CN202450111U CN2011204925111U CN201120492511U CN202450111U CN 202450111 U CN202450111 U CN 202450111U CN 2011204925111 U CN2011204925111 U CN 2011204925111U CN 201120492511 U CN201120492511 U CN 201120492511U CN 202450111 U CN202450111 U CN 202450111U
Authority
CN
China
Prior art keywords
elephant trunk
turndown
middle hopper
materials
hopper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011204925111U
Other languages
Chinese (zh)
Inventor
杨成
王郢
郭键
刘嵘
郭丽红
毛建新
张卫东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xingtai Iron and Steel Co Ltd
Original Assignee
Xingtai Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xingtai Iron and Steel Co Ltd filed Critical Xingtai Iron and Steel Co Ltd
Priority to CN2011204925111U priority Critical patent/CN202450111U/en
Application granted granted Critical
Publication of CN202450111U publication Critical patent/CN202450111U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a device for charging materials during turndown and belongs to the technical field of steelmaking equipment. The device is used for charging the materials in two turndown directions of steel and slag discharging. According to the technical scheme, a charging hopper consists of a rotary elephant trunk, a middle hopper and a fixed elephant trunk; the lower end of the fixed elephant trunk is connected with a charging hole; the middle hopper is connected between the fixed elephant trunk and the rotary elephant trunk; the upper part of the rotary elephant trunk is bent toward one side; the middle hopper is a cuboid, a cylinder, or a cylindroid; and the horizontal section of the middle hopper is larger than the circumferential sections of the fixed elephant trunk and the charging hole. The device can charge the materials in the turndown directions of steel and slag discharging, so that the materials are charged uniformly, and the slagging effect is guaranteed; pressed slag materials are uniformly charged, so that the damage of overflowed molten steel to a rail and equipment below a furnace can be avoided, and the personal safety is guaranteed; and when the materials are charged during turndown, a furnace lining is uniformly heated and protected, the service life of the furnace lining is prolonged, the refractory materials of the furnace lining are saved, and the great loss caused by runout can be avoided.

Description

The reinforced device of a kind of ability turndown
Technical field
The utility model relates to a kind of feeding device of iron alloy smelting furnace, belongs to the steelmaking equipment technical field.
Background technology
The adding mode of iron alloy smelting furnace alloy material has two kinds, and first kind for reinforced behind the bell of outwarding winding, and second kind for to feed in raw material through the charge cavity on the bell.The reinforced program of outwarding winding behind the bell is complicated, and electrode needs to have a power failure, promote, and is prone to cause dissipation of heat energy, and general at present the employing fed in raw material through the charge cavity on the bell.But in process of production,, can not satisfy, cause burden distribution inhomogeneous, influence the slag making effect tapping, feeding in raw material when slagging tap turndown for the charge cavity that this feed way designed can only could feed in raw material when stove is in vertical position; Owing to press can not evenly adding of slag charge, might cause molten steel excessive simultaneously, damage track and equipment under the stove, security incident takes place; And when turndown, can not feed in raw material, it is inhomogeneous that furnace lining is heated, and reduced the life-span of furnace lining, and runout might take place, the massive losses that brings.
The utility model content
The utility model technical problem to be solved provides a kind of reinforced device of ability turndown that can tap, feed in raw material when slagging tap two turndown directions.
The technical scheme that solves the problems of the technologies described above is:
The reinforced device of a kind of ability turndown, it comprises center bell, charge cavity, water cooled cover, on the bell of center, is evenly equipped with 3 electrode holes; Its improvements are, its loading hopper is made up of rotation elephant trunk, middle hopper, fixed slide pipe, and the lower end of fixed slide pipe is connected with charge cavity; The upper end of fixed slide pipe connects middle hopper, and the rotation elephant trunk is installed in the upper end of middle hopper, and the bottom of rotation elephant trunk is connected with the middle hopper vertical fixing; The top of rotation elephant trunk is to a lateral buckling, and middle hopper is a rectangular parallelepiped, or cylinder; Or elliptical cylinder, the horizontal section of middle hopper is greater than the circumferential section of fixed slide pipe and charge cavity.
The reinforced device of above-mentioned ability turndown, for being rotatably connected, the angle between top bending part and the lower vertical part is greater than 90 degree between the top bending part of said rotation elephant trunk and the lower vertical part.
The reinforced device of above-mentioned ability turndown; Said charge cavity is between two electrode holes of center bell; With two electrode hole equidistance, the minor increment at charge cavity margin and center bell center is greater than the distance at electrode hole Center-to-Center bell center, and the diameter of charge cavity is less than the diameter of electrode hole.
The usefulness of the utility model is:
The utility model has improved the position of feeding device and the shape of loading hopper, has solved in tapping, the reinforced problem of two the turndown directions of slagging tap.Guarantee to feed in raw material evenly, guaranteed the slag making effect; Press the even adding of slag charge simultaneously, prevent track and equipment under the excessive damage stove of molten steel, guarantee personnel safety; Reinforced when turndown, furnace lining is heated evenly, protected furnace lining, prolonged furnace lining life-span, practiced thrift the anti-material of furnace lining, prevent the massive losses that runout brings.
Description of drawings
Fig. 1 is the structural representation of the utility model;
Fig. 2 is the vertical view of Fig. 1.
Mark is following among the figure: rotation elephant trunk 1, middle hopper 2, fixed slide pipe 3, charge cavity 4, water cooled cover 5, center bell 6, electrode hole 7.
Embodiment
Show among the figure that the utility model improves loading hopper.
Loading hopper is made up of rotation elephant trunk 1, middle hopper 2, fixed slide pipe 3.Middle hopper 2 is connected between fixed slide pipe 3 and the rotation elephant trunk 1, and the lower end of fixed slide pipe 3 is connected with charge cavity 4, and the top of rotation elephant trunk 1 is to a lateral buckling.When reinforced, furnace charge is added middle hopper 2, through fixed slide pipe 3, charge cavity 4 furnace charge is added positions different in the iron alloy smelting furnace again through rotation elephant trunk 1.
Show among the figure that middle hopper 2 is a rectangular parallelepiped, or cylinder, or other geometrical shapies such as elliptical cylinder, the horizontal section of middle hopper 2 is greater than the circumferential section of fixed slide pipe 3 and charge cavity 4.
Show among the figure that rotation elephant trunk 1 is two body structures, its bottom is a straight tube; Be connected with the upper surface vertical fixing of middle hopper 2; Its top is to a lateral buckling, and for being rotatably connected, the angle between bending top and the vertical lower is greater than 90 degree between the upper and lower part.
After adopting this structure, be in slagging tap, tapping during state of heeling condition, can rotation elephant trunk 1 be rotated at body of heater; The feeding mouth of rotation elephant trunk 1 is made progress; Promptly can in body of heater, feed in raw material, the volume of middle hopper 2 is bigger, can hold more material; Make even pan feeding when feeding in raw material, avoid suspending and interrupted pan feeding.
Show among the figure; Improve the position of the utility model charge cavity 4, and the position of original charge cavity 4 by changing into now on center bell 6 on the water cooled cover 5, can be added the electrode of iron alloy smelting furnace near the hot-zone with furnace charge like this; Guarantee that furnace charge can add the hot-zone of stove; Quickened furnace charge fusing, make molten steel composition even, prolonged furnace lining life-span, practiced thrift the anti-material of furnace lining, guaranteed that the operative employee can observe the furnace lining situation.
Show among the figure; The position of the charge cavity 4 after the improvement is between two electrode holes 7 of center bell 6; Charge cavity 4 and the distance of bell 6 width between centerss in center greater than electrode hole 7 and center bell 2 centers; Can make charge cavity 4 and electrode keep certain distance like this, avoid charge cavity 4 ionization electrodes near excessively, the situation that electricity causes structure deteriorate takes place to connect.
The utility model has been realized the uniform distribution of iron alloy smelting furnace furnace charge through the enforcement of the reinforced device of ability turndown, guarantees to feed in raw material in tapping, two the turndown directions of slagging tap.

Claims (3)

1. the reinforced device of an ability turndown, it comprises center bell (6), charge cavity (4), water cooled cover (5), on center bell (6), is evenly equipped with 3 electrode holes (7); It is characterized in that: its loading hopper is made up of rotation elephant trunk (1), middle hopper (2), fixed slide pipe (3); The lower end of fixed slide pipe (3) is connected with charge cavity (4), and the upper end of fixed slide pipe (3) connects middle hopper (2), and rotation elephant trunk (1) is installed in the upper end of middle hopper (2); The bottom of rotation elephant trunk (1) is connected with middle hopper (2) vertical fixing; The top of rotation elephant trunk (1) is to a lateral buckling, and middle hopper (2) is a rectangular parallelepiped, or cylinder; Or elliptical cylinder, the horizontal section of middle hopper (2) is greater than the circumferential section of fixed slide pipe (3) and charge cavity (4).
2. the reinforced device of ability turndown according to claim 1 is characterized in that: for being rotatably connected, the angle between top bending part and the lower vertical part is greater than 90 degree between the top bending part of said rotation elephant trunk (1) and the lower vertical part.
3. the reinforced device of ability turndown according to claim 2; It is characterized in that: said charge cavity (4) is positioned between two electrode holes (7) of center bell (6); With two electrode holes (7) equidistance; The minor increment at charge cavity margin and center bell center is greater than the distance at electrode hole Center-to-Center bell center, and the diameter of charge cavity (4) is less than the diameter of electrode hole (7).
CN2011204925111U 2011-12-01 2011-12-01 Device for charging materials during turndown Expired - Fee Related CN202450111U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204925111U CN202450111U (en) 2011-12-01 2011-12-01 Device for charging materials during turndown

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204925111U CN202450111U (en) 2011-12-01 2011-12-01 Device for charging materials during turndown

Publications (1)

Publication Number Publication Date
CN202450111U true CN202450111U (en) 2012-09-26

Family

ID=46865992

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204925111U Expired - Fee Related CN202450111U (en) 2011-12-01 2011-12-01 Device for charging materials during turndown

Country Status (1)

Country Link
CN (1) CN202450111U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103925785A (en) * 2014-05-07 2014-07-16 苏州皇森机电科技有限公司 Feeding device of rotary kiln

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103925785A (en) * 2014-05-07 2014-07-16 苏州皇森机电科技有限公司 Feeding device of rotary kiln
CN103925785B (en) * 2014-05-07 2016-02-10 太仓市高泰机械有限公司 A kind of feeding device of rotary kiln

Similar Documents

Publication Publication Date Title
US9453678B2 (en) Apparatus for manufacturing molten metal
CN103344112B (en) Banish method corundum smelting stove
CN103333979B (en) Electricity coal method molten point reduction iron production system and technical process thereof
CN202450111U (en) Device for charging materials during turndown
CN107218800B (en) A kind of direct current electric arc furnace
CN203964657U (en) A kind of special-purpose induction furnace of ferroalloy smelting
CN204388616U (en) Loading device for feeding electric furnace
CN110819791A (en) Production process of nickel-containing molten iron with low iron distribution and low silicon-magnesium ratio for submerged arc furnace
CN201545862U (en) Distribution chute for blast furnace
CN205067396U (en) Hot modified test device of refining slag
CN104344711A (en) Split furnace cover
CN203200287U (en) Melting reduction iron-making system employing electricity-coal method
CN102776307B (en) Single cast house system of double-taphole blast furnace
CN202074829U (en) Full sealed lead discharging groove type ore-smelting furnace bottom
CN202450115U (en) Furnace mouth tapping slot device for argon oxygen refining furnace
CN203917899U (en) A kind of Novel hot-metal bottle tank mouth structure
CN201593911U (en) Three-phase alternating current furnace for aluminum-silicon alloy mine
CN206768167U (en) A kind of masonry construction of RH refining furnaces lower channel
CN219797870U (en) Discharging pipe of submerged arc furnace
CN202329196U (en) Groove carbon block for molten iron flow groove of ore-smelting electric furnace
CN104567423B (en) Loading device for feeding electric furnace
CN204261744U (en) A kind of semi-autogenous mill feed arrangement
CN202414526U (en) Limestone storage device
CN202793008U (en) Slag and iron discharging structure of titanium slag electric-arc furnace
CN201620172U (en) Blast furnace mixer with novel iron outlet

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120926

Termination date: 20151201