CN202391115U - Construction device taking air bag as foundation preformed hole - Google Patents

Construction device taking air bag as foundation preformed hole Download PDF

Info

Publication number
CN202391115U
CN202391115U CN2011205142392U CN201120514239U CN202391115U CN 202391115 U CN202391115 U CN 202391115U CN 2011205142392 U CN2011205142392 U CN 2011205142392U CN 201120514239 U CN201120514239 U CN 201120514239U CN 202391115 U CN202391115 U CN 202391115U
Authority
CN
China
Prior art keywords
air bag
preformed hole
basic
construction device
construction equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011205142392U
Other languages
Chinese (zh)
Inventor
罗卓英
沈家文
张立超
李明华
杨国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Construction Engineering Water Conservancy & Hydropower Construction Co Ltd
Original Assignee
Yunnan Construction Engineering Water Conservancy & Hydropower Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Construction Engineering Water Conservancy & Hydropower Construction Co Ltd filed Critical Yunnan Construction Engineering Water Conservancy & Hydropower Construction Co Ltd
Priority to CN2011205142392U priority Critical patent/CN202391115U/en
Application granted granted Critical
Publication of CN202391115U publication Critical patent/CN202391115U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to the technical field of building construction equipment and discloses a construction device taking an air bag as a foundation preformed hole. The construction device comprises a foundation main body; the preformed hole is formed on the foundation main body; the preformed hole is provided with the air bag; the air bag is mounted at the inner side of the preformed hole; the air bag is provided with an air bag body; and a vent hole is formed at the top end of the air bag body. The construction device taking the air bag as the foundation preformed hole has the advantages of simplicity and convenience in dismounting, reusability and low cost.

Description

A kind of air bag is made basic preformed hole construction equipment
Technical field
The utility model relates to the technical field of construction implement device.
Background technology
Chinese invention patent number: 200710152304.X discloses a kind of preparation method of architecture pipeline preformed hole; It is characterized in that: the method that pipeline preformed hole adopts substep to reserve: the first step is fixed on thin sleeve pipe on the template by fixed bar; Avoid the preformed hole position, colligation preformed hole position main reinforcement and constructional reinforcement are after colligation is accomplished; Second step with thick casing pipe sleeve on thin sleeve pipe, place on the main reinforcement and constructional reinforcement of colligation; Colligation constructional reinforcement and button iron run into the position of outer tube during colligation again, do bending process; 3. guaranteeing fluid concrete under the situation that main reinforcement, constructional reinforcement and thick, thin sleeve pipe are not subjected to displacement; 4. thick, thin sleeve pipe and mould are pulled the concrete of cast, preformed hole is promptly accomplished.
Being cast in of basis preformed hole, hole mainly in traditional work progress adopts material such as wooden as template, and template is placed in the basic precast reinforced frame, then template fixed, and carries out base concrete again to build, build completion after, template is split out.After concreting was accomplished, template was not drawn out easily, and wastes time and energy, and damages template easily, waste material.
The utility model content
The utility model purpose aims to provide a kind of air bag and makes basic preformed hole construction equipment, and it is easy that this air bag is done basic preformed hole construction equipment dismounting, can reuse, and cost is low.
For realizing above-mentioned purpose; The technical scheme that the utility model adopts is: a kind of air bag is made basic preformed hole construction equipment, comprises basic main body, and said basic main body is provided with preformed hole; Said preformed hole is provided with air bag; Said air bag is installed in the inboard of preformed hole, and said air bag is provided with airbag body, and said airbag body top is provided with air vent.
Said a kind of air bag is made basic preformed hole construction equipment, and its preformed hole is identical with shape, the size of air bag.
Said a kind of air bag is made basic preformed hole construction equipment, and its air bag is the air bag of sealing.
This air bag is made basic preformed hole construction equipment and is mainly adopted air bag to replace template, and air bag replaces the wooden template that waits material, removes easyly, can reuse, and cost is low, has avoided material damage, the saving cost.Save the operation of setting up fixed mount, accelerated construction speed.This air bag is made basic preformed hole construction equipment and is applicable to basic preformed hole, hole, is specially adapted to the darker situation of preformed hole.
Description of drawings
Sketch map in Fig. 1 the utility model specific embodiment.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is further described.
As shown in Figure 1: a kind of air bag is made basic preformed hole construction equipment; Comprise basic main body 1, preformed hole 2, air bag 3, airbag body 4, air vent 5; Said basic main body 1 is provided with preformed hole 2, and said preformed hole 2 is provided with air bag 3, and said air bag 3 is installed in the inboard of preformed hole 2; Said air bag 3 is provided with airbag body 4, and said airbag body 4 tops are provided with air vent 5.Adopt air bag 3 to replace template, earlier air bag 3 is inflated, air bag 3 is made according to the shape and the design size of basic preformed hole 2, and the air bag of making 3 is fixed on the relevant position.Treat that base concrete builds completion, the gas of air bag 3 is carried out emptying after, air bag 3 is pulled out.
A kind of air bag is made basic preformed hole construction equipment; Comprise basic main body 1, preformed hole 2, air bag 3, airbag body 4, air vent 5; Said basic main body 1 is provided with preformed hole 2, and said preformed hole 2 is provided with air bag 3, and said air bag 3 is installed in the inboard of preformed hole 2; Said air bag 3 is provided with airbag body 4, and said airbag body 4 tops are provided with air vent 5.Its air bag 3 is identical with shape, the size of preformed hole 2.Its air bag 3 is the air bag 3 of sealing.Adopt air bag 3 to replace template, earlier air bag 3 is inflated, air bag 3 is made according to the shape and the design size of basic preformed hole 2, and the air bag of making 3 is fixed on the relevant position.Treat that base concrete builds completion, the gas of air bag 3 is carried out emptying after, air bag 3 is pulled out.This air bag is made basic preformed hole construction equipment and is mainly adopted air bag to replace template, and air bag replaces the wooden template that waits material, removes easyly, can reuse, and cost is low, has avoided material damage, the saving cost.Save the operation of setting up fixed mount, accelerated construction speed.This air bag is made basic preformed hole construction equipment and is applicable to basic preformed hole, hole, is specially adapted to the darker situation of preformed hole.

Claims (3)

1. an air bag is made basic preformed hole construction equipment, comprises basic main body, it is characterized in that; Said basic main body is provided with preformed hole, and said preformed hole is provided with air bag, and said air bag is installed in the inboard of preformed hole; Said air bag is provided with airbag body, and said airbag body top is provided with air vent.
2. make basic preformed hole construction equipment according to the said a kind of air bag of claim 1, it is characterized in that, said preformed hole is identical with shape, the size of air bag.
3. make basic preformed hole construction equipment according to the said a kind of air bag of claim 1, it is characterized in that, said air bag is the air bag of sealing.
CN2011205142392U 2011-12-12 2011-12-12 Construction device taking air bag as foundation preformed hole Expired - Lifetime CN202391115U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011205142392U CN202391115U (en) 2011-12-12 2011-12-12 Construction device taking air bag as foundation preformed hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011205142392U CN202391115U (en) 2011-12-12 2011-12-12 Construction device taking air bag as foundation preformed hole

Publications (1)

Publication Number Publication Date
CN202391115U true CN202391115U (en) 2012-08-22

Family

ID=46666049

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011205142392U Expired - Lifetime CN202391115U (en) 2011-12-12 2011-12-12 Construction device taking air bag as foundation preformed hole

Country Status (1)

Country Link
CN (1) CN202391115U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019558A (en) * 2015-08-02 2015-11-04 长安大学 Steel bar anchoring connection structure and connection method for precast fabricated concrete components
CN105014785A (en) * 2015-08-02 2015-11-04 长安大学 Steel bar anchoring preformed hole forming device and method for prefabricated assembled type concrete members
CN108999397A (en) * 2018-05-31 2018-12-14 重庆建工建材物流有限公司 The clear-water concrete exposed joint strip of outseam is hardly damaged when demoulding
CN109339089A (en) * 2018-09-19 2019-02-15 中铁十六局集团城市建设发展有限公司 A kind of rim of a cup isolated footing cup core forming method
CN113200250A (en) * 2021-04-27 2021-08-03 杨国栋 Fluidized bed assembly of bulk cement tank car
CN114718299A (en) * 2022-04-30 2022-07-08 北京中铁建建筑科技有限公司 Recyclable filling template and method for building construction

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105019558A (en) * 2015-08-02 2015-11-04 长安大学 Steel bar anchoring connection structure and connection method for precast fabricated concrete components
CN105014785A (en) * 2015-08-02 2015-11-04 长安大学 Steel bar anchoring preformed hole forming device and method for prefabricated assembled type concrete members
CN108999397A (en) * 2018-05-31 2018-12-14 重庆建工建材物流有限公司 The clear-water concrete exposed joint strip of outseam is hardly damaged when demoulding
CN109339089A (en) * 2018-09-19 2019-02-15 中铁十六局集团城市建设发展有限公司 A kind of rim of a cup isolated footing cup core forming method
CN113200250A (en) * 2021-04-27 2021-08-03 杨国栋 Fluidized bed assembly of bulk cement tank car
CN114718299A (en) * 2022-04-30 2022-07-08 北京中铁建建筑科技有限公司 Recyclable filling template and method for building construction

Similar Documents

Publication Publication Date Title
CN202391115U (en) Construction device taking air bag as foundation preformed hole
CN203022024U (en) Integrally-movable formwork for pipe gallery cast-in-situ construction
CN105696599A (en) Pressurizing grouting method utilizing air bag blockage device
CN102966121A (en) Integrally movable mould frame for pipe rack cast-in-site construction
CN202448226U (en) Molding mould group for prestressed steel cylinder concrete pipe applied to jacking construction method
CN202970767U (en) Air bag plugging device
CN104141351A (en) Sealing method for reserved paying-off hole and paying-off hole mold
CN205889490U (en) Adopt empty core plate's of precast concrete of rubber tube pore -forming mould
CN101806067A (en) Construction method of underground continuous wall joints by using air bag
CN206351135U (en) Precast slab automatic mold cleaning device
CN204199694U (en) Concrete preformed hole shaping device
CN103882992A (en) Connection piece with annular steel bar
CN103882840B (en) A kind of surge shaft Cast-in-place concrete assembling falsework and mounting method thereof
CN204001212U (en) Band ring-type rebar connector
CN205935681U (en) Inflatable plastics mould shell removal tool
CN202727092U (en) Plugging device for position of straight rib of side mold of precast concrete component of wall
CN209479705U (en) Transport vehicle is used in a kind of reinforcing of jacking construction tube head
CN101812900A (en) Reinforced mortar pipe with reserved hole and method for steel bar connection
CN201953085U (en) Crack-repairing device for making up concrete crack
CN203905326U (en) Construction form for construction of roof exhaust pipe piers
CN111749260A (en) Prefabricated bearing platform suitable for foundation construction of offshore wind power high-rise pile bearing platform and construction method
CN203846406U (en) Air bag inner mold for bridge reinforcement
CN102296598A (en) Construction method of PCC (cast-in-place concrete large-diameter pipe) pile
CN112012216A (en) Double-liquid rotary spraying reinforcement method for improving bearing capacity of steel pipe pile
CN102704685A (en) Quick insert tube of concreting blanking and use method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20120822

CX01 Expiry of patent term