CN202227476U - High-altitude large-span overhung corridor-type reinforced concrete structure - Google Patents
High-altitude large-span overhung corridor-type reinforced concrete structure Download PDFInfo
- Publication number
- CN202227476U CN202227476U CN2011203458244U CN201120345824U CN202227476U CN 202227476 U CN202227476 U CN 202227476U CN 2011203458244 U CN2011203458244 U CN 2011203458244U CN 201120345824 U CN201120345824 U CN 201120345824U CN 202227476 U CN202227476 U CN 202227476U
- Authority
- CN
- China
- Prior art keywords
- steel
- corridor
- floor
- formwork
- stiffness
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本实用新型涉及一种高空大跨度悬挑连廊型钢混凝土结构,连廊部位为劲性梁结构,梁模板支撑体系利用型钢自身的承载力,采用U形螺杆、螺母固定方钢方式的挂吊式模板支撑体系;楼板采用自承式钢筋桁架模板,采用拴钉焊接在劲性梁上的预埋钢板上。连廊下部相对应楼层设置钢平台作为模板支架施工的操作及安全防护平台。本实用新型有益的效果是:采用工字钢或型钢梁搭建操作平台、劲性梁干挂自承重、楼板自承重的支模施工方法,解决了高空大跨度悬挑连廊结构支模难的问题,大大节约了周转材料,降低施工成本,加快施工进度,安全得到保障。劲性梁上预埋钢板,解决了楼承板与劲性梁有效连接、使楼承板与劲性梁能共同作用,保证结构安全。
The utility model relates to a high-altitude and large-span cantilevered corridor-shaped steel concrete structure, the corridor part is a stiff beam structure, the beam formwork support system utilizes the bearing capacity of the shaped steel itself, and adopts U-shaped screw rods and nuts to fix square steel. Type formwork support system; the floor adopts self-supporting steel truss formwork, which is welded to the pre-embedded steel plate on the stiff beam by nails. Corresponding floors at the lower part of the corridor are equipped with steel platforms as operation and safety protection platforms for formwork support construction. The beneficial effect of the utility model is that the formwork support construction method of using I-beam or profiled steel beams to build the operation platform, the rigid beam dry hanging self-supporting, and the floor slab self-supporting solves the difficulty in formwork support of the high-altitude and large-span cantilevered corridor structure. The problem, greatly saving the turnover materials, reducing the construction cost, speeding up the construction progress, and ensuring safety. The pre-embedded steel plate on the stiff beam solves the problem of effective connection between the floor deck and the stiff beam, enables the floor deck and the stiff beam to work together, and ensures structural safety.
Description
技术领域 technical field
本实用新型涉及高空悬挑连廊劲性混凝土结构施工的技术领域,尤其是一种高空大跨度悬挑连廊型钢混凝土结构。The utility model relates to the technical field of high-altitude cantilevered corridor rigid concrete structure construction, in particular to a high-altitude large-span cantilevered corridor shaped steel concrete structure.
背景技术 Background technique
随着城市建设的发展,建筑师们充分发挥聪明才智,奇思妙想,相继涌现出许多造型奇特、结构复杂的建筑,为人们带来了视觉上的冲击,但也给工程师施工带来了极大的挑战。特别是公共建筑常采用高空大悬挑的手法,来满足造型的需求,例如,在两幢中几幢成排高层、超高层建筑的塔楼,设计要求在半空中通过钢筋混凝土结构各悬挑一半形成连廊使结构再次联成一个整体,利用空洞的效果,以实现环境的通透和视觉上的冲击,以立面的明暗和空间的虚实,来体现建筑师的设计意图。With the development of urban construction, architects have given full play to their ingenuity and whimsy, and many buildings with peculiar shapes and complex structures have emerged one after another, which have brought visual impact to people, but also brought great challenges to engineers' construction. Great challenge. In particular, public buildings often adopt the method of high-altitude and large cantilever to meet the needs of the shape. For example, in the towers of several high-rise and super high-rise buildings in a row, the design requires half of each to be cantilevered in mid-air through a reinforced concrete structure. The formation of corridors connects the structure into a whole again. The effect of voids is used to achieve the transparency of the environment and the visual impact. The light and shade of the facade and the virtual reality of the space reflect the architect's design intention.
然而,高空、大跨度悬挑连廊劲性混凝土结构施工,在全国类似工程不多,可参考的施工技术措施和资料很少,且稍有失误容易出现支模系统坍塌的重大安全事故和重大质量事故,如该类事故的发生,会直接影响到施工作业人员的人生安全和造成重大质量事故,使国家和企业蒙受巨大损失,同时也影响到企业的声誉。However, there are not many similar projects in the country for the construction of stiff concrete structures with high-altitude and long-span cantilevered corridors. There are few construction technical measures and materials that can be referred to, and minor mistakes are prone to major safety accidents and major accidents caused by the collapse of the formwork system. Quality accidents, such as the occurrence of such accidents, will directly affect the life safety of construction workers and cause major quality accidents, which will cause huge losses to the country and enterprises, and also affect the reputation of enterprises.
对此类结构支模的特点是:跨度大、高度高、施工荷载大、施工工艺要求高、难度大,因此为了做到技术先进、经济合理、保证质量、确保安全,对完善高空、大跨度悬挑连廊劲性混凝土结构施工方法是一个新课题,具有非常显著的现实意义。The characteristics of formwork support for this type of structure are: large span, high height, large construction load, high construction technology requirements, and high difficulty. The construction method of stiffened concrete structure for cantilevered corridor is a new topic, which has very significant practical significance.
实用新型内容 Utility model content
本实用新型的目的是利用悬挑连廊之间的两幢塔楼采用工字钢或型钢梁搭建的操作平台,进行悬挑连廊的支模及浇注钢筋混凝土,连廊的主次梁采用自承重吊挂模技术,连廊楼板采用自承式楼板进行施工,形成一种施工方法简单、操作安全、安装拆除方便、有利于文明施工的一种高空大跨度悬挑连廊型钢混凝土结构。The purpose of this utility model is to use the operation platform built by I-beams or steel beams between the two towers between the cantilevered corridors to carry out formwork support and pouring of reinforced concrete for the cantilevered corridors. Self-supporting hanging formwork technology, the corridor floor is constructed with self-supporting floor slabs, forming a high-altitude and large-span cantilevered corridor-shaped steel concrete structure with simple construction methods, safe operation, convenient installation and disassembly, and conducive to civilized construction.
本实用新型解决其技术问题采用的技术方案:这种高空大跨度悬挑连廊型钢混凝土结构,工字钢主梁安装在东、西塔楼结构下层楼面结构之间,主梁锚环预埋在下层楼面结构内,工字钢主梁吊装安装后在端部与主梁锚环固定连接;上层楼面结构预埋有斜拉杆预埋件和保险斜拉钢丝绳吊环,下层楼面结构与上层楼面结构之间设置有工字钢斜拉杆,下层楼面结构上安装有工字钢次梁,工字钢斜拉杆通过高强螺栓与连接耳板进行连接;劲性主梁、劲性次梁的U形螺杆通过方钢与双螺母固定梁底模板和内楞方木,内楞方木平行于梁轴线布置,方钢垂直行梁轴线布置;梁侧模板外侧安装内楞方木并由双钢管外楞和对拉螺杆紧固连接;在劲性主梁、劲性次梁梁顶预埋好与钢筋桁架模板焊接的劲性板,厚劲性板与劲性主梁、劲性次梁箍筋焊接连接。The technical scheme adopted by the utility model to solve its technical problems: the high-altitude and large-span cantilevered corridor-shaped steel concrete structure, the I-steel main beam is installed between the lower floor structure of the east and west tower structures, and the anchor ring of the main beam is pre-buried In the lower floor structure, the I-beam main girder is fixedly connected with the anchor ring of the main beam at the end after hoisting and installation; I-steel diagonal tie rods are installed between the upper floor structures, and I-steel secondary beams are installed on the lower floor structure. The U-shaped screw of the beam fixes the bottom formwork of the beam and the inner corrugated square wood through square steel and double nuts. The inner corrugated square wood is arranged parallel to the axis of the beam, and the square steel is arranged perpendicular to the axis of the beam; Double-steel pipe outer corrugated and tensioned connection of tensioning screws; pre-embedded stiff plates welded with steel truss formwork on the top of stiff main beams and stiff secondary beams, thick stiff plates and stiff main beams, stiff secondary beams Beam stirrup welded connection.
这种高空大跨度悬挑连廊型钢混凝土结构的施工方法,施工方法步骤如下;The construction method of this high-altitude large-span cantilevered corridor steel concrete structure, the construction method steps are as follows;
总体设计思路:连廊部位为劲性梁结构,梁模板支撑体系利用型钢自身的承载力,采用U形螺杆、螺母固定方钢方式的挂吊式模板支撑体系;楼板采用自承式钢筋桁架模板,采用拴钉焊接在劲性梁上的预埋钢板上。连廊下部相对应楼层设置钢平台作为模板支架施工的操作及安全防护平台。Overall design idea: the corridor part is a stiff beam structure, the beam formwork support system utilizes the bearing capacity of the section steel itself, and uses a hanging formwork support system in the form of U-shaped screws and nuts to fix square steel; the floor adopts a self-supporting steel truss formwork , using studs welded to the embedded steel plate on the stiff beam. Corresponding floors at the lower part of the corridor are equipped with steel platforms as operation and safety protection platforms for formwork support construction.
1根据工程结构类型、施工荷载、《建筑结构荷载规范》GB50009、《钢结构设计规范》GB50017、《混凝土结构设计规范》GB50010、《钢管扣件式脚手架规范》JGJ130、《建筑施工模板安全技术规范》JGJ162等相关规范编制施工方案,确定预埋件的埋设楼层、位置及工字负或型钢、钢丝绳的型号、规格;1 According to the type of engineering structure, construction load, "Building Structure Load Code" GB50009, "Steel Structure Design Code" GB50017, "Concrete Structure Design Code" GB50010, "Steel Tube Fastener Scaffold Specification" JGJ130, "Building Construction Formwork Safety Technical Code 》JGJ162 and other relevant specifications to prepare the construction plan, determine the embedded floor, location and type and specification of the I-shaped negative or section steel and wire rope of the embedded parts;
2操作平台工字钢主梁的安装:在确定楼层的相应位置埋设锚筋或锚环型预埋件;相应楼层楼板施工完成砼强度达到2.0MPa后,进行操作平台的工字钢主梁安装工作,遇剪力墙31时需在工字钢主梁安装部位预留好孔洞,以便后期的拆除。2 Installation of the I-beam main beam of the operation platform: bury anchor bars or anchor ring-type embedded parts at the corresponding positions of the determined floors; after the concrete strength of the corresponding floor slab construction reaches 2.0MPa, install the I-beam main beam of the operation platform Work, when encountering
a、安装施工准备a. Preparation for installation and construction
平台型钢安装工作需在相应楼层结构完成,砼强度达到2.0MPa时进行。操作平台主梁采用22a#工字钢搁置在两幢塔楼之间,两端各内锚1250mm,总长度为16m,由于生产厂家生产单根最大长度为9m,吊装前需提前做好型钢的连接工作,型钢连接螺栓选用8.8级,M20摩擦型高强螺栓。The installation of platform section steel shall be completed when the corresponding floor structure is completed and the concrete strength reaches 2.0MPa. The main girder of the operation platform is placed between the two towers with 22a# I-beam. The inner anchors at both ends are 1250mm, and the total length is 16m. Since the maximum length of a single beam produced by the manufacturer is 9m, the connection of the section steel must be done in advance before hoisting. For work, the steel connecting bolts are grade 8.8, M20 friction-type high-strength bolts.
工字钢主梁斜拉杆埋件在操作平台上一层塔楼结构浇注前必须按设计尺寸位置进行预埋。The embedded parts of the I-beam main girder oblique tie rods must be pre-embedded according to the designed size and position before pouring the tower structure of the first floor on the operation platform.
工字钢主、次梁,采用塔吊进行吊装。吊装前,根据操作平台脚手架平面布置图上尺寸进行放样符。按照规范规定对型钢、钢管、扣件、脚手片进行检查验收。I-beam primary and secondary beams are hoisted by tower cranes. Before hoisting, stake out according to the dimensions on the floor plan of the scaffolding of the operating platform. Inspection and acceptance of section steel, steel pipe, fasteners and scaffolding shall be carried out in accordance with the regulations.
b、操作平台工字钢主梁安装方法b. Installation method of I-beam main beam of operating platform
操作平台的工字钢主梁采用塔吊直接吊装,按照事先弹好的线就位。工字钢主梁吊装就位后,用木楔将工字钢与事先预埋好的Φ20压环楔紧。The I-beam main girder of the operation platform is hoisted directly by a tower crane and placed in place according to the pre-stretched line. After the I-beam main girder is hoisted in place, use a wooden wedge to wedge the I-beam and the pre-buried Φ20 pressure ring tightly.
c、主梁工字钢预控钢丝绳安装c. Installation of main girder I-beam pre-control wire rope
为防止在进行次梁及斜拉杆安装时工字钢主梁绕度过大,在工字钢主梁与操作平台上一层塔楼结构梁上预埋Φ20拉环采用6×19Φ20钢丝绳进行预控,预控钢丝绳在操作平台上一层结构强度等级达到75%,操作平台次梁、斜拉杆安装前设置到位。In order to prevent the I-beam main girder from being too large during the installation of the secondary beam and the inclined stay rod, the Φ20 pull ring is pre-embedded on the I-beam main beam and the tower structure beam on the upper floor of the operation platform, and 6×19Φ20 steel wire ropes are used for pre-control. , the pre-controlled steel wire rope is on the upper layer of the operating platform with a structural strength level of 75%, and the secondary beams and diagonal stay rods of the operating platform are set in place before installation.
3施工预埋斜拉杆预埋件,待砼强度达到设计强度75%后,进行斜拉杆、操作平台次梁的安装。3 Construction pre-embedded oblique tie rod embedded parts, after the concrete strength reaches 75% of the design strength, install the oblique tie rod and the secondary beam of the operation platform.
a、斜拉杆安装a. Diagonal tie rod installation
在两塔楼操作平台上一层结构完成砼强度达到75%预控钢丝绳安装就位后,进行斜拉杆安装。斜拉杆采用16#工字钢,工字钢主梁拉接点设置在两端3.6m部位,垂直方向在操作平台上一层塔楼结构梁、柱上预埋拉接点埋件并预埋一个钢丝绳拉环,后期次梁工字钢、斜拉杆拆除时采用钢丝绳临时拉结在主梁上,作为安全储备,形成45°夹角。为便于斜拉杆安装,在预埋件及22a#工字钢主梁上焊接短加劲板,最后采用高强螺栓将加劲板与16#工字钢拉杆进行连接。详见附图七After the concrete strength reaches 75% and the pre-controlled steel wire rope is installed in place on the first floor structure on the operation platform of the two towers, install the diagonal stay rod. The diagonal stay rods are made of 16# I-beam, and the I-beam main girder pull joints are set at 3.6m from both ends. In the vertical direction, the tie joints are pre-embedded on the structural beams and columns of the tower on the first floor of the operation platform, and a steel wire rope is pre-embedded. When the ring, secondary beam I-beam and diagonal stay rod are removed in the later period, the steel wire rope is temporarily tied to the main beam as a safety reserve, forming an included angle of 45°. In order to facilitate the installation of the diagonal tie rods, short stiffeners are welded on the embedded parts and the 22a# I-beam main beam, and finally the stiffeners are connected with the 16# I-beam tie rods with high-strength bolts. See Attachment VII for details
b斜拉杆安装步骤:b Diagonal stay rod installation steps:
第一步:主梁工字钢安装完毕后,需在斜拉杆安装范围搭设临时架体,作为斜拉杆安装时的操作平台。首先在斜拉杆跨度范围内3.6m安装上工字钢次梁并与主梁固定牢固,次梁固定好后,采用方木、胶合板在次梁上铺设上人操作平台。Step 1: After the main girder I-beam is installed, a temporary frame needs to be erected in the installation range of the diagonal stay as an operating platform for the installation of the diagonal stay. First, install the I-beam secondary beam within 3.6m of the span of the diagonal stay and fix it firmly with the main beam. After the secondary beam is fixed, use square wood and plywood to lay the operator's operating platform on the secondary beam.
第二步 斜拉杆安装:斜拉杆采用16#工字钢,塔吊进行协助安装。斜拉杆连接采用高强螺栓,先将斜拉杆吊运至墙体预埋件高度,进行与墙上预埋件的临时固定,螺母暂时不拧紧,指挥塔吊将斜拉杆缓缓放下至主梁拉接点位置,进行主梁工字钢上拉接点的连接,最后紧固螺母。The second step is to install the diagonal tie rod: the diagonal stay rod is made of 16# I-beam, and the tower crane is used to assist in the installation. The diagonal tie rods are connected with high-strength bolts. First, lift the diagonal stay rods to the height of the embedded parts on the wall, and then temporarily fix them with the embedded parts on the wall. The nuts are not tightened temporarily, and the command tower crane slowly lowers the diagonal stay rods to the main beam pull joints. position, connect the pull-up joints of the main beam I-beam, and finally tighten the nuts.
c、工字钢次梁安装c. Installation of I-beam secondary beam
次梁作为操作平台支架基础,搁置在22a#工字钢主梁之上,按1000mm间距垂直与主梁布置,安装就位后采用点焊与主梁进行固定。次梁安装固定完成后,在次梁上按立杆间距1000mm焊接2根Φ20长100mm短钢筋头,以用来防止支架立杆位移。The secondary beam is used as the support foundation of the operation platform, resting on the 22a# I-beam main beam, arranged vertically with the main beam at a distance of 1000mm, and fixed with the main beam by spot welding after installation in place. After the secondary beam is installed and fixed, weld two Φ20 short steel bar heads with a length of 100mm on the secondary beam according to the pole spacing of 1000mm to prevent the displacement of the support pole.
4操作平台以上层塔楼屋面结构、柱施工,待柱砼强度达到设计强度75%后进行连廊部位内锚段劲性梁型钢吊装、结构模板、钢筋施工、砼浇注。4 For the roof structure and column construction of the tower above the operation platform, after the concrete strength of the column reaches 75% of the design strength, the hoisting of the stiff beam section steel of the anchor section in the corridor, structural formwork, steel bar construction, and concrete pouring will be carried out.
5操作平台架体搭设。5 Erection of the operating platform frame.
搭设平台支架时,首先在以安装、固定好的次梁工字钢上采用方木、模板铺设一个临时的上人操作平台,然后开始搭设立杆,立杆套进提前焊好的短钢筋上,以防止位移,造成架体基础悬空。立杆搭设,先按4m×4m的矩形四角开始竖立杆,然后连接扫地杆、水平杆使架体稳定,在按立杆间距要求进行搭设。When setting up the platform support, firstly, a temporary master operation platform is laid with square wood and formwork on the installed and fixed secondary beam I-beam, and then the upright pole is set up, and the upright pole is inserted into the short steel bar welded in advance , in order to prevent displacement, causing the base of the frame to be suspended. To set up the pole, first erect the pole according to the four corners of the rectangle of 4m×4m, then connect the sweeping pole and the horizontal pole to make the frame stable, and then set up according to the distance between the poles.
支架搭设步距为1.800m,离地200mm设纵横双向扫地杆,沿架体四周每四跨设置斜向剪刀撑,在第二步架高度处设一道水平剪刀撑。The step distance of the support is 1.800m, and the vertical and horizontal two-way sweeping poles are set at 200mm from the ground. The oblique scissors braces are installed every four spans around the frame body, and a horizontal scissors brace is set at the height of the second step frame.
架体搭设完毕后,在支架低层、顶层满铺上脚手板,用铁丝固定牢固。After the frame body is erected, the scaffolding boards are fully spread on the lower layer and the top layer of the frame, and fixed firmly with iron wires.
剪力墙上预埋钢板,按两步两跨设置,最后与架体拉结钢管进行焊接详附图十五The pre-embedded steel plate on the shear wall is set up in two steps and two spans, and finally welded with the frame body tie steel pipe for details.
6待屋面层非连廊部位结构砼强度达到设计强度的75%后,采用塔吊进行连廊部分型钢的吊装、固定安装。6 After the structural concrete strength of the non-corridor part of the roof layer reaches 75% of the design strength, the tower crane is used to hoist and fix the section steel of the corridor.
7型钢的吊装完成、操作平台搭设完毕后,进行连廊部位劲性梁的模板、钢筋、砼施工,并在梁顶预埋好与钢筋桁架模板焊接的钢板,进行连廊部位主梁及一半截面高度的边梁砼浇筑。After the hoisting of the 7-shaped steel and the erection of the operation platform are completed, the formwork, steel bars and concrete construction of the stiff beam at the corridor will be carried out, and the steel plate welded with the steel truss formwork will be pre-embedded on the top of the beam, and the main beam and half of the corridor will be constructed. Concrete pouring of side beams at the height of the section.
a劲性梁型钢安装到位后,将制作加工的U型螺杆倒挂焊接在型钢梁上,点焊进行固定,U型螺杆设置间距应符合方案计算中的间距要求。a. After the stiffened beam profile steel is installed in place, the manufactured U-shaped screw is welded upside down on the profiled steel beam, and fixed by spot welding. The spacing between the U-shaped screws should meet the spacing requirements in the scheme calculation.
b安装梁底模板、模板采用18mm厚胶合板,配好模板后,将内楞方木钉在模板面板上,套进固定在型钢上的U形螺杆上,模板上预留孔洞需与U形螺杆位置一致,为方便安装,可用螺栓对已安装上的模板进行临时固定。b. Install the beam bottom formwork. The formwork is made of 18mm thick plywood. After the formwork is prepared, the inner corrugated square wood is nailed to the formwork panel and inserted into the U-shaped screw fixed on the section steel. The holes reserved on the formwork need to be matched with the U-shaped screw. The positions are consistent, and for the convenience of installation, bolts can be used to temporarily fix the installed formwork.
c安装梁底外楞方钢、螺母:外楞方钢上与螺杆拉结的孔洞需提前开孔完成并符合螺杆的间距要求,外楞方钢安装完成后采用螺母拧紧固定,并进行水平测量,可利用螺母进行微调。外楞方钢采用3只螺母进行固定。c Install the outer corrugated square steel and nuts at the bottom of the beam: the hole on the outer corrugated square steel and the screw rod must be opened in advance and meet the spacing requirements of the screw. , can be fine-tuned with nuts. The outer corrugated square steel is fixed with 3 nuts.
d、劲性梁钢筋、梁顶预埋钢板安装d. Installation of steel bars for stiff beams and pre-embedded steel plates on top of beams
梁钢筋安装顺序:梁纵筋连接--箍筋安装---箍筋拉钩安装。The installation sequence of beam reinforcement: beam longitudinal reinforcement connection - stirrup installation - stirrup hook installation.
梁顶预埋钢板安装:因连廊楼板采用的是自承式钢筋桁架模板,钢筋桁架模板安装时需和梁进行焊接固定,为此,在劲性梁梁顶预埋通长的钢板,作为与钢筋桁架模板焊接的母材。钢板宽同劲性梁型钢宽,厚度为10mm,钢板预埋拉结采用Φ10200的U形拉钩。Installation of pre-embedded steel plates on the top of the beam: Since the corridor floor uses a self-supporting steel truss formwork, the steel truss formwork needs to be welded and fixed to the beam during installation. Therefore, a full-length steel plate is pre-embedded on the top of the stiff beam as Base metal welded with steel truss formwork. The width of the steel plate is the same as that of the steel beam with a thickness of 10mm. The pre-embedded tie of the steel plate adopts a U-shaped hook of Φ10200.
预埋前,首先采用经纬仪确定出轴线位置,在梁箍筋上拉好通线,作为钢板预埋时的控制线然后进行预埋,预埋固定时采用水准仪对钢板板面标高进行复测。轴线位置、标高无误后,将U形拉钩与梁钢筋焊接固定。Before pre-embedding, the theodolite is used to determine the position of the axis, and the wire is drawn on the beam stirrup as the control line when the steel plate is pre-embedded, and then pre-embedded. After the axis position and elevation are correct, weld the U-shaped hook to the beam reinforcement.
e、劲性梁侧模安装e. Rigid beam side formwork installation
梁钢筋,预埋件安装结束后,进行侧模封闭,梁侧模板固定采用对拉螺杆拉结外楞钢管进行固定。After the beam reinforcement and embedded parts are installed, the side formwork shall be closed, and the beam side formwork shall be fixed with the outer corrugated steel pipes tied with the pull screw.
第一步:安装对拉螺杆,对需穿过型钢腹板的部位,需提前进行开孔,将螺栓安装固定。Step 1: Install the pull screw. For the part that needs to pass through the steel web, it is necessary to make holes in advance to install and fix the bolts.
第二步:安装梁侧模板、方木安装:配好模板后,将内楞方木钉在模板面板上,套进固定好的对拉螺杆上。Step 2: Install the beam side formwork and square wood Installation: After the formwork is prepared, nail the inner corrugated square wood on the formwork panel and put it into the fixed tension screw.
第三步:梁侧模板固定:采用扇形卡箍住双钢管外楞,用双螺母紧固。Step 3: Beam side formwork fixation: Use fan-shaped clamps to clamp the outer corrugations of the double steel pipes, and fasten them with double nuts.
8连廊部位次梁及剩余一半的边梁砼浇注8. Concrete pouring of the secondary beam and the remaining half of the side beam at the corridor
考虑到劲性主、次梁、楼板混凝土同时浇注时,劲性主梁端部挠度较大,故采用分段浇筑,先浇注主梁及边梁的一半高度,等主梁及边梁混凝土强度等级达到100%后,再进行边梁剩余高度及次梁砼浇注,等边梁及次梁混凝土强度等级达到75%后进行楼板砼浇注。Considering that the deflection of the end of the stiff main beam is relatively large when the concrete of the stiff main beam, the secondary beam, and the floor slab are poured at the same time, segmental pouring is adopted, and half the height of the main beam and side beam is poured first, so that the concrete strength of the main beam and side beam is equal After the level reaches 100%, the remaining height of the side beam and the concrete pouring of the secondary beam will be carried out, and the floor concrete will be poured after the concrete strength level of the equal side beam and secondary beam reaches 75%.
9钢筋桁架模板的施工,浇筑楼面砼。9 Construction of reinforced truss formwork, pouring floor concrete.
10拆除梁底模板。10 Remove the formwork at the bottom of the beam.
11拆除操作平台11 Remove the operating platform
a、拆除准备工作a. Preparation for demolition
拆除之前清除脚手架上的杂物,连廊底部及周边15m拉上警戒绳,禁止行人进入;由项目技术负责人进行安全拆除技术交底,并履行签字手续;拆除作业人员必须带好安全帽、安全带。Before the demolition, remove the sundries on the scaffolding, put a warning rope on the bottom of the corridor and 15m around it, and prohibit pedestrians from entering; the technical person in charge of the project will explain the technical details of the safe demolition and perform the signing procedures; the demolition operators must wear safety helmets and safety belts .
b、架体拆除b. Removal of the frame
第一步 清除架体脚手板上的垃圾、杂物,拆除安全网。The first step is to remove the garbage and sundries on the scaffolding board of the frame body, and remove the safety net.
第二步 拆除架体上的脚手板:拆除顺序从临边两侧往中间进行,留宽1.5m左右范围作为通道最后拆除。The second step is to remove the scaffolding on the frame body: the removal sequence is from both sides of the border to the middle, leaving a width of about 1.5m as the channel for final removal.
第三步 拆除斜向剪刀撑、水平剪刀撑。The third step is to remove the oblique scissors brace and horizontal scissors brace.
第四步 由上而下进行小横杆、大横杆、立杆拆除。架体拆除时,上部楼板均已封闭,拆除的钢管、扣件无法利用塔吊立即进行吊装,拆除下来的钢管、扣件,通过通道处洞口运至楼层内,严禁堆载在待拆的架体上。The fourth step is to remove the small crossbar, large crossbar and vertical pole from top to bottom. When the frame body is dismantled, the upper floor is closed, and the removed steel pipes and fasteners cannot be hoisted immediately by the tower crane. The removed steel pipes and fasteners are transported to the floor through the opening of the passage, and it is strictly forbidden to stack them on the frame body to be dismantled. superior.
c、次梁工字钢、斜拉杆拆除c. Removal of secondary beam I-beams and diagonal stays
次梁拆除前,采用方木、模板在次梁上铺设临时的上人通道。Before the demolition of the secondary beam, use square timber and formwork to lay a temporary passage on the secondary beam.
根据现场情况,拆除分为先两侧后中间进行,中间留设通道,最后进行拆除。According to the site conditions, the demolition is divided into two sides first and then the middle, leaving a passage in the middle, and finally demolishing.
操作工人必须系好安全带并保证安全带有可靠拉接点后方可进行作业,首先将跳板搁置在临时作业平台与次梁上稳固后,操作工人站在跳板上用磨光机将次梁与主梁固定焊点割开,然后将绳索栓在次梁工字钢2侧将工字钢拖至临时作业平台上,运至楼层内,再进行下段次梁的拆除,纵向的一条工字钢拆除结束,将平台向内移进一跨,按照同样的方法进行下面的次梁拆除。The operator must fasten the safety belt and ensure that the safety belt has a reliable pull point before proceeding with the operation. First, the springboard is placed on the temporary work platform and the secondary beam and after being stabilized, the operator stands on the springboard and uses a grinder to connect the secondary beam with the main beam. Cut off the fixed welding spot of the beam, then tie the rope to the side of the I-beam 2 of the secondary beam, drag the I-beam to the temporary work platform, transport it to the floor, and then remove the next section of the secondary beam, and dismantle the vertical I-beam At the end, move the platform inward into a span, and remove the secondary beam below in the same way.
临时平台移至最里侧后,按主梁跨度采取倒退式进行分段拆除,首先进行斜拉杆拆除,为确保安全,斜拉杆拆除之前必须先将6×19Φ20保险钢丝绳安装到位。斜拉杆自重较大,需分4段气割拆除。斜拉杆拆除后一边拆除脚手板,一边拆除次梁工字钢,最后将预控钢丝绳割断,便于最后的主梁工字钢拆除。After the temporary platform is moved to the innermost side, it is dismantled step by step according to the span of the main girder in a backward manner. Firstly, the diagonal tie rods are removed. To ensure safety, the 6×19Φ20 safety wire ropes must be installed in place before the diagonal stay rods are removed. The oblique tie rod has a large dead weight and needs to be dismantled by gas cutting in 4 stages. After the oblique tie rods are removed, the scaffold board is removed, and the secondary beam I-beam is removed, and finally the pre-control wire rope is cut to facilitate the final removal of the main beam I-beam.
最后进行通道部位次梁的拆除。Finally, the secondary beam at the channel part is removed.
d、操作平台主梁拆除d. Removal of the main beam of the operating platform
主梁工字钢拆除,采用:在屋面连廊中间沉降缝部位安装卷扬机,在拆除次梁工字钢时,将手动卷扬机的钢丝绳固定在主梁型钢的拉环上,然后将吊挂钢丝绳拉直后锁住卷扬机制动。待次梁工字钢、斜拉杆、钢丝绳拆除完成后,采用气焊将主梁工字钢从两边端部割断,打开卷扬机制动将主梁工字钢缓缓吊至地面上,最后运至堆放场地。To dismantle the I-beam of the main beam, adopt: install a hoist at the settlement joint in the middle of the roof corridor. Lock the winch brake straight back. After the secondary beam I-beam, diagonal stay rods, and wire ropes are removed, gas welding is used to cut off the main beam I-beam from both ends, and the winch brake is turned on to lift the main beam I-beam slowly to the ground, and finally transported to the stack site.
e、外墙上拉环拆除e. Remove the pull ring on the outer wall
外墙上的拉环利用外墙装饰时吊篮进行拆卸。The pull ring on the outer wall is disassembled by using the hanging basket when the outer wall is decorated.
本实用新型有益的效果是:The beneficial effects of the utility model are:
1、采用工字钢或型钢梁搭建操作平台、劲性梁干挂自承重、楼板自承重的支模施工方法,解决了高空大跨度悬挑连廊结构支模难的问题,大大节约了周转材料,降低施工成本,加快施工进度,安全得到保障。1. The formwork construction method of using I-beam or profiled steel beams to build the operation platform, stiff beams to hang self-supporting, and floor slabs to support the formwork solves the problem of difficult formwork support of the high-altitude and large-span cantilevered corridor structure, which greatly saves Turnover materials, reduce construction costs, speed up construction progress, and ensure safety.
2、劲性梁上预埋钢板,解决了楼承板与劲性梁有效连接、使楼承板与劲性梁能共同作用,保证结构安全。2. The pre-embedded steel plate on the stiff beam solves the problem of effective connection between the floor deck and the stiff beam, enables the floor deck and the stiff beam to work together to ensure structural safety.
3、大跨度型钢梁焊接吊环,斜拉杆安装前采用钢丝绳进行斜接,有效解决了安装过程型钢梁或工字钢梁挠度过大的问题,使操作平台安装和拆除过程安全得到了保障。3. Large-span steel girders are welded with rings, and steel wire ropes are used for mitering the diagonal stays before installation, which effectively solves the problem of excessive deflection of steel girders or I-beams during installation, and ensures the safety of the installation and removal of the operating platform .
4、对工字钢主梁采取添加加劲肋的办法,即每隔2米左右在工字钢腹板左右各焊接一根直径为20mm的钢筋,避免了吊装过程使其挠度过大影响主梁拼接焊缝质量的问题。4. Add stiffeners to the I-beam main beam, that is, weld a steel bar with a diameter of 20mm on the left and right sides of the I-beam web every 2 meters, so as to avoid the excessive deflection of the hoisting process and affect the main beam The quality of splicing welds.
5、本实用新型的支撑体系上部操作平台荷载通过钢管支架和连系梁传递到工字钢梁和斜拉杆上,传力明确,受力合理。安装拉杆方便、安全,用钢量少,经济性高,另外单一构件的重量较小,工艺简单无特殊要求,占用场地少,便于高空操作,施工工艺简单、结构可靠、稳定性强、装拆方便、实用性强。5. The load of the upper operating platform of the support system of the utility model is transmitted to the I-beam and the diagonal tie rod through the steel pipe bracket and the connecting beam, and the force transmission is clear and the force is reasonable. The installation of tie rods is convenient and safe, with less steel consumption and high economy. In addition, the weight of a single component is small, the process is simple and has no special requirements, and it occupies less space, which is convenient for high-altitude operation. The construction process is simple, the structure is reliable, the stability is strong, and the assembly and disassembly Convenient and practical.
附图说明 Description of drawings
附图1流程图;Accompanying drawing 1 flowchart;
附图2操作平台脚手架平面布置图;Attached drawing 2 is the plane layout of the scaffolding of the operation platform;
附图3操作平台脚手架剖面图;Accompanying drawing 3 is the sectional view of the scaffolding of the operation platform;
附图4屋面连廊劲性梁、自承式钢筋桁架楼板连接图;Attached drawing 4 is the connection diagram of the roof corridor stiff beam and self-supporting steel truss floor;
附图5劲性梁吊模详图;Attached drawing 5 is a detailed drawing of the suspension formwork of the stiffened beam;
附图6劲性梁吊模侧视局部放大图;Attached drawing 6 is a partial enlarged view of the side view of the stiff beam suspension formwork;
附图7操作平台斜拉杆大样图Attached drawing 7 is a large sample diagram of the inclined rod of the operation platform
附图8操作平台基础详图Accompanying drawing 8 basic detailed diagram of operation platform
附图9操作平台拆除顺序图Accompanying drawing 9 is the dismantling sequence diagram of the operating platform
附图标记说明:下层楼面结构1、上层楼面结构2、满堂脚手架操作平台3、屋面层楼面结构4、工字钢主梁5、工字钢斜拉杆6、工字钢次梁7、竖向剪刀撑8、水平剪刀撑9、满铺脚手片10、临边防护斜撑11、斜拉杆预埋件12、纵横向钢管13、上人爬梯14、隔离层15、保险斜拉钢丝绳16、保险斜拉钢丝绳吊环17、脚手架立杆18、自承式钢筋桁架模板19、劲性板20、劲性主梁21、劲性次梁22、方钢23、双钢管外楞24、梁侧模板25、对拉螺杆26、U形螺杆27、双螺母28、内楞方木29、连接耳板30、剪力墙31、连墙件32、主梁吊环33、高强螺栓34、临时上人平台35、主梁锚环36、变形缝37、梁底模板38。Explanation of reference signs: lower floor structure 1, upper floor structure 2, mansion
具体实施方式 Detailed ways
下面结合附图对本实用新型作进一步说明:Below in conjunction with accompanying drawing, the utility model is further described:
如图所示,这种高空大跨度悬挑连廊型钢混凝土结构,工字钢主梁5安装在东、西塔楼结构下层楼面结构1之间,主梁锚环36预埋在下层楼面结构1内,工字钢主梁5吊装安装后在端部与主梁锚环36固定连接;上层楼面结构2预埋有斜拉杆预埋件12和保险斜拉钢丝绳吊环17,下层楼面结构1与上层楼面结构2之间设置有工字钢斜拉杆6,下层楼面结构1上安装有工字钢次梁7,工字钢斜拉杆6通过高强螺栓34与连接耳板30进行连接;劲性主梁21、劲性次梁22的U形螺杆27通过方钢23与双螺母28固定梁底模板38和内楞方木29,内楞方木29平行于梁轴线布置,方钢23垂直行梁轴线布置;梁侧模板25外侧安装内楞方木29并由双钢管外楞24和对拉螺杆26紧固连接;在劲性主梁21、劲性次梁22梁顶预埋好与钢筋桁架模板焊接的劲性板20,厚劲性板20与劲性主梁21、劲性次梁22箍筋焊接连接。As shown in the figure, in this high-altitude and large-span cantilevered corridor-shaped steel concrete structure, the I-shaped steel
实例:以一框剪结构,主楼由东、西2幢塔楼组成,地下1层,地上24层,建筑总高度为108.700米;裙房共三层,框架结构,建筑高度16.900m。主楼从三层楼面10.950m开始分为东、西2幢独立的塔楼西区塔楼1-7轴,东区塔楼8-14轴,在屋面层91.85m标高)东西塔楼各向外悬6.725m,形成高空连廊7-8轴间。连廊底标高92.45m,顶标高108.7m的建筑为例。Example: With a frame-shear structure, the main building consists of two towers in the east and west, with one floor underground and 24 floors above ground, with a total building height of 108.700 meters; the podium has three floors, a frame structure, and a building height of 16.900 meters. The main building is divided into two independent towers in the east and west starting from 10.950m on the third floor. The towers in the west area are 1-7 axes, and the towers in the east area are 8-14 axes. The elevation of the roof layer is 91.85m). Form the 7-8 axis room of the high-altitude corridor. Take a building with a bottom elevation of 92.45m and a top elevation of 108.7m as an example.
该连廊楼板自三层楼面+10.950m至屋面层91.850m离地净高度为80.950m,各向外悬挑6.725m,形成高空连廊,连廊部位梁采用劲性梁,板采用150mm厚自承式钢筋桁架混凝土楼板。劲性主梁截面尺寸为450mm×1200mm,采用250mm×900mm型钢,劲性次梁截面为300mm×1200mm,采用150mm×400mm型钢,型钢选用Q345B钢,梁、板砼设计强度均为C30。The floor slabs of the corridor have a net height of 80.950m from the third floor +10.950m to the roof layer of 91.850m, and cantilever 6.725m outwards to form a high-altitude corridor. 150mm thick self-supporting reinforced truss concrete floor. The section size of the rigid main beam is 450mm×1200mm, using 250mm×900mm section steel, the section of the stiffened secondary beam is 300mm×1200mm, using 150mm×400mm section steel, the section steel is Q345B steel, and the design strength of beam and slab concrete is C30.
施工方法如下;The construction method is as follows;
该连廊施工步骤为:以变形缝37为界分为东西塔楼,东西塔楼分层施工至24层楼面结构2→屋面层楼面结构4劲性梁安装→塔楼、连廊搭设屋面层楼面结构4模板支架→塔楼、连廊屋面层楼面结构4钢筋、砼施工。The construction steps of the corridor are as follows: the east and west towers are divided into east and west towers by the deformation joint 37, and the east and west towers are constructed in layers up to the floor structure 2 of the 24th floor → the roof
经过各方案的优选,采用搭设高空操作平台、劲性梁吊挂模施工方法,即在23层楼面结构1搭梁设钢结构操作平台、满堂脚操作层3,屋面层楼面结构4劲性梁采用吊挂模施工、板采用自承重楼承板施工。After optimization of various schemes, the construction method of setting up high-altitude operation platform and stiff beam hanging formwork is adopted, that is, a steel structure operation platform is set up on the floor structure 1 of the 23rd floor, the operation floor with full hall feet is 3, and the floor structure of the roof floor is 4 stiff The beams are constructed with hanging formwork, and the slabs are constructed with self-supporting floor slabs.
施工方法具体步骤如下;The specific steps of the construction method are as follows;
第一步:操作平台工字钢主梁的安装:在东、西塔楼结构下层楼面结构1施工完成砼强度达到2.0MPa后,进行操作平台的工字钢主梁5安装工作,工字钢主梁5由塔式起重机的吊绳与主梁吊环33连接后吊装至下层楼面结构1,主梁锚环36需在下层楼面结构1浇注前进行预埋,因⑦、⑧轴外墙大部分为剪力墙结构,因此剪力墙在支模时需在工字钢主梁安装部位预留好孔洞,以便后期的拆除。工字钢主梁5吊装安装后在端部与主梁锚环36进行固定;The first step: installation of the I-beam main beam of the operation platform: after the construction of the lower floor structure 1 of the east and west tower structures is completed and the concrete strength reaches 2.0MPa, the installation of the I-beam
第二步:在施工上层楼面结构2时预埋斜拉杆预埋件12、保险斜拉钢丝绳吊环17,待砼强度达到设计强度75%后,进行工字钢斜拉杆6、工字钢次梁7的安装,工字钢斜拉杆6通过高强螺栓34与连接耳板30进行连接;Step 2: When constructing the upper floor structure 2, pre-embed the embedded
第三步:上层楼面结构2与屋面层楼面结构4的柱施工,待柱砼强度达到设计强度75%后进行连廊部位内锚段劲性梁型钢吊装、结构模板、钢筋施工、砼浇注;The third step: the column construction of the upper floor structure 2 and the
第四步:进行满堂脚手架操作平台3架体搭设,即操作平台的纵横向钢管13、水平剪刀撑9、隔离层15、上人爬梯14、临边防护斜撑11的安装搭设,隔离层15满铺脚手片下挂安全网;Step 4: Carry out the erection of the 3-frame body of the scaffolding operation platform in the whole hall, that is, the installation and erection of the vertical and
第五步:待屋面层非连廊部位结构砼强度达到设计强度的75%后,采用塔吊进行连廊部分的劲性主梁21、劲性次梁22型钢的吊装、固定安装;Step 5: After the structural concrete strength of the non-corridor part of the roof layer reaches 75% of the design strength, the tower crane is used to hoist and fix the rigid
第六步:劲性主梁21、劲性次梁22型钢吊装完成、满堂脚手架操作平台3搭设完毕后,安装劲性主梁21、劲性次梁22的U形螺杆27,U形螺杆27通过方钢23与双螺母28固定梁底模板38和内楞方木29,内楞方木29平行于梁轴线布置,方钢23垂直行梁轴线布置;当梁底模板38安装完成固定后进行梁内钢筋安装和梁侧模板25安装,梁侧模板25外侧安装内楞方木29并由双钢管外楞24和对拉螺杆26进行紧固;梁底模板38和梁侧模板25安装完成后在劲性主梁21、劲性次梁22梁顶预埋好与钢筋桁架模板焊接的劲性板20,厚劲性板20与劲性主梁21、劲性次梁22箍筋上焊接,进行连廊部位的劲性主梁21及一半截面高度的边梁砼浇筑;脚手架立杆18通过连墙件32与剪力墙31固定连接;Step 6: After the steel hoisting of the rigid main beam 21 and the rigid secondary beam 22 is completed, and the scaffolding operation platform 3 is erected, install the U-shaped screw 27 and the U-shaped screw 27 of the rigid main beam 21 and the rigid secondary beam 22 Fix the beam bottom formwork 38 and the inner corrugated square wood 29 through the square steel 23 and double nuts 28, the inner corrugated square wood 29 is arranged parallel to the beam axis, and the square steel 23 is arranged perpendicular to the beam axis; when the beam bottom formwork 38 is installed and fixed, carry out Installation of steel bars inside the beam and installation of beam side formwork 25, installation of inner corrugated square wood 29 on the outside of beam side formwork 25 and fastening by double steel pipe outer corrugation 24 and tension screw 26; after the beam bottom formwork 38 and beam side formwork 25 are installed The stiffening plate 20 welded with the reinforcement truss formwork is pre-buried on the top of the stiff main beam 21 and the stiff secondary beam 22, and the thick stiff plate 20 is welded on the stirrups of the stiff main beam 21 and the stiff secondary beam 22, Concrete pouring of the rigid main beam 21 of the corridor and the edge beam of half the height of the section; the scaffold pole 18 is fixedly connected with the shear wall 31 through the connecting wall piece 32;
第七步:连廊部位的劲性次梁22及剩余一半的边梁砼浇注;Step 7: concrete pouring of the rigid
第八步:自承式钢筋桁架模板19的施工,浇筑屋面层楼面结构4砼;The eighth step: the construction of the self-supporting
第九步:拆除梁底模板38;The ninth step: remove the
第十步:拆除满堂脚手架操作平台3、工字钢斜拉杆6、工字钢次梁7、工字钢主梁5。Step 10: Remove the mantang
a、架体拆除a. Removal of the frame
第一步 清除满堂脚手架操作平台3上的垃圾、杂物,拆除安全网。The first step is to remove the garbage and sundries on the
第二步 拆除满堂脚手架操作平台3上的脚手板:拆除顺序从南北两侧往中间进行,留宽1.5m左右范围临时上人平台35作为通道最后拆除。The second step is to dismantle the scaffold board on the
第三步 拆除竖向剪刀撑8、水平剪刀撑9。The third step is to remove the
第四步 由上而下进行纵横向钢管13、脚手架立杆18拆除。拆除下来的钢管、扣件,通过临时上人平台35处洞口运至楼层内。The fourth step is to remove the vertical and
c、工字钢次梁7、工字钢斜拉杆6拆除。c. The I-beam
工字钢次梁7拆除前采用方木、模板在工字钢次梁7上铺设临时的上人通道。Before the I-beam
根据现场情况,拆除分为先两侧后中间进行,中间留设临时上人平台35,最后进行拆除。According to the site conditions, the demolition is divided into two sides and then the middle, leaving a temporary access platform 35 in the middle, and finally demolishing.
操作工人必须系好安全带并保证安全带有可靠拉接点后方可进行作业,首先将跳板搁置在临时作业平台与工字钢次梁7上稳固后,操作工人站在跳板上用磨光机将工字钢次梁7与工字钢主梁5固定焊点割开,然后将绳索栓在工字钢次梁7两侧将工字钢拖至临时作业平台上,运至楼层内,再进行下段次梁7的拆除,纵向的一条工字钢7拆除结束,将平台向内移进一跨,按照同样的方法进行下面的次梁7拆除。The operator must fasten the safety belt and ensure that the safety belt has a reliable pull point before carrying out the operation. First, the springboard is placed on the temporary work platform and the I-beam
临时平台移至最里侧后,按工字钢主梁5跨度采取倒退式进行分段拆除,首先进行工字钢斜拉杆6拆除,为确保安全,工字钢斜拉杆6拆除之前必须先将保险斜拉钢丝绳16安装到位,保险斜拉钢丝绳16一端固定在保险斜拉钢丝绳吊环17上,另一端与主梁吊环33进行连接。工字钢斜拉杆6自重较大,需分4段气割拆除。工字钢斜拉杆6拆除后一边拆除脚手板,一边拆除工字钢次梁7,最后将保险斜拉钢丝绳16割断,便于最后的工字钢主梁5拆除。After the temporary platform is moved to the innermost side, it is dismantled in sections according to the span of the I-steel
最后进行通道部位次梁的拆除。Finally, the secondary beam at the channel part is removed.
d、操作平台工字钢主梁5拆除d. Removal of the I-beam
工字钢主梁5拆除,采用:在屋面连廊中间沉降缝部位安装卷扬机,在拆除工字钢次梁7时,将手动卷扬机的钢丝绳固定在工字钢主梁5的拉环上,然后将吊挂钢丝绳拉直后锁住卷扬机制动。待工字钢次梁7、工字钢斜拉杆6、保险斜拉钢丝绳16拆除完成后,采用气焊将工字钢主梁5从两边端部割断,打开卷扬机制动将工字钢主梁5缓缓吊至三层楼面上,最后运至堆放场地。To dismantle the I-beam
e、外墙上拉环拆除e. Remove the pull ring on the outer wall
外墙上的拉环利用外墙装饰时吊篮进行拆卸。The pull ring on the outer wall is disassembled by using the hanging basket when the outer wall is decorated.
本实用新型的支撑体系上部操作平台荷载通过钢管支架和连系梁传递到工字钢梁和斜拉杆上,传力明确,受力合理。安装拉杆方便、安全,用钢量少,经济性高,另外单一构件的重量较小,工艺简单无特殊要求,占用场地少,便于高空操作,施工工艺简单、结构可靠、稳定性强、装拆方便、实用性强。The load of the upper operating platform of the support system of the utility model is transmitted to the I-shaped steel beam and the diagonal stay rod through the steel pipe support and the connecting beam, so that the force transmission is clear and the force is reasonable. The installation of tie rods is convenient and safe, with less steel consumption and high economy. In addition, the weight of a single component is small, the process is simple and has no special requirements, and it occupies less space, which is convenient for high-altitude operation. The construction process is simple, the structure is reliable, the stability is strong, and the assembly and disassembly Convenient and practical.
除上述实施例外,本实用新型还可以有其他实施方式。凡采用等同替换或等效变换形成的技术方案,均落在本实用新型要求的保护范围。In addition to the above embodiments, the utility model can also have other implementations. All technical solutions formed by equivalent replacement or equivalent transformation fall within the scope of protection required by the utility model.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011203458244U CN202227476U (en) | 2011-09-15 | 2011-09-15 | High-altitude large-span overhung corridor-type reinforced concrete structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011203458244U CN202227476U (en) | 2011-09-15 | 2011-09-15 | High-altitude large-span overhung corridor-type reinforced concrete structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN202227476U true CN202227476U (en) | 2012-05-23 |
Family
ID=46078065
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2011203458244U Withdrawn - After Issue CN202227476U (en) | 2011-09-15 | 2011-09-15 | High-altitude large-span overhung corridor-type reinforced concrete structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN202227476U (en) |
Cited By (16)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102444203A (en) * | 2011-09-15 | 2012-05-09 | 浙江城建建设集团有限公司 | High-altitude large-span cantilever corridor type steel concrete structure and construction method |
| CN102888991A (en) * | 2012-10-25 | 2013-01-23 | 南通纺织职业技术学院 | Large-scale profile steel beam and concrete combined house roof constructing method |
| CN103061501A (en) * | 2012-12-29 | 2013-04-24 | 中建八局第二建设有限公司 | Formwork supporting system for composite beam and floor-slab structure of building and construction method for formwork supporting system |
| CN103993739A (en) * | 2014-05-19 | 2014-08-20 | 中化二建集团有限公司 | Method for constructing stiff beam of spraying layer of prilling tower |
| CN104314312A (en) * | 2014-11-12 | 2015-01-28 | 江苏南通六建建设集团有限公司 | High altitude reinforced concrete corridor structure triangle steel tube cantilever formwork construction technology |
| CN104900136A (en) * | 2015-05-29 | 2015-09-09 | 长沙理工大学 | Cable stayed bridge for test, and mounting method |
| CN106193592A (en) * | 2016-08-29 | 2016-12-07 | 成都市第四建筑工程公司 | A kind of form bracing system and construction method |
| CN106760500A (en) * | 2017-03-07 | 2017-05-31 | 中国五冶集团有限公司 | A kind of formwork support structure of hole to be provided top cover construction |
| CN108487312A (en) * | 2015-11-29 | 2018-09-04 | 杭州跟策科技有限公司 | Contain template vehicle in channel |
| CN108643121A (en) * | 2018-06-09 | 2018-10-12 | 中交航局第工程有限公司 | A kind of frame-type construction bracket and its building technology |
| CN109736440A (en) * | 2019-02-28 | 2019-05-10 | 北京市第三建筑工程有限公司 | A kind of large-span steel staggered floor closes up installation method |
| CN110644613A (en) * | 2019-09-23 | 2020-01-03 | 上海宝冶建筑工程有限公司 | Convenient pull-up formula board strutting arrangement that encorbelments of dismantling |
| CN110805257A (en) * | 2019-11-18 | 2020-02-18 | 广西途辉建筑工程有限公司 | Flower basket overhanging type section steel bearing beam structure and construction method |
| CN113775207A (en) * | 2021-09-22 | 2021-12-10 | 张国锋 | Temporary door type passage design and construction method for building |
| CN115559520A (en) * | 2022-10-18 | 2023-01-03 | 中国建筑第四工程局有限公司 | Construction method for oversized-span high-altitude cast-in-situ corridor supporting structure |
| CN117365153A (en) * | 2023-12-01 | 2024-01-09 | 中建八局第二建设有限公司 | A method for reinforcing super high-rise cavity concrete |
-
2011
- 2011-09-15 CN CN2011203458244U patent/CN202227476U/en not_active Withdrawn - After Issue
Cited By (23)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102444203B (en) * | 2011-09-15 | 2013-06-19 | 浙江城建建设集团有限公司 | High-altitude long-span overhanging corridor type reinforced concrete structure and construction method |
| CN102444203A (en) * | 2011-09-15 | 2012-05-09 | 浙江城建建设集团有限公司 | High-altitude large-span cantilever corridor type steel concrete structure and construction method |
| CN102888991A (en) * | 2012-10-25 | 2013-01-23 | 南通纺织职业技术学院 | Large-scale profile steel beam and concrete combined house roof constructing method |
| CN103061501A (en) * | 2012-12-29 | 2013-04-24 | 中建八局第二建设有限公司 | Formwork supporting system for composite beam and floor-slab structure of building and construction method for formwork supporting system |
| CN103061501B (en) * | 2012-12-29 | 2015-03-25 | 中建八局第二建设有限公司 | Formwork supporting system for composite beam and floor-slab structure of building and construction method for formwork supporting system |
| CN103993739A (en) * | 2014-05-19 | 2014-08-20 | 中化二建集团有限公司 | Method for constructing stiff beam of spraying layer of prilling tower |
| CN104314312A (en) * | 2014-11-12 | 2015-01-28 | 江苏南通六建建设集团有限公司 | High altitude reinforced concrete corridor structure triangle steel tube cantilever formwork construction technology |
| CN104314312B (en) * | 2014-11-12 | 2017-02-15 | 江苏南通六建建设集团有限公司 | High altitude reinforced concrete corridor structure triangle steel tube cantilever formwork construction technology |
| CN104900136A (en) * | 2015-05-29 | 2015-09-09 | 长沙理工大学 | Cable stayed bridge for test, and mounting method |
| CN108487312B (en) * | 2015-11-29 | 2020-08-28 | 诸暨市澳速机械设计工作室 | Channel culvert template vehicle |
| CN108487312A (en) * | 2015-11-29 | 2018-09-04 | 杭州跟策科技有限公司 | Contain template vehicle in channel |
| CN106193592A (en) * | 2016-08-29 | 2016-12-07 | 成都市第四建筑工程公司 | A kind of form bracing system and construction method |
| CN106760500A (en) * | 2017-03-07 | 2017-05-31 | 中国五冶集团有限公司 | A kind of formwork support structure of hole to be provided top cover construction |
| CN108643121A (en) * | 2018-06-09 | 2018-10-12 | 中交航局第工程有限公司 | A kind of frame-type construction bracket and its building technology |
| CN109736440A (en) * | 2019-02-28 | 2019-05-10 | 北京市第三建筑工程有限公司 | A kind of large-span steel staggered floor closes up installation method |
| CN109736440B (en) * | 2019-02-28 | 2020-07-14 | 北京市第三建筑工程有限公司 | Staggered-layer folding installation method for large-span steel structure |
| CN110644613A (en) * | 2019-09-23 | 2020-01-03 | 上海宝冶建筑工程有限公司 | Convenient pull-up formula board strutting arrangement that encorbelments of dismantling |
| CN110805257A (en) * | 2019-11-18 | 2020-02-18 | 广西途辉建筑工程有限公司 | Flower basket overhanging type section steel bearing beam structure and construction method |
| CN110805257B (en) * | 2019-11-18 | 2022-03-15 | 广西途辉建筑工程有限公司 | Flower basket overhanging type section steel bearing beam structure and construction method |
| CN113775207A (en) * | 2021-09-22 | 2021-12-10 | 张国锋 | Temporary door type passage design and construction method for building |
| CN113775207B (en) * | 2021-09-22 | 2022-09-23 | 张国锋 | Temporary door type passage design and construction method for building |
| CN115559520A (en) * | 2022-10-18 | 2023-01-03 | 中国建筑第四工程局有限公司 | Construction method for oversized-span high-altitude cast-in-situ corridor supporting structure |
| CN117365153A (en) * | 2023-12-01 | 2024-01-09 | 中建八局第二建设有限公司 | A method for reinforcing super high-rise cavity concrete |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN202227476U (en) | High-altitude large-span overhung corridor-type reinforced concrete structure | |
| CN102444203B (en) | High-altitude long-span overhanging corridor type reinforced concrete structure and construction method | |
| CN103635643B (en) | Construction Method of Reinforced Concrete Cylinder in High-rise Steel Structure Building | |
| CN101886466B (en) | Construction method for support structure of coal tower template for tamping type coke oven | |
| CN105926448B (en) | A kind of construction method of the Cable stayed Bridge Main Tower in the double rope faces of the only tower of curve | |
| CN105298100B (en) | A kind of cylinder building cast-in-place flare structure of superelevation is encorbelmented the construction method of operation platform | |
| CN102392536B (en) | Construction method for long-span hanging vestibule type template support system | |
| CN102535845A (en) | Construction method of bearing frame of corridor structure | |
| CN103452311A (en) | Method for erecting section steel cantilever structure support frame | |
| CN110409318B (en) | A method for assembling and erecting large-span simply supported steel-concrete beams | |
| CN108677962B (en) | Subway entrance and exit segment foundation pit formwork installing and dismantling method | |
| CN105649314A (en) | Suspension platform for high and long-span corridor construction | |
| CN101775896B (en) | Rigid suspended scaffold for installing pipeline of steel roof equipment | |
| CN106592962A (en) | Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus | |
| CN106284103B (en) | Steel reinforced concrete combination beam roof steel bar concrete high-altitude cantilever pouring construction method | |
| CN103993666A (en) | Improved supporting system construction method suitable for large overhung outer floating plate roof | |
| CN212507296U (en) | High formwork system | |
| CN103122691A (en) | Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method | |
| CN110409319A (en) | A kind of cast-in-place floorings bracket of large span steel reinforced concrete combination beam and construction method | |
| CN110409624A (en) | A large-scale equipment installation and main structure reverse calculation and construction method | |
| CN206902913U (en) | A kind of high-altitude long-span overhung structure | |
| CN103993739B (en) | The construction method of granulation tower spraying layer stiff beam | |
| CN201915631U (en) | High-altitude long-span reinforced concrete corridor construction supporting structure | |
| CN205502551U (en) | Platform is suspended in midair in high altitude large -span vestibule construction | |
| CN203034799U (en) | Tower hoist standard knot bearing overhead support formwork steel platform structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| AV01 | Patent right actively abandoned |
Granted publication date: 20120523 Effective date of abandoning: 20130619 |
|
| AV01 | Patent right actively abandoned |
Granted publication date: 20120523 Effective date of abandoning: 20130619 |
|
| RGAV | Abandon patent right to avoid regrant |
