CN202249735U - Full-sleeve full-rotation drilling machine - Google Patents

Full-sleeve full-rotation drilling machine Download PDF

Info

Publication number
CN202249735U
CN202249735U CN2011202737298U CN201120273729U CN202249735U CN 202249735 U CN202249735 U CN 202249735U CN 2011202737298 U CN2011202737298 U CN 2011202737298U CN 201120273729 U CN201120273729 U CN 201120273729U CN 202249735 U CN202249735 U CN 202249735U
Authority
CN
China
Prior art keywords
pipe
oil cylinder
sleeve pipe
guide
sleeve
Prior art date
Application number
CN2011202737298U
Other languages
Chinese (zh)
Inventor
陈卫
魏垂勇
陈小青
谢丁咚
刘学军
王忠态
王户生
Original Assignee
徐州鑫景泰重工机械制造有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
Application filed by 徐州鑫景泰重工机械制造有限公司 filed Critical 徐州鑫景泰重工机械制造有限公司
Priority to CN2011202737298U priority Critical patent/CN202249735U/en
Application granted granted Critical
Publication of CN202249735U publication Critical patent/CN202249735U/en
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=46110994&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN202249735(U) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.

Links

Abstract

The utility model discloses a full-sleeve full-rotation drilling machine, relating to engineering machinery; the full-sleeve full-rotation drilling machine comprises three parts, namely a power station, a working device and an auxiliary driller; the power station is externally arranged; the working device comprises a base, a power support platform, an upright post, a lift platform and a sleeve clamping device; a support oil cylinder for levelling is arranged in the base; a drawing oil cylinder, a hydraulic motor, a gearbox, a clamping oil cylinder and a gear transmission device are main devices for transferring power to sleeves, so that the sleeves are driven to rotate, raise and lower; and the auxiliary driller comprises various standards of sleeves, grab buckets, multi-head grab buckets and the like. The full-sleeve full-rotation drilling machine has four main actions of levelling, clamping, rotating and press-extracting. A plurality of hydraulic pumps are driven by an engine in the power station. The hydraulic pumps are connected to the working device through a hydraulic soft pipe, so that power is transferred to a corresponding execution mechanism.

Description

A complete set of pipe full circle swinging rig

Technical field

The utility model relates to a kind of engineering machinery, is specifically related to a kind of a complete set of pipe full circle swinging rotary drilling rig.

Background technology

Along with the continuous quickening of China's infrastructure, the construction under various complicated geological environments such as plateau, mountain area, hills, seabeach, rivers,lakes and seas beach is more and more, often runs into the underground drift sand that has during site operation, various complicated geological situations such as solution cavity, rock stratum.The traditional crawler-type excavator, drilling rod separates with sleeve pipe, and sleeve pipe is short, is the effect that can only play local retaining wall, and the landslide problem can't be avoided, and influences workmanship.Crawler-mounted excavator is poor to neutrality, and verticality is difficult to guarantee.

Summary of the invention

In order to solve the problems of the technologies described above, the utility model provides a kind of a complete set of pipe full circle swinging rig, and fixing chassis that can the adjusting level is arranged; Drilling tool is installed on the sleeve pipe, realizes a complete set of pipe full circle swinging function, adopts Hydraulic Elements to drive; Boring, feeding, a stake drawing and clamping force all are higher than crawler-mounted excavator far away, can be used for drift sand, solution cavity, rock stratum; Construction under the various complicated geological situations such as old stake can not only guarantee that the quick and stable of constructing carries out, and guarantees high vertical precision simultaneously.

The utility model is realized with following technical scheme: a kind of a complete set of pipe full circle swinging rig, it is characterized in that: it comprises: the gear drive of base, dynamically supported platform, lift platform, column, sleeve pipe clamping device, sleeve pipe drawing oil cylinder, hydraulic motor, gearbox and drive sleeve rotation.Described base is the steel work rectangular frame, and the lower end of base is provided with supporting leg.Described column is four round tubes, and four columns are vertically fixed on four jiaos of base.Described dynamically supported platform is the steel work rectangular frame, fixing four guide pipe I on the dynamically supported platform, and guide pipe I sliding fit is inserted on the column, and the guide pipe I is connected with column through sleeve pipe drawing oil cylinder; Described lift platform is the steel work rectangular frame, fixing four guide pipe II on the lift platform, and guide pipe II sliding fit is inserted on the guide pipe I, and lift platform is connected with the dynamically supported platform through clamping cylinder.Described hydraulic motor and gearbox are four groups, and four groups of hydraulic motors and gearbox are installed on the dynamically supported platform, and gearbox is connected with sleeve pipe with the sleeve pipe clamping device through gear drive.Described sleeve pipe clamping device, be installed on the lift platform through last pivoting support.

Described gear drive comprises: transmission case body, pinion, gear wheel and bull gear.Described transmission case body is four, and four transmission case bodies are uniformly distributed with and are installed on the dynamically supported platform.The output shaft of gearbox is connected with bull gear with gear wheel through pinion.Described bull gear is installed on the dynamically supported platform through the turning down supporting, and bull gear is connected with sleeve pipe through the sleeve pipe clamping device.

Described supporting leg is installed on the piston rod of support oil cylinder, and described support oil cylinder is installed in the bottom of column pore, and the cylinder body of support oil cylinder is fixed on the base.

Described sleeve pipe drawing oil cylinder is installed in the top of column pore, and the cylinder body of sleeve pipe drawing oil cylinder is fixed on the upper end of guide pipe I, sleeve pipe drawing oil cylinder, piston rod be fixed on the hole wall of column through terminal pad.

On the described guide pipe I hole wall guide ring I is set, the guide ring I is installed in the bottom of guide pipe I through guide ring gland I.

On the described guide pipe II hole wall guide ring II is set, the guide ring II is installed in the end under the guide ring II through guide ring gland II.

The beneficial effect of the utility model is:

1, sleeve pipe good rigidly, plays that stake drawing output torque is big, noise is low, can be used for drift sand, solution cavity, rock stratum, the construction under the various complicated geological situations such as old stake at boring, feeding.

2, frame is made up of base, dynamically supported platform and lift platform three parts, can be fast, steadily, the big degree of depth, high-quality construction.

3, base is regulated level by hydraulic leg, and is good to neutrality.All right rat holing, widely applicable.

4, rational in infrastructure, guiding, rotation, lubricated good, long service life.

Description of drawings

Below in conjunction with the accompanying drawing and the specific embodiment the utility model is done further explain

Fig. 1 is the utility model structural representation.

Fig. 2 is the vertical view of Fig. 1.

Among the figure: 1, supporting leg, 2, base, 3, support oil cylinder, 4, flange, 5, guide ring gland I, 6, the guide ring I; 7, dynamically supported platform, 8, column, 9, terminal pad, 10, the guide pipe I, 11, sleeve pipe drawing oil cylinder, 12, gearbox; 13, hydraulic motor, 14, guide ring gland II, 15, the guide ring II, 16, the guide pipe II, 17, lift platform; 18, clamping cylinder, 19, go up pivoting support, 20, the sleeve pipe clamping device, 21, gear drive, the 21-1 transmission case body; 21-2, pinion, 21-3, gear wheel, 21-4, bull gear, 22, go up pivoting support down, 23, sleeve pipe.

The specific embodiment

Like Fig. 1, shown in 2: a kind of a complete set of pipe full circle swinging rig, it is characterized in that: it comprises: the gear drive 21 of base 2, dynamically supported platform 7, lift platform 17, column 8, sleeve pipe clamping device 20, sleeve pipe drawing oil cylinder 11, hydraulic motor 13, gearbox 12 and drive sleeve 23 rotations.Described base 2 is the steel work rectangular frame, and the lower end of base 2 is provided with supporting leg 1.Described column 8 is four round tubes, and four columns 8 are vertically fixed on four jiaos of base 2.Described dynamically supported platform 7 is the steel work rectangular frame, fixing four guide pipe I 10 on the dynamically supported platform 7, and guide pipe I 10 sliding fits are inserted on the column 8, and guide pipe I 10 is connected with column 8 through sleeve pipe drawing oil cylinder 11.Described lift platform 17 is the steel work rectangular frame, fixing four guide pipe II 16 on the lift platform 17, and guide pipe II 16 sliding fits are inserted on the guide pipe I 10, and lift platform 17 is connected with dynamically supported platform 7 through clamping cylinder 18.Described hydraulic motor 13 is four groups with gearbox 12, and four groups of hydraulic motors 13 are installed on the dynamically supported platform 7 with gearbox 12, and gearbox 12 is connected with sleeve pipe 23 with sleeve pipe clamping device 20 through gear drive 21.Described sleeve pipe clamping device 20 is installed on the lift platform 17 through last pivoting support 19.

Described gear drive 21 comprises: transmission case body 21-1, pinion 21-2, gear wheel 21-3 and bull gear 21-4.Described transmission case body 21-1 is four, and four transmission case body 21-1 are uniformly distributed with and are installed on the dynamically supported platform 7.The output shaft of gearbox 12 is connected with bull gear 21-4 with gear wheel 21-3 through pinion 21-2.Described bull gear 21-4 is installed on the dynamically supported platform 7 through turning down supporting 22, and bull gear 21-4 is connected with sleeve pipe 23 through sleeve pipe clamping device 20.

Described supporting leg 1 is installed on the piston rod of support oil cylinder 3, and described support oil cylinder 3 is installed in the bottom of column 8 pores, and the cylinder body of support oil cylinder 3 is fixed on the base 2.

Described sleeve pipe drawing oil cylinder 11 is installed in the top of column 8 pores, and the cylinder body of sleeve pipe drawing oil cylinder 11 is fixed on the upper end of guide pipe I 10, and the piston rod of sleeve pipe drawing oil cylinder 11 is fixed on the hole wall of column 8 through terminal pad 9.

On described guide pipe I 10 hole walls guide ring I 6 is set, guide ring I 6 is installed in the bottom of guide pipe I 10 through guide ring gland I 5.

On described guide pipe II 16 hole walls guide ring II 15 is set, the end that guide ring II 15 is installed under the guide ring II 15 through guide ring gland II 14.

The main effect of guide ring I 6 and guide ring II 15 plays guiding and does, and makes guide pipe I 10,16 motions of guide pipe II steadily.Guide ring I 6 adopts engineering plastics to make with guide ring II 1, and abrasion resistance is good.Be convenient to change as consumable accessory, improve the application life of column 8 guide ring I 6 and guide ring II.

Like Fig. 1, shown in 2: the power station that this machine uses separates with this machine, and the some hydraulic pumps of motor driven are connected on the equipment through hydraulic hose, with transmission of power corresponding executing agency to the equipment.Operating desk can remote control, also can on lift platform, operate.

Like Fig. 1, shown in 2: during use; Balance through the support oil cylinder 3 leveling bases 2 in the base 2; Sleeve pipe clamping device 20 is controlled stepping up of sleeve pipes 23 and is unclamped, and four hydraulic motors 13 drive sleeve pipes 23 rotations through gearboxes 12 and sleeve pipe clamping device 20 on the equipment, cut boring.The rising of sleeve pipe drawing oil cylinder 11 control sleeve pipes 23 or the action of decline.

Sleeve pipe 23 is put into equipment, and operating sleeve pipe clamping device 20 gripping sleeves 23 can turn round cutting, utilize sleeve pipe drawing oil cylinder 11 to apply the required power of being pressed into simultaneously.After being pressed into a stroke, unclamp sleeve pipe clamping device 20, promote dynamically supported platform 7, accomplish an actuation cycle, so back and forth.In this process, utilize auxiliary drilling tool to remove cutting objects such as the interior earth of sleeve pipe, rock simultaneously.Work utilizes clamping device that sleeve pipe 23 is extracted after accomplishing equally.This rig since output torque big, noise is low, sleeve pipe good rigidly, clamping and diameter changing device is convenient and reliable, to characteristics such as neutrality are good; At drift sand; Solution cavity, rock stratum; Under the various complicated geological situations such as old stake, can be fast, the big degree of depth, high-quality construction, be a kind of rising construction equipment.

Claims (6)

1. a complete set is managed the full circle swinging rig, and it is characterized in that: it comprises: the gear drive (21) of base (2), dynamically supported platform (7), lift platform (17), column (8), sleeve pipe clamping device (20), sleeve pipe drawing oil cylinder (11), hydraulic motor (13), gearbox (12) and drive sleeve (23) rotation; Described base (2) is the steel work rectangular frame, and the lower end of base (2) is provided with supporting leg (1); Described column (8) is four round tubes, and four columns (8) are vertically fixed on four jiaos of base (2); Described dynamically supported platform (7) is the steel work rectangular frame; Dynamically supported platform (7) is gone up fixing four guide pipe I (10); Guide pipe I (10) sliding fit is inserted on the column (8), and guide pipe I (10) is connected with column (8) through sleeve pipe drawing oil cylinder (11); Described lift platform (17) is the steel work rectangular frame; Lift platform (17) is gone up fixing four guide pipe II (16); Guide pipe II (16) sliding fit is inserted on the guide pipe I (10), and lift platform (17) is connected with dynamically supported platform (7) through clamping cylinder (18); Described hydraulic motor (13) and gearbox (12) are four groups; Four groups of hydraulic motors (13) and gearbox (12) are installed on the dynamically supported platform (7), and gearbox (12) is connected with sleeve pipe (23) with sleeve pipe clamping device (20) through gear drive (21); Described sleeve pipe clamping device (20) is installed on the lift platform (17) through last pivoting support (19).
2. a complete set of pipe full circle swinging rig according to claim 1, it is characterized in that: described gear drive (21) comprising: transmission case body (21-1), pinion (21-2), gear wheel (21-3) and bull gear (21-4); Described transmission case body (21-1) is four, and four transmission case bodies (21-1) are uniformly distributed with and are installed on the dynamically supported platform (7); The output shaft of gearbox (12) is connected with bull gear (21-4) with gear wheel (21-3) through pinion (21-2); Described bull gear (21-4) is installed on the dynamically supported platform (7) through turning down supporting (22), and bull gear (21-4) is connected with sleeve pipe (23) through sleeve pipe clamping device (20).
3. a complete set of pipe full circle swinging rig according to claim 1; It is characterized in that: described supporting leg (1) is installed on the piston rod of support oil cylinder (3); Described support oil cylinder (3) is installed in the bottom of column (8) pore, and the cylinder body of support oil cylinder (3) is fixed on the base (2).
4. a complete set of pipe full circle swinging rig according to claim 1; It is characterized in that: described sleeve pipe drawing oil cylinder (11) is installed in the top of column (8) pore; The cylinder body of sleeve pipe drawing oil cylinder (11) is fixed on the upper end of guide pipe I (10), and the piston rod of sleeve pipe drawing oil cylinder (11) is fixed on the hole wall of column (8) through terminal pad (9).
5. a complete set of pipe full circle swinging rig according to claim 1, it is characterized in that: on described guide pipe I (10) hole wall guide ring I (6) is set, guide ring I (6) is installed in the bottom of guide pipe I (10) through guide ring gland I (5).
6. a complete set of pipe full circle swinging rig according to claim 1; It is characterized in that: on described guide pipe II (16) hole wall guide ring II (15) is set, guide ring II (15) is installed in the end under the guide ring II (15) through guide ring gland II (14).
CN2011202737298U 2011-07-30 2011-07-30 Full-sleeve full-rotation drilling machine CN202249735U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202737298U CN202249735U (en) 2011-07-30 2011-07-30 Full-sleeve full-rotation drilling machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202737298U CN202249735U (en) 2011-07-30 2011-07-30 Full-sleeve full-rotation drilling machine

Publications (1)

Publication Number Publication Date
CN202249735U true CN202249735U (en) 2012-05-30

Family

ID=46110994

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202737298U CN202249735U (en) 2011-07-30 2011-07-30 Full-sleeve full-rotation drilling machine

Country Status (1)

Country Link
CN (1) CN202249735U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102287132A (en) * 2011-07-30 2011-12-21 宿迁景泰重工机械制造有限公司 Full sleeve full slewing drilling machine
CN103015918A (en) * 2012-11-23 2013-04-03 徐州盾安景泰重工机械制造有限公司 Upright post structure for operation of fully slewing drilling machine
CN103195357A (en) * 2013-04-19 2013-07-10 郑州宇通重工有限公司 Full-casing type special drilling machine
CN103206169A (en) * 2012-11-23 2013-07-17 徐州盾安重工机械制造有限公司 Rotary cone for all-casing full-rotating drilling machine
CN104213838A (en) * 2014-09-02 2014-12-17 北京市三一重机有限公司 Drive barrel and rotary drilling rig
CN104213837A (en) * 2014-09-01 2014-12-17 北京市三一重机有限公司 Drive barrel and rotary drilling rig

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102287132A (en) * 2011-07-30 2011-12-21 宿迁景泰重工机械制造有限公司 Full sleeve full slewing drilling machine
CN103015918A (en) * 2012-11-23 2013-04-03 徐州盾安景泰重工机械制造有限公司 Upright post structure for operation of fully slewing drilling machine
CN103206169A (en) * 2012-11-23 2013-07-17 徐州盾安重工机械制造有限公司 Rotary cone for all-casing full-rotating drilling machine
CN103195357A (en) * 2013-04-19 2013-07-10 郑州宇通重工有限公司 Full-casing type special drilling machine
CN104213837A (en) * 2014-09-01 2014-12-17 北京市三一重机有限公司 Drive barrel and rotary drilling rig
CN104213838A (en) * 2014-09-02 2014-12-17 北京市三一重机有限公司 Drive barrel and rotary drilling rig

Similar Documents

Publication Publication Date Title
CN104612140B (en) π shape cement earth pile wall telephone
CN101709586B (en) Double-cylinder hydraulic grooving machine
CN106761399B (en) Multifunctional drilling machine and construction method thereof
CN102803616B (en) For the method and apparatus manufacturing the underwater foundation of building
CN201786244U (en) Rotary drilling rig
CN102561946B (en) Drilling rig with following pipe pile and construction method for following pipe pile
CN102383723B (en) Seabed type conical investigating and drilling integrated machine
CN102304922B (en) Full-pile casing construction device
CN104763328A (en) Hydraulic reaming circulation drilling machine and reaming pile construction technology thereof
CN104989413B (en) Single shield TBM planes slide step device and its stepping method
CN104712339B (en) A kind of annular push-bench
CN103603342B (en) Major diameter assembled casing super-long filling pile construction method
CN204753589U (en) A static pressure stake machine complete machine is planted in reaming
CN204877481U (en) Horizontal guiding twist bit
CN201924360U (en) Multifunctional hydraulic static pile press
CN202946011U (en) Track walking deck rotation full hydraulic underground drilling rig
CN201358805Y (en) Working device of drilling jumbo
CN102852457B (en) Follow-up drilling machine for down-hole hammer casing pipe
CN103233691B (en) The supporting high inclination-angle drill stem conveying device of coal mine drilling machine
CN103758453A (en) Intelligent micro drilling machine
CN102518105A (en) Seabed static sounding penetration device
CN105840110B (en) A kind of multifunctional rotary digging machine
CN103061673A (en) Multifunctional micropile drilling machine
CN105649083A (en) All-casing one-time rotary cutting type pile removing device and pile removing method thereof
CN105178970A (en) Horizontal oriented spiral drilling machine

Legal Events

Date Code Title Description
GR01 Patent grant
C14 Grant of patent or utility model
TR01 Transfer of patent right

Effective date of registration: 20120912

Address after: 221006 Jiangsu city of Xuzhou Province era North Development Zone Quanshan District Road West Road Guoan booming Logistics Park

Patentee after: Xuzhou DunAn Jing Tai Heavy Machinery Co., Ltd.

Address before: 1-5 No. 221006 Jiangsu city of Xuzhou Province era North Development Zone Quanshan District Road

Patentee before: Xuzhou Xinjingtai Heavy Industry Machine Manufacture Co., Ltd.

ASS Succession or assignment of patent right

Owner name: XUZHOU DUN'AN JINGTAI HEAVY INDUSTRIAL MACHINERY M

Free format text: FORMER OWNER: XUZHOU XINJINGTAI HEAVY INDUSTRY MACHINERY MANUFACTURING CO., LTD.

Effective date: 20120912

C41 Transfer of patent application or patent right or utility model
CP03 Change of name, title or address

Address after: 221000, Jiangsu City, Xuzhou Province North Development Zone era avenue west prosperous road

Patentee after: Xuzhou Dun An Heavy Industry Machinery Manufacturing Co., Ltd.

Address before: 221006 Jiangsu city of Xuzhou Province era North Development Zone Quanshan District Road West Road Guoan booming Logistics Park

Patentee before: Xuzhou DunAn Jing Tai Heavy Machinery Co., Ltd.

C56 Change in the name or address of the patentee

Owner name: XUZHOU DUNAN HEAVY INDUSTRY MACHINERY MANUFACTURIN

Free format text: FORMER NAME: XUZHOU DUN'AN JINGTAI HEAVY INDUSTRIAL MACHINERY MANUFACTURING CO., LTD.

IW01 Full invalidation of patent right

Decision date of declaring invalidation: 20160727

Decision number of declaring invalidation: 29684

Granted publication date: 20120530

IW01 Full invalidation of patent right