CN202358139U - Relay protection test trolley for maintenance of power substation - Google Patents

Relay protection test trolley for maintenance of power substation Download PDF

Info

Publication number
CN202358139U
CN202358139U CN2011205041584U CN201120504158U CN202358139U CN 202358139 U CN202358139 U CN 202358139U CN 2011205041584 U CN2011205041584 U CN 2011205041584U CN 201120504158 U CN201120504158 U CN 201120504158U CN 202358139 U CN202358139 U CN 202358139U
Authority
CN
China
Prior art keywords
base plate
maintenance
protection test
lower floor
relay protection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011205041584U
Other languages
Chinese (zh)
Inventor
蒋柯青
谢士奇
黄剑
王建东
沈虎
王谊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHUJI POWER SUPPLY BUREAU
State Grid Corp of China SGCC
Original Assignee
ZHUJI POWER SUPPLY BUREAU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHUJI POWER SUPPLY BUREAU filed Critical ZHUJI POWER SUPPLY BUREAU
Priority to CN2011205041584U priority Critical patent/CN202358139U/en
Application granted granted Critical
Publication of CN202358139U publication Critical patent/CN202358139U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model provides a relay protection test trolley for maintenance of a power substation. The relay protection test trolley comprises a lower-layer bottom plate and an upper-layer bottom plate, wherein the lower-layer bottom plate is connected with the upper-layer bottom plate through a supporting rod; and a push rod and a pulley are mounted on the lower-layer bottom plate. With the adoption of the relay protection test trolley provided by the utility model, the timeliness of the maintenance of the power substation is improved; the problems of more relay protection instruments, inconvenience in transportation, wiring, mounting and dismounting, and the like in a maintenance process can be effectively solved; and the relay protection test trolley has the characteristics of improving the maintenance quality and efficiency and being good for personal and equipment safety on site.

Description

A kind of substation maintenance reaying protection test dolly
Technical field
The utility model relates to a kind of substation maintenance reaying protection test dolly.
Background technology
At present, the continuous development of electric system and safe and stable operation have brought huge power and benefit to national economy and social development.Relaying is exactly to ensure power equipment safety and the most basic, most important, the effective technical means that prevents and limit the long-time large-area power-cuts of electric system.Facts have proved that for many years debugging and conventional maintenance verification are depended in the maintenance of protective relaying device performance to a great extent; Substation's maintenance reaying protection test needs check apparatus to accomplish; It is various to test required check apparatus and instrument, whenever carries out the verification of a project, just needs to change instrument and dismounting wiring; These work at present all need a dead lift; Work-site is at random, and efficient reduces, and is unfavorable for the person, device security.Carried out concrete investigation statistics through interval reaying protection test situation under the area just outside a city gate being become annual overhaul 10kV I section, situation is as shown in table 1.From table 1 can draw each 10kV at interval test period need about 1 hour 30 minutes approximately, it is to be used in the carrying of repeated in experiments equipment and the wiring dismounting that the time was wherein arranged about 30 minutes, the labour intensity height, efficient is restricted, and is unfavorable for the person, device security.The utility model can reduce test setup time and test period.If promote the use of, with pressure that significantly alleviates the reaying protection test personnel and work capacity, to carrying out playing a positive role smoothly of equipment rebuilding on a large scale.
The content of utility model
The purpose of the utility model is to provide a kind of substation maintenance reaying protection test dolly; Solve in maintenance process problems such as the many and carrying inconvenience of relaying instrument, wiring dismounting effectively; Have the repair quality of raising and efficient, help the characteristics of the field man person, device security.
For achieving the above object, the technical scheme of the utility model is:
A kind of substation maintenance reaying protection test dolly comprises lower floor's base plate and upper strata base plate; Lower floor's base plate links to each other with the upper strata base plate through strut bar; Push rod and pulley are installed on lower floor's base plate.
2 first guardrails and 2 second guardrails are installed on the described lower floor base plate; And first guardrail and second guardrail are intervally arranged and weld and surround one.
On the base plate of described upper strata first baffle plate and second baffle are housed; And first baffle plate and second baffle are intervally arranged and weld and surround one.
2 first guardrails and 2 second guardrails are installed on the described lower floor base plate; And first guardrail and second guardrail are intervally arranged and weld and surround one; On the base plate of described upper strata first baffle plate and second baffle are housed; And first baffle plate and second baffle are intervally arranged and weld and surround one.
The beneficial effect of the utility model is: through making reaying protection test more convenient behind a kind of substation maintenance reaying protection test dolly that uses the utility model to provide; Improved the ageing of substation's maintenance; Solve in maintenance process problems such as the many and carrying inconvenience of relaying instrument, wiring dismounting effectively, the fixation of being convenient to equipment and instrument is put surely, is convenient to certainly and safeguards; Be convenient to standardization; Make things convenient for the service personnel operation, thereby improve repair quality and efficient, help the field man person, device security.
Description of drawings
Fig. 1 is the front view of the utility model;
Fig. 2 is the lateral plan of the utility model.
The specific embodiment
Below in conjunction with accompanying drawing a nearly step being done in the enforcement of the utility model describes in detail.
Embodiment 1
Like Fig. 1, shown in Figure 2, a kind of substation maintenance reaying protection test dolly of present embodiment comprises lower floor's base plate 1 and upper strata base plate 2; Lower floor's base plate 1 links to each other with upper strata base plate 2 through strut bar 7; Push rod 6 and pulley 5 are installed on lower floor's base plate 1.2 first guardrails 3 and 2 second guardrails 8 are installed on the described lower floor base plate 1; And first guardrail 3 and second guardrail 8 are intervally arranged and weld and surround one.Lower floor's base plate 1, upper strata base plate 2, first guardrail 3, push rod 6, strut bar 7, second guardrail, 8 material therefors are aluminum alloy; Pulley 5 material therefors are plastic cement.
This car divides two-layer up and down, and check apparatus, table meter are placed in the upper strata; Power supply, check apparatus for use and Work tool are placed by lower floor.Its function has:
1, is convenient to the carrying of reaying protection test equipment;
2, be convenient to the carrying out of reaying protection test, shorten test period;
3, the fixation of being convenient to equipment and instrument is put surely, keeping and safeguarding;
4, satisfy the requirement of test aspect safety and reliability.
By 6 electrical separations of 10kV I section is example, compare with adopting traditional mode, and test setup time minimizing 1 hour 34 minutes, test period reduces 1 hour 15 minutes, amounts to 2 hours 49 minutes.If promote the use of, with pressure that significantly alleviates the reaying protection test personnel and work capacity, to carrying out playing a positive role smoothly of equipment rebuilding on a large scale.
The substation of present embodiment maintenance reaying protection test dolly solves in maintenance process problems such as the many and carrying inconvenience of relaying instrument, wiring dismounting effectively; Have the repair quality of raising and efficient, help the characteristics of the field man person, device security.
Embodiment 2
Like Fig. 1, shown in Figure 2, a kind of substation maintenance reaying protection test dolly of present embodiment comprises lower floor's base plate 1 and upper strata base plate 2; Lower floor's base plate 1 links to each other with upper strata base plate 2 through strut bar 7; Push rod 6 and pulley 5 are installed on lower floor's base plate 1.2 first baffle plates 4 and 2 second baffles 9 are housed on the described upper strata base plate 2; And first baffle plate 4 is intervally arranged and welds with second baffle 9 and surrounds one.Lower floor's base plate 1, upper strata base plate 2, first baffle plate 4, push rod 6, strut bar 7, second baffle 9 material therefors are aluminum alloy; Pulley 5 material therefors are plastic cement.
This car divides two-layer up and down, and check apparatus, table meter are placed in the upper strata; Power supply, check apparatus for use and Work tool are placed by lower floor.Its function has:
1, is convenient to the carrying of reaying protection test equipment;
2, be convenient to the carrying out of reaying protection test, shorten test period;
3, the fixation of being convenient to equipment and instrument is put surely, keeping and safeguarding;
4, satisfy the requirement of test aspect safety and reliability.
By 6 electrical separations of 10kV I section is example, compare with adopting traditional mode, and test setup time minimizing 1 hour 34 minutes, test period reduces 1 hour 15 minutes, amounts to 2 hours 49 minutes.If promote the use of, with pressure that significantly alleviates the reaying protection test personnel and work capacity, to carrying out playing a positive role smoothly of equipment rebuilding on a large scale.
The substation of present embodiment maintenance reaying protection test dolly solves in maintenance process problems such as the many and carrying inconvenience of relaying instrument, wiring dismounting effectively; Have the repair quality of raising and efficient, help the characteristics of the field man person, device security.
Embodiment 3
Like Fig. 1, shown in Figure 2, a kind of substation maintenance reaying protection test dolly of present embodiment comprises lower floor's base plate 1 and upper strata base plate 2; Lower floor's base plate 1 links to each other with upper strata base plate 2 through strut bar 7; Push rod 6 and pulley 5 are installed on lower floor's base plate 1.2 first guardrails 3 and 2 second guardrails 8 are installed on the described lower floor base plate 1; And first guardrail 3 and second guardrail 8 are intervally arranged and weld and surround one.2 first baffle plates 4 and 2 second baffles 9 are housed on the described upper strata base plate 2; And first baffle plate 4 is intervally arranged and welds with second baffle 9 and surrounds one.Lower floor's base plate 1, upper strata base plate 2, first guardrail 3, first baffle plate 4, push rod 6, strut bar 7, second guardrail 8, second baffle 9 material therefors are aluminum alloy; Pulley 5 material therefors are plastic cement.
This car divides two-layer up and down, and check apparatus, table meter are placed in the upper strata; Power supply, check apparatus for use and Work tool are placed by lower floor.Its function has:
1, is convenient to the carrying of reaying protection test equipment;
2, be convenient to the carrying out of reaying protection test, shorten test period;
3, the fixation of being convenient to equipment and instrument is put surely, keeping and safeguarding;
4, satisfy the requirement of test aspect safety and reliability.
By 6 electrical separations of 10kV I section is example, compare with adopting traditional mode, and test setup time minimizing 1 hour 34 minutes, test period reduces 1 hour 15 minutes, amounts to 2 hours 49 minutes.If promote the use of, with pressure that significantly alleviates the reaying protection test personnel and work capacity, to carrying out playing a positive role smoothly of equipment rebuilding on a large scale.
The substation of present embodiment maintenance reaying protection test dolly solves in maintenance process problems such as the many and carrying inconvenience of relaying instrument, wiring dismounting effectively; Have the repair quality of raising and efficient, help the characteristics of the field man person, device security.
Figure DEST_PATH_IMAGE002

Claims (4)

1. substation's maintenance reaying protection test dolly is characterized in that: comprise lower floor's base plate (1) and upper strata base plate (2); Lower floor's base plate (1) links to each other with upper strata base plate (2) through strut bar (7); Push rod (6) and pulley (5) are installed on lower floor's base plate (1).
2. a kind of substation according to claim 1 maintenance reaying protection test dolly is characterized in that: 2 first guardrails (3) and 2 second guardrails (8) are installed on the described lower floor base plate (1); And first guardrail (3) and second guardrail (8) are intervally arranged and weld and surround one.
3. a kind of substation according to claim 1 maintenance reaying protection test dolly is characterized in that: 2 first baffle plates (4) and 2 second baffles (9) are housed on the described upper strata base plate (2); And first baffle plate (4) and second baffle (9) are intervally arranged and weld and surround one.
4. a kind of substation according to claim 1 maintenance reaying protection test dolly is characterized in that: 2 first guardrails (3) and 2 second guardrails (8) are installed on the described lower floor base plate (1); And first guardrail (3) and second guardrail (8) are intervally arranged and weld and surround one; 2 first baffle plates (4) and 2 second baffles (9) are housed on the described upper strata base plate (2); And first baffle plate (4) and second baffle (9) are intervally arranged and weld and surround one.
CN2011205041584U 2011-12-07 2011-12-07 Relay protection test trolley for maintenance of power substation Expired - Lifetime CN202358139U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011205041584U CN202358139U (en) 2011-12-07 2011-12-07 Relay protection test trolley for maintenance of power substation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011205041584U CN202358139U (en) 2011-12-07 2011-12-07 Relay protection test trolley for maintenance of power substation

Publications (1)

Publication Number Publication Date
CN202358139U true CN202358139U (en) 2012-08-01

Family

ID=46569349

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011205041584U Expired - Lifetime CN202358139U (en) 2011-12-07 2011-12-07 Relay protection test trolley for maintenance of power substation

Country Status (1)

Country Link
CN (1) CN202358139U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102514603A (en) * 2011-12-07 2012-06-27 诸暨市供电局 Relay protection test buggy for transformer station overhaul
CN109017894A (en) * 2018-07-19 2018-12-18 广东电网有限责任公司 A kind of electric power safety rail cart

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102514603A (en) * 2011-12-07 2012-06-27 诸暨市供电局 Relay protection test buggy for transformer station overhaul
CN109017894A (en) * 2018-07-19 2018-12-18 广东电网有限责任公司 A kind of electric power safety rail cart
CN109017894B (en) * 2018-07-19 2024-04-12 广东电网有限责任公司 Electric power security fence shallow

Similar Documents

Publication Publication Date Title
CN202358139U (en) Relay protection test trolley for maintenance of power substation
CN202041412U (en) Compaction device for bituminous mixture
CN102514603A (en) Relay protection test buggy for transformer station overhaul
CN203232058U (en) Lightning arrester test frame
CN204190233U (en) A kind of low pressure rod-type power distribution cabinet operating platform
CN206592069U (en) A kind of electric power first-aid ladder
CN204241323U (en) Insulation ropes test unit
CN205973693U (en) Transformer substation removes work platform
CN203277667U (en) Grounding wire grounding body for high and low voltage line maintenance operation
CN201893509U (en) Portable overhead hoisting device special for transformer substation
CN205189502U (en) Rail for electric overhaul equipment
CN203977994U (en) Safety warning shielding
CN204485134U (en) A kind of portable secured band bracing or strutting arrangement
CN102684089A (en) Transformer overhauling platform
CN202601748U (en) Storage battery anti-theft steel bridge of base station and machine room
CN202961726U (en) Lift type 360-degee rotary simple live-working insulating platform
CN102887445A (en) Hinge fixing structure of tower crane inside-climbing steel beam
CN202275966U (en) 10kv-capacitor electric discharge device
CN205243207U (en) Mistake tool to lock protection casing is prevented to removable formula
CN202633793U (en) Transformer maintenance platform
CN205231576U (en) Half high -rise overall arrangement isolator's of dismouting auxiliary device
CN205537900U (en) Road bridge overload monitoring devices
CN204818684U (en) Auxiliary assembly is installed fast to portable gate -type safety inspection machine
CN103048127B (en) Ground tackle static load anchoring performance experimental safe protective housing
CN205693212U (en) A kind of maintaining high-voltage isolation switch dividing plate

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Effective date: 20130104

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130104

Address after: 311800 Zhejiang city of Shaoxing province Zhuji city streets Jiyang Huansha Road No. 1

Patentee after: Zhuji Power Supply Bureau

Patentee after: State Grid Corporation of China

Address before: 311800 Zhejiang city of Shaoxing province Zhuji Huansha Road No. 1

Patentee before: Zhuji Power Supply Bureau

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120801