CN202323929U CN2011204706754U CN201120470675U CN202323929U CN 202323929 U CN202323929 U CN 202323929U CN 2011204706754 U CN2011204706754 U CN 2011204706754U CN 201120470675 U CN201120470675 U CN 201120470675U CN 202323929 U CN202323929 U CN 202323929U
Authority
CN
China
Prior art keywords
steel sheet
sheet pile
fore shaft
lock catch
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011204706754U
Other languages
Chinese (zh)
Inventor
方磊
李仁民
付裕
龚文宗
李春苗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Original Assignee
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University filed Critical Southeast University
Priority to CN2011204706754U priority Critical patent/CN202323929U/en
Application granted granted Critical
Publication of CN202323929U publication Critical patent/CN202323929U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Revetment (AREA)

Abstract

The utility model discloses a steel plate pile fore shaft structure which belongs to the technical field of the building engineering. A lock catch structure disclosed by the utility model comprises a male lock catch and a female lock catch which are mutually buckled, wherein an end part on the male lock catch, which is near the female lock catch, is connected with a round pipe used for grouting, and one end of the round pipe is sealed. The steel plate pile fore shaft structure has the advantages of simple structure and good waterstop effect, the problem that a water-proof material is difficult to fill can be favorably solved, and the construction quality is guaranteed.

Description

A kind of steel sheet pile locking notch structure
Technical field
The utility model relates to the locking notch structure of steel sheet pile, belongs to the technical field of construction work.
Background technology
Steel sheet pile often is used to building foundation pit, tunnel, side slope, dock, harbour, river levee, and field such as bridge pier cofferdam.Because steel sheet pile is green, rapid construction, steel sheet pile is used for protection such as cofferdam more, engineering blocks water.Therefore, in this case, waterproof becomes higher requirement.In the middle of existing steel sheet pile waterproof measure, mainly contain following several kinds of forms:
1, filled and process agent, cost is higher.
2, paste the magnetic sealing rod.This type construction rapidly, and is easy to operate, but expense is higher.
3, smear pitch, play waterproof action.This type operation is that one deck pitch is respectively brushed in both sides in the steel sheet pile fore shaft, and its surface can not done soon, needs nature, slowly solidifies.
4, the filling film plays waterproof action.
5, the way that the steel sheet pile leak stopping is general is with fillers such as cotton-wool, butter filling seam in steel sheet pile injection process.
More than several kinds of waterproof measures or expense is very high, or waterproof effect is not ideal, perhaps construction is inconvenient.Particularly when steel sheet pile does not have free face, can't accomplish choke material especially at steel sheet pile fore shaft place.Present steel sheet pile mainly is to solve through smearing waterproofing materials in order to overcome the problem of sealing, but the waterproofing materials of in the piling process, smearing is very easily owing to the friction between pile body or stake soil comes off the waterproof effect reduction.And the good waterproof of adhesion property is smeared material, and like polyurethane, magnetic sealing rod etc., its price is very expensive again.Therefore, present steel sheet pile sealing is mostly in piling, the materials such as filling cotton-wool, butter toward the fore shaft place.All can there be certain influence in this to safety of construction quality and technician etc.
Summary of the invention
The utility model purpose provides a kind of simple in structure, and stagnant water effect is good, can be good at solving waterproofing materials and fills difficult problem, guarantees the steel sheet pile locking notch structure of construction quality.
A kind of steel sheet pile locking notch structure, said locking notch structure are pin thread, the box of mutual snapping, and the end near box on the pin thread connects the pipe that is used for slip casting, the end sealing of pipe.
Arrange several circular holes on the sidewall of the utility model pipe.
Distance between the utility model circular hole is 0.5m.
The utility model adopts technique scheme, compared with prior art has following advantage: the utility model can effectively solve the problem that the waterproofing materials that when the steel sheet pile waterproof, runs into is filled difficulty.In general, steel sheet pile will reach good waterproof effect, just should carry out particular processing at the fore shaft place.The utility model straight forming pours into waterproofing materials toward pipe the inside again after piling finishes.The range of choice of the waterproofing materials of this moment wants much extensive, can select some expansion characters good and the less demanding product of adhesiveness needn't be worried the problem that material comes off in the piling process.In addition, the perfusion waterproofing materials carries out after piling finishes, and in the safety that has guaranteed operating personnel, has also guaranteed the quality and the efficient of piling to a certain extent.For nonvolatil steel sheet pile construction, then can carry out slip casting at the fore shaft place, reach the purpose of " forever " sealing.
Description of drawings
Fig. 1 is a kind of structural representation of the utility model.
The specific embodiment
Be elaborated below in conjunction with the technical scheme of accompanying drawing to the utility model:
As shown in Figure 1, a kind of steel sheet pile locking notch structure, said locking notch structure are pin thread 1, the box 2 of mutual snapping, and the end near box 2 on the pin thread 1 connects the pipe 3 that is used for slip casting, the end sealing of pipe 3.
Arrange several circular holes on the pipe 3 of the utility model.
Distance between the circular hole of the utility model is 0.5m.
Cleared up the steel sheet pile surface before the utility model construction, steel sheet pile is tested and proofreaied and correct.The place coats sliding agent at the steel sheet pile fore shaft, the convenient connection.To the different model steel sheet pile, adopt the mode of singles or two doubles, steel sheet pile is squeezed into.Stake is poured into waterproofing materials, perhaps slip casting after squeezing into and finishing in pipe.Treat that perfusion reaches when necessarily requiring, piling finishes.When secondary uses, after steel sheet pile extracted, can the bottom of pipe be cut, clean steel stake surface and fore shaft carry out the check and the correction of steel sheet pile again.

Claims (3)

1. a steel sheet pile locking notch structure is characterized in that said locking notch structure is pin thread (1), the box (2) of mutual snapping, and the end that pin thread (1) is gone up near box (2) connects the pipe (3) that is used for slip casting, the end sealing of pipe (3).
2. steel sheet pile locking notch structure according to claim 1 is characterized in that arranging on the sidewall of above-mentioned pipe (3) several circular holes.
3. steel sheet pile locking notch structure according to claim 2 is characterized in that the distance between the above-mentioned circular hole is 0.5m.
CN2011204706754U 2011-11-24 2011-11-24 Steel plate pile fore shaft structure Expired - Fee Related CN202323929U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011204706754U CN202323929U (en) 2011-11-24 2011-11-24 Steel plate pile fore shaft structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011204706754U CN202323929U (en) 2011-11-24 2011-11-24 Steel plate pile fore shaft structure

Publications (1)

Publication Number Publication Date
CN202323929U true CN202323929U (en) 2012-07-11

Family

ID=46435912

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011204706754U Expired - Fee Related CN202323929U (en) 2011-11-24 2011-11-24 Steel plate pile fore shaft structure

Country Status (1)

Country Link
CN (1) CN202323929U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535439A (en) * 2011-11-24 2012-07-04 东南大学 Steel sheet pile joint structure
CN105603965A (en) * 2016-02-29 2016-05-25 上海市水利工程设计研究院有限公司 Sheet pile with tenon disengagement preventing structure and pile planting process thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535439A (en) * 2011-11-24 2012-07-04 东南大学 Steel sheet pile joint structure
CN105603965A (en) * 2016-02-29 2016-05-25 上海市水利工程设计研究院有限公司 Sheet pile with tenon disengagement preventing structure and pile planting process thereof

Similar Documents

Publication Publication Date Title
CN102535439A (en) Steel sheet pile joint structure
US8974152B2 (en) Polymer grouting method for constructing vertical supporting system
CN203821847U (en) Sealing element and sealing structure for building template
CN101705667A (en) Anti-freezing water stop structure of hydraulic concrete expansion joint
CN202323929U (en) Steel plate pile fore shaft structure
CN110453650B (en) Aqueduct water stop structure and construction method thereof
CN107345406A (en) A kind of method for the sealing of piping lane waterproofing of movement joints
CN213389995U (en) Cast-in-place concrete core wall and gravity dam connection structure
CN106256965A (en) A kind of sheet pile for seepage control connects snap close
CN208517891U (en) The novel reinforced structure of gravity type quay
CN109356102B (en) Asphalt concrete core wall and dam foundation impervious wall connecting structure
CN203684206U (en) Leakage-proof steel sheet pile
CN115613633A (en) Novel steel plate water stop and using method
CN202830881U (en) Anti-seepage structure for joint of earth-rock dam and other buildings
CN205206055U (en) Basement outer wall post -cast strip thickening anti -seepage waterstop structure
CN113445470A (en) Water seepage blocking structure for settlement joint of flood wall and construction process
CN207452923U (en) Gather the seepage prevention of cofferdam structure of cut-pff wall and composite geo-membrane
CN211395769U (en) Sewage treatment pond cell body movement joint stagnant water structure
CN204199324U (en) Connecting reinforcement cage i iron in construction of diaphragm wall
CN205776158U (en) A kind of sheet pile for seepage control connects snap close
CN202202334U (en) Seepage-proofing curtain arranged in engineering major structure
CN211421150U (en) Connection structure of earth-rock cofferdam prevention of seepage geomembrane and concrete cofferdam
CN215367071U (en) Flood prevention wall subsiding crack infiltration blocks up structure
CN113700051B (en) Anti-floating pressure relief hole plugging structure for underground building and construction method thereof
CN218757621U (en) Novel steel plate water stop

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120711

Termination date: 20141124

EXPY Termination of patent right or utility model