rack for high-altitude rescue training of power transmission line and training system |
-
2012
- 2012-02-09 CN CN 201220041887 patent/CN202454103U/en not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103258464A (en) * | 2013-04-19 | 2013-08-21 | 国家电网公司 | Double-circuit tension-resistant electric pole analog device for practical training of live working |
CN104091480A (en) * | 2014-05-26 | 2014-10-08 | 国家电网公司 | Transmission line condition-based maintenance simulation training method |
CN106373467A (en) * | 2016-10-18 | 2017-02-01 | 国网福建省电力有限公司 | Power transmission and transformation live line work training simulation platform training method |
CN106409085A (en) * | 2016-10-18 | 2017-02-15 | 国网福建省电力有限公司 | Power transmission and transformation live working practical-training simulation stand |
CN106781924A (en) * | 2017-01-23 | 2017-05-31 | 中国电力科学研究院 | Extra high voltage line livewire work actual training device |
CN106781924B (en) * | 2017-01-23 | 2021-01-29 | 中国电力科学研究院 | Live working training device for extra-high voltage line |
CN106952514A (en) * | 2017-04-30 | 2017-07-14 | 国网江苏省电力公司职业技能训练基地 | It is a kind of to simulate the equipment that substation is operated every hotline maintenance |
CN106952514B (en) * | 2017-04-30 | 2019-05-21 | 国网江苏省电力公司职业技能训练基地 | A kind of equipment that simulation substation is operated every hotline maintenance |
CN110706544A (en) * | 2019-10-24 | 2020-01-17 | 国网山东省电力公司应急管理中心 | Rack for high-altitude rescue training of power transmission line and training system |
CN110706544B (en) * | 2019-10-24 | 2021-09-07 | 国网山东省电力公司应急管理中心 | Rack for high-altitude rescue training of power transmission line and training system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202454103U (en) | Outward training and transmission line overhaul and hot-line work training integrated platform | |
CN109102731A (en) | A kind of substation simulation platform and method based on VR | |
CN109410669A (en) | Replacing insulator operation simulation training system based on VR | |
CN206627708U (en) | A kind of new VR glasses with a variety of experience functions | |
CN204163606U (en) | A kind of electric power work high above the ground multimode combined type maintenance step ladder | |
CN206388436U (en) | A kind of transmission tower high-altitude trainer | |
CN205206454U (en) | Green and safe wire pole | |
CN201625859U (en) | Locomotive gearbox assembly and disassembly service cart | |
CN203800449U (en) | Overhaul platform of equipment on transformer station pillar | |
CN201705193U (en) | Dedicated flexible ladder used for replacing insulators | |
CN103117021B (en) | Falling derrick construction technology teaching simulator | |
CN203632113U (en) | Portable safety string bag for electric pole | |
CN202926197U (en) | Auxiliary hooking device for safety belt of steel tube tower | |
CN202754442U (en) | Conveyor device for 110-500KV steel pylon | |
CN201882845U (en) | Portable special jack for cable cover plate | |
CN203284100U (en) | Tower crane achieving automatic replacement of steel wire rope | |
CN201904572U (en) | Trolley for transferring rope | |
CN203054154U (en) | Polarity test rod for outdoor current transformers | |
CN202897968U (en) | Detachable fixing device of aerial work platform scissor fork shaft | |
CN204113099U (en) | 10kV distribution irony shaft tower folds hanging ladder | |
CN204517280U (en) | Single string synthetic insulator seton device | |
CN207795039U (en) | A kind of herringbone maintenance ladder with pulley gear | |
CN203734210U (en) | 110kV dry outdoor cable terminal hoisting assistance device | |
CN203255831U (en) | Connecting and fastening device of lifting machine for external use of wind-power tower drum | |
CN204044993U (en) | A kind of carbon fiber composite core wire plug Non-Destructive Testing radio transmitting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120926 Termination date: 20140209 |