CN202202251U - Boarding bridge - Google Patents

Boarding bridge Download PDF

Info

Publication number
CN202202251U
CN202202251U CN2011203011828U CN201120301182U CN202202251U CN 202202251 U CN202202251 U CN 202202251U CN 2011203011828 U CN2011203011828 U CN 2011203011828U CN 201120301182 U CN201120301182 U CN 201120301182U CN 202202251 U CN202202251 U CN 202202251U
Authority
CN
China
Prior art keywords
channel
door frame
going
bridge
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011203011828U
Other languages
Chinese (zh)
Inventor
杨月峰
张肇红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen CIMC Tianda Airport Support Ltd
Original Assignee
China International Marine Containers Group Co Ltd
Shenzhen CIMC Tianda Airport Support Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China International Marine Containers Group Co Ltd, Shenzhen CIMC Tianda Airport Support Ltd filed Critical China International Marine Containers Group Co Ltd
Priority to CN2011203011828U priority Critical patent/CN202202251U/en
Application granted granted Critical
Publication of CN202202251U publication Critical patent/CN202202251U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a boarding bridge which comprises a first walkable portal, a second walkable portal independent from the first walkable portal, a first channel, a lifting device, a second channel and a third channel, wherein the first channel is suitable for being butted with a waiting castle and is fixedly arranged on the first walkable portal; the lifting device is arranged on the second walkable portal and comprises a lifting table and a driving device, the lifting table can perform lifting motion relative to the second walkable portal, and the driving device is used for driving the lifting table to move; the second channel is suitable for being butted with a passenger liner and is arranged on the lifting table; the third channel which has telescopic length is connected between the first channel and the second channel; and the telescopic third channel is coordinated with the lifting device, the first walkable portal and the second walkable portal, so that not only can the length of the third channel be adjustable, but also the slope, relative to a horizontal plane, of the third channel can be adjustable.

Description

A kind of bridge of going on board
Technical field
The utility model relates to the bridge of going on board.
Background technology
The bridge of going on board is arranged on the harbour, comfortable, transit passage easily is provided waiting between castle and the cruise to the passenger.An early stage Chinese invention patent application 200910237531.1 of applicant provides a kind of bridge of going on board.As shown in Figure 1, this bridge of going on board comprises first frame 26 and second frame 25 that is set up in parallel with predetermined space.Be fixed with the interface gallery 202 that docks with marquis's castle 24 on first frame 26.One end of second frame 25 is provided with and goes up and down to lack corridor 203, and the ship mouth 204 that connects that is used for docking with cruise is arranged on a side of going up and down to lack corridor 203; The other end of second frame 25 is fixed with the fixing short corridor 207 that is connected with the short corridor 203 that goes up and down.Passing through fixedly between interface gallery 202 and the fixing short corridor 207, gallery 210 links to each other.This bridge of going on board has decomposed drop through between first frame 26 and second frame 25, gallery being set, the mild gradient.Factors such as vertical bank direction spacing according to drop height, time castle and cruise can be provided with a plurality of galleries (as 211,213) between first and second frames, and on corresponding frame, necessary short corridor (as 206) are being set.
Yet in a single day this bridge of going on board is set up, and its gallery is unadjustable along the gradient and length along the bank direction, and is difficult to adapt to the variation of waiting vertical bank direction spacing between castle and the cruise.Because it is diversified resting in the type of the cruise of quayside, therefore this bridge of going on board is difficult to satisfy the actual use needs of harbour.
The utility model content
The purpose of the utility model is to provide a kind of bridge of going on board, to solve or to be to improve one or more deficiencies above-mentioned at least.
For realizing above-mentioned purpose, the utility model provides a kind of bridge of going on board, and it is used between marquis's castle and cruise, for the passenger transit passage being provided.The said bridge of going on board comprises: first door frame that can walk; Second door frame is independent of said first door frame and also can walks; Be suitable for the first passage that docks with said marquis's castle, be fixedly installed on said first door frame; Lifting gear is arranged on said second door frame, the drive unit that comprises the elevating stage that moves with respect to the said second door frame liftable and be used to drive the motion of said elevating stage; Be suitable for the second channel that docks with said cruise, be arranged on the said elevating stage; And the telescopic third channel of length, be connected between said first passage and the said second channel.
One end of said third channel is hinged to said first door frame and the other end is hinged to said elevating stage.
Said third channel can comprise first section of being hinged to said first door frame with second section that is hinged to said elevating stage, the socket and can sliding relatively each other of said first section and second section.
Said second channel can be that length is telescopic, and comprises two sections that interlock each other, wherein first section be fixed on the said elevating stage and second section with said first section socket and with respect to said first section movable.
The length of said second channel is fixed, and slidably is installed on the said elevating stage, the end of said third channel through be arranged on one of said second channel side slide the door be connected with said second channel.
Said second channel can be provided with along vertical bank direction, and said third channel can be along being provided with along the bank direction.
The bottom of said first door frame and/or said second door frame can be respectively arranged with one or more wheels that are used to walk.
Said first door frame can be along walking along bank and/or vertical bank direction; Said second door frame also can be along walking along bank and/or vertical bank direction.
Said first passage can comprise be suitable for docking with the door opening of marquis's castle connect the building mouth.
Said second channel can comprise be suitable for docking with the hatch door of cruise connect the ship mouth.
The said bridge of going on board also can comprise the ladder that is arranged on said first door frame, and one of said ladder terminates to said first passage, and the other end is received ground.
The second channel of the bridge of going on board that is arranged so that the utility model of the lifting gear and second door frame that can walk is in vertical direction and the equal scalable of horizontal direction, thereby can accurately dock with dissimilar cruise realizations.First and/or second door frame that telescopic third channel cooperates lifting gear and can walk makes not only also scalable of adjustable in length but also the gradient with respect to the horizontal plane of third channel.
Below in conjunction with accompanying drawing and detailed embodiment the utility model is elaborated.
Description of drawings
Fig. 1 is the schematic top plan view of the bridge of going on board mentioned in the early stage patent application of applicant;
Fig. 2 is the front view according to the bridge of going on board of the utility model one embodiment;
Fig. 3 is the vertical view of the bridge of going on board among Fig. 2;
Fig. 4 is the end view of the bridge of going on board among Fig. 2;
Fig. 5 is according to the front view of the bridge of going on board of another embodiment of the utility model;
The vertical view of the bridge of going on board among Fig. 6 Fig. 5.
The specific embodiment
Below, through exemplary embodiment the utility model is specifically described.Yet should be appreciated that under the situation that is not having further narration element, structure and characteristic among embodiment also can be attached in other embodiment valuably.
Shown in Fig. 2-4; The bridge 100 of going on board according to the utility model one embodiment is arranged on the G of quay surface, comprise first door frame 110, second door frame 120 that can walk, be fixedly installed on first passage 130 on first door frame 110, be arranged on lifting gear 140 and the second channel 150 on second door frame 120 and be connected first passage 130 and second channel 150 between the telescopic third channel 160 of length.Wherein, first passage 130 is set for marquis's castle 10 and docks, and second channel 150 is set for cruise (not shown) and docks.Like this, first passage 130, third channel 160 and second channel 150 just form a passage that supplies passenger's walking between marquis's castle and cruise.
Lifting gear 140 is arranged on second door frame 120, comprises the drive unit of the elevating stage 141 that can move up and down with respect to second door frame 120 and the motion that is used to drive elevating stage 141, like fluid pressure drive device etc.Second channel 150 is arranged on the elevating stage 141, thereby lifting gear capable of using 140 adjustment second channels 150 are with respect to the vertical height of quay surface.Show the second channel 150 that is in the higher position with solid line among Fig. 4, and be shown in broken lines the second channel 150 ' that is in lower position.Simultaneously, second door frame 120 that can walk of utilization can be adjusted second channel 150 position in the horizontal direction.This set of the utility model makes second channel 150 have adjustable range widely, can realize accurately docking with dissimilar cruises.
In an example, second channel 150 is that length is telescopic, so that adapt to the variable in distance between cruise hatch door and the marquis's castle better.For example, second channel 150 can comprise two sections that interlock each other, wherein is fixed on the elevating stage 141 second section 152 and first sections 151 socket and with respect to first section 151 slidably for first section 151.Like this, on the one hand, second channel 150 can dock with the different cruise of distance that pulls in to shore smoothly; Also make the bridge of going on board of the utility model can be applicable to different harbours on the other hand.
In an alternative example of the utility model, the length of second channel also can be fixing.Like Fig. 5, shown in 6, second channel 150 ' for example be installed on the elevating stage 141 slidably or rollably through slide block or the roller 153 that is provided with thereunder, and can be provided with track 154 accordingly on the elevating stage 141.Second channel 150 ' on track 154, slide through roller or slide block 153; Door 155 and second channel 150 ' be connected are slided through being arranged on one of second channel 150 ' side in the end of third channel 160, thus second channel 150 ' in the process of sliding, dock with third channel all the time.Here, sliding door 155 can be the door that slides of any known type, its can second channel 150 ' side (between) for example near position intermediate and end slide.Second channel 150 ' other structure be provided with second channel 150 similar.First passage 130 the end towards marquis's castle preferably be provided be suitable for docking with the door opening of marquis's castle connect building mouth 132.Second channel 150 the end towards cruise preferably be provided be suitable for docking with the cruise hatch door connect ship mouth 158.According to an embodiment of the utility model, second channel 150 is along the bank direction setting of hanging down, and third channel 160 is along being provided with along the bank direction.Yet,, can first, second and third channel be set along any suitable direction according to actual conditions.
When the distance between first door frame 110 and second door frame 120 changes, and when elevating stage 141 moved up and down, the length of third channel 160 is telescopic variation correspondingly, and third channel 160 gradient α with respect to the horizontal plane also can change.Like this, when cruise has a plurality of hatch door, can select suitable hatch door and second channel 150 to achieve a butt joint, so that third channel 160 has the gradient α of suitable person walks.In an example, the two ends of third channel 160 can be hinged to first door frame 110 and elevating stage 141 respectively.Specifically, third channel 160 comprises first section 161 of being hinged to first door frame 110 and is hinged to second section 162, the first sections 161 and second sections 162 of elevating stage 141 sockets and can sliding relatively each other.Alternatively, the two ends of third channel 160 also can be hinged to first passage 130 and second channel 140 respectively.
According to an embodiment of the utility model, first door frame 110 also can be arranged to walk, and the walking of first door frame 110 and second door frame 120 is relatively independent.Specifically, the speed synchronization walking that two door frames 110,120 can be identical perhaps also can friction speed be walked relatively independently.Each door frame 110,120 all can be along walking along bank and/or vertical bank direction.Yet according to the utility model, door frame 110,120 according to actual needs can be along the direction walking of any appropriate.For marquis's castle that a plurality of door openings are arranged; Can select a suitable door opening to realize docking according to the stop position of cruise with first passage 130; So that the length that shortens third channel 160 reduces the distance of passenger's walking, or the gradient α of third channel 160 is adjusted in the suitable scope.
In an example, the bottom of first door frame 110 can be provided with one or more wheels that are used to walk 112, and the bottom of second door frame 120 also can be provided with one or more wheels that are used to walk 122.First door frame 110 and/or second door frame 120 can be implemented in the walking on the quay surface through modes such as manual work or motor-driven.
According to an embodiment, the bridge 100 of going on board also can comprise the ladder 170 that is arranged on first door frame 110.One end 171 of ladder 170 docks with first passage 130, and the other end 172 is received the quay surface, directly gets into the passage of the bridge of going on board from harbour thereby be convenient to passenger or staff.
Though should be pointed out that through above-mentioned embodiment the utility model is described, yet the utility model also can have other numerous embodiments.Under the prerequisite that does not break away from the utility model spirit and scope; Those of ordinary skill in the art obviously can make various corresponding changes and distortion to the utility model, but these changes and distortion all should belong in the scope that the utility model accompanying claims and equivalent thereof protect.

Claims (11)

1. bridge of going on board is used between marquis's castle and cruise it is characterized in that for the passenger provides transit passage the said bridge of going on board comprises:
First door frame that can walk;
Second door frame is independent of said first door frame and also can walks;
Be suitable for the first passage that docks with said marquis's castle, be fixedly installed on said first door frame;
Lifting gear is arranged on said second door frame, the drive unit that comprises the elevating stage that moves with respect to the said second door frame liftable and be used to drive the motion of said elevating stage;
Be suitable for the second channel that docks with said cruise, be arranged on the said elevating stage; And
The telescopic third channel of length is connected between said first passage and the said second channel.
2. the bridge of going on board according to claim 1, an end of wherein said third channel is hinged to said first door frame and the other end is hinged to said elevating stage.
3. the bridge of going on board according to claim 1 and 2, wherein said third channel comprise first section of being hinged to said first door frame with second section that is hinged to said elevating stage, the socket and can sliding relatively each other of said first section and second section.
4. the bridge of going on board according to claim 1, wherein said second channel are that length is telescopic, and comprise two sections that interlock each other, wherein first section be fixed on the said elevating stage and second section with said first section socket and with respect to said first section slidably.
5. the bridge of going on board according to claim 1; The length of wherein said second channel is fixed; And be installed in slidably or rollably on the said elevating stage, the end of said third channel through be arranged on one of said second channel side slide the door be connected with said second channel.
6. the bridge of going on board according to claim 1 and 2, wherein said second channel are along the bank direction setting of hanging down, and said third channel is along being provided with along the bank direction.
7. the bridge of going on board according to claim 1, the bottom of wherein said first door frame and/or said second door frame is respectively arranged with one or more wheels that are used to walk.
8. according to claim 1 or the 7 described bridges of going on board, wherein said first door frame is along walking along bank and/or vertical bank direction; Said second door frame is along walking along bank and/or vertical bank direction.
9. the bridge of going on board according to claim 1, wherein said first passage comprise be suitable for docking with the door opening of marquis's castle connect the building mouth.
10. the bridge of going on board according to claim 1, wherein said second channel comprise be suitable for docking with the hatch door of cruise connect the ship mouth.
11. the bridge of going on board according to claim 1 also comprises the ladder that is arranged on said first door frame, one of said ladder terminates to said first passage, and the other end is received ground.
CN2011203011828U 2011-08-18 2011-08-18 Boarding bridge Expired - Lifetime CN202202251U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011203011828U CN202202251U (en) 2011-08-18 2011-08-18 Boarding bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011203011828U CN202202251U (en) 2011-08-18 2011-08-18 Boarding bridge

Publications (1)

Publication Number Publication Date
CN202202251U true CN202202251U (en) 2012-04-25

Family

ID=45966383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011203011828U Expired - Lifetime CN202202251U (en) 2011-08-18 2011-08-18 Boarding bridge

Country Status (1)

Country Link
CN (1) CN202202251U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951400A (en) * 2018-05-29 2018-12-07 广州宾模工程管理有限公司 A kind of boarding bridge and equipment of going on board with double-layer lifting gallery
CN112030716A (en) * 2020-05-14 2020-12-04 深圳中集天达空港设备有限公司 Cross-sliding boarding bridge and control method thereof
SE2050212A1 (en) * 2020-02-25 2021-08-26 Fmt Int Trade Ab Passenger bridge

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951400A (en) * 2018-05-29 2018-12-07 广州宾模工程管理有限公司 A kind of boarding bridge and equipment of going on board with double-layer lifting gallery
SE2050212A1 (en) * 2020-02-25 2021-08-26 Fmt Int Trade Ab Passenger bridge
WO2021173065A1 (en) * 2020-02-25 2021-09-02 Fmt International Trade Ab Passenger bridge
SE543962C2 (en) * 2020-02-25 2021-10-12 Fmt Int Trade Ab Passenger bridge
US11761159B2 (en) 2020-02-25 2023-09-19 Fmt International Trade Ab Passenger bridge
EP4110993A4 (en) * 2020-02-25 2023-10-04 Fmt International Trade AB Passenger bridge
CN112030716A (en) * 2020-05-14 2020-12-04 深圳中集天达空港设备有限公司 Cross-sliding boarding bridge and control method thereof

Similar Documents

Publication Publication Date Title
CN201202086Y (en) Moving lifting type passenger boarding bridge
AU2012311213B2 (en) System of vertical and horizontal movement of the transport cabin in a elevator translator plant for the overcoming of obstacles
CN202202251U (en) Boarding bridge
CN204078018U (en) Boats and ships are gone on board device
WO2019227965A1 (en) Offshore platform embarkation apparatus and offshore platform
US20080066241A1 (en) Overhead self-levelling lift system for transporting payloads in dynamic settings and use thereof
ATE521534T1 (en) AIRCRAFT WITH AN ELEVATOR
CN102310928A (en) L-shaped traveler boarding bridge
CN202911921U (en) Novel telescopic type combined gangway ladder
CN101857075B (en) Lifting system of slipway
CN202194681U (en) Movable transfer belt conveyor under coal mine
CN103171960A (en) Inclined roadway personnel transportation system with extensible pedals
CN211810076U (en) Sliding door for hydraulic sliding type pilot
CN108674502B (en) Robot for searching and rescuing in marsh
CN203143898U (en) Inclined roadway personnel transportation system provided with telescopic pedals
CN207785898U (en) Double-deck drift river amusement facility
CN210262667U (en) Telescopic boarding bridge of rail mounted
CN112030716B (en) Cross-sliding boarding bridge and control method thereof
CN110847581B (en) Climbing frame with lifting and conveying functions
CN210126612U (en) Side door device capable of automatically retracting and adjusting height
CN205530143U (en) Reservoir dam upstream face concrete panel observation device
CN207498762U (en) A kind of grade separation bus or train route conversion equipment for having function of parking concurrently
CN220813402U (en) Multi-ship-receiving port boarding system capable of being independently adjusted
CN116552715A (en) Passenger boarding bridge capable of adjusting ship receiving port along shore
CN112374337A (en) Port lifting adjusting type pedestrian path

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210621

Address after: 518103 No.9, Fuyuan 2nd Road, Fuyong street, Bao'an District, Shenzhen City, Guangdong Province

Patentee after: SHENZHEN CIMC-TIANDA AIRPORT SUPPORT Co.,Ltd.

Address before: Four No. four industrial road, Shekou Industrial Zone, Guangdong, Shenzhen 518067, China

Patentee before: SHENZHEN CIMC-TIANDA AIRPORT SUPPORT Co.,Ltd.

Patentee before: China International Marine Containers (Group) Co.,Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20120425