CN202164545U - Vertical prestressing pore canal communicating pipes and mud-jacking pipes - Google Patents

Vertical prestressing pore canal communicating pipes and mud-jacking pipes Download PDF

Info

Publication number
CN202164545U
CN202164545U CN2011202652355U CN201120265235U CN202164545U CN 202164545 U CN202164545 U CN 202164545U CN 2011202652355 U CN2011202652355 U CN 2011202652355U CN 201120265235 U CN201120265235 U CN 201120265235U CN 202164545 U CN202164545 U CN 202164545U
Authority
CN
China
Prior art keywords
pipes
mud
vertical prestressing
jacking
thin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011202652355U
Other languages
Chinese (zh)
Inventor
王海良
任权昌
董鹏
杨新磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Urban Construction College
Original Assignee
Tianjin Urban Construction College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Urban Construction College filed Critical Tianjin Urban Construction College
Priority to CN2011202652355U priority Critical patent/CN202164545U/en
Application granted granted Critical
Publication of CN202164545U publication Critical patent/CN202164545U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

Vertical prestressing pore canal communicating pipes and mud-jacking pipes belong to the technical field of road and bridge construction. The vertical prestressing pore canal communicating pipes and the mud-jacking pipes are characterized in that twisted steel penetrates into a thin-wall steel pipe, two ports of the thin-wall steel pipe are fixedly sealed through an upper nut and a lower nut, horizontal communicating pipes are arranged on the lower portion of the thin-wall steel pipe, inclined mud-jacking pipes or mud discharging pipes are arranged on the upper portion of the thin-wall steel pipe, and the communicating pipes are matched with connecting sleeves in an inserted mode so as to enable the communicating pipes to be communicated in a sealing mode. The vertical prestressing pore canal communicating pipes and the mud-jacking pipes have the advantages of greatly quickening installing speed of vertical prestressing rebar, enabling adjacent assemblies to be integrally communicated through the communicating pipes, enabling all the vertical prestressing pore canal mud jacking to be performed on a bridge surface, reducing construction difficulty, improving construction quality and speed and enabling vacuum mud jacking of a vertical prestressing pore canal to be possible.

Description

Vertical prestressing force opening UNICOM madjack pipe
Technical field
The utility model belongs to the construction of road and bridge technical field.
Background technology
In the construction of long span bridge girder construction; Often in the case web, vertical prestressing bar is set; Along with requiring increasingly high to mud jacking compactness in the duct; Now the duct all requires vacuum grouting in the bridge construction, because that vertical prestressing force opening is provided with is more, and its squeezing quality influences durability of structures.
At present, in the construction of long span bridge beam vertical prestressing force opening mud jacking, traditional vertical prestressing force opening is employed in the interior bottom of case beam madjack pipe is set; In fluid concrete, dismounting, in the mold process, be easy to damage the mud jacking provided pipe, because the existence of mud jacking preformed hole; Internal mold processing, installation have been increased very big difficulty, and caused spillage in the vertical prestressing force opening bottom easily, in the bridge construction of a lot of employing conventional methods construction; A lot of vertical prestressing force openings bottom is arranged can not utilize the provided pipe mud jacking because spillage stops up the duct, having to influences squeezing quality at top, duct redrilling mud jacking; Possibly not realize the vacuum grouting of vertical prestressing force opening; If adopt horizontal double vertical prestressing bar in the web, later stage boring difficulty is bigger, in the long span bridge girder construction; The spacing of vertical prestressing bar is generally about 50cm; Arrange that quantity is quite big, adopt reliable, easy vertical prestressing force opening mud jacking technology, to improving speed of application, guaranteeing that the bridge construction durability is very necessary.
Summary of the invention
The purpose of the utility model is: a kind of vertical prestressing force opening UNICOM madjack pipe is provided, and it can realize vacuum grouting effectively, improves mud jacking, installation, dismounting internal mold speed of application, has improved the bridge engineering quality.
The technical scheme of the utility model is: indented bars passes in the thin-wall steel tube; the thin-wall steel tube two-port is through top nut and lower nut sealing and fixing; be provided with the cross over pipe of level in the thin-wall steel tube bottom; top is provided with the madjack pipe or the outlet pipe of inclination, and each cross over pipe inserts with splicing sleeve and cooperates, and makes airtight connection between each cross over pipe.
The beneficial effect of the utility model is: the smart bundle of vertical prestressing twisted steel, thin-wall steel tube, last madjack pipe (outlet pipe), cross over pipe are processed assembly at the reinforcing bar processing space, accelerated the installation rate of vertical prestressing bar greatly;
Adjacent component is connected to integral body through cross over pipe; And utilize the 22# iron wire to be fixed together; Form the mud jacking cross over pipe, all vertical prestressing force opening mud jackings are all carried out at bridge floor, reduced difficulty of construction; Improved construction quality and speed, and made the vertical prestressing force opening vacuum grouting become possibility.
Description of drawings
Fig. 1 is the utility model structure chart.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is done and to be further described:
As shown in the figure, the 1st, indented bars, the 2nd, thin-wall steel tube, the 3rd, top nut, the 4th, lower nut, the 5th, cross over pipe, the 6th, madjack pipe, the 7th, outlet pipe, the 8th, splicing sleeve, the 9th, concrete or plastic cushion, the 10th, iron wire.
Utilize thin-wall steel tube smart pulp (or mud jacking) pipe of pricking indented bars 1, thin-wall steel tube 2, cross over pipe 5, lower nut 4, top nut 3, top of vertical prestressing to be connected into black box at the reinforcing bar processing space; After case web reinforcing bar binding is accomplished; Assembly is placed in design attitude; Smart indented bars 1 bottom of pricking of vertical prestressing is supported with cushion block 9, makes the smart indented bars 1 of pricking have enough protective layer thickness, and assembly is fixed on the web reinforcement skeleton; Cross over pipe 5 between adjacent component inserts respectively in the bigger splicing sleeve 8; Cross over pipe and splicing sleeve 8 gap at joint positions twine the jail with adhesive tape, for preventing the coupling part to be ripped when the fluid concrete, with 22# iron wire 10 adjacent assembly are connected one.
Concrete pouring finish reach the stretch-draw of designing requirement intensity after, can on bridge floor, carry out the mud jacking of vertical prestressing force opening, be pressed into from an assembly madjack pipe 6 during mud jacking; From another assembly outlet pipe 7 pulps; Cement paste gets into its bottom from an assembly steel pipe top, gets into another assembly steel pipe bottom through cross over pipe 5, is emerged by its top; Whole mud jacking process is all carried out on bridge floor; In box girder inner formwork installation, unloading process, can not occur owing in each bottom, duct the construction inconvenience that madjack pipe causes is set by conventional method, mud jacking, installation, dismounting internal mold speed of application can improve greatly; And squeezing quality can be guaranteed, and makes vertical prestressing force opening adopt vacuum grouting to become possibility.

Claims (1)

1. vertical prestressing force opening UNICOM madjack pipe; Comprise indented bars, it is characterized in that: indented bars passes in the thin-wall steel tube, and the thin-wall steel tube two-port is through top nut and lower nut sealing and fixing; Be provided with the cross over pipe of level in the thin-wall steel tube bottom; Top is provided with the madjack pipe or the outlet pipe of inclination, and each cross over pipe inserts with splicing sleeve and cooperates, and makes airtight connection between each cross over pipe.
CN2011202652355U 2011-07-26 2011-07-26 Vertical prestressing pore canal communicating pipes and mud-jacking pipes Expired - Fee Related CN202164545U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202652355U CN202164545U (en) 2011-07-26 2011-07-26 Vertical prestressing pore canal communicating pipes and mud-jacking pipes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202652355U CN202164545U (en) 2011-07-26 2011-07-26 Vertical prestressing pore canal communicating pipes and mud-jacking pipes

Publications (1)

Publication Number Publication Date
CN202164545U true CN202164545U (en) 2012-03-14

Family

ID=45800384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202652355U Expired - Fee Related CN202164545U (en) 2011-07-26 2011-07-26 Vertical prestressing pore canal communicating pipes and mud-jacking pipes

Country Status (1)

Country Link
CN (1) CN202164545U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747690A (en) * 2012-07-20 2012-10-24 中交二公局第三工程有限公司 Grouting construction method for vertical finish-rolling threaded steel U-shaped communicating tube
CN105568855A (en) * 2015-12-21 2016-05-11 中铁六局集团天津铁路建设有限公司 Construction method for vertical prestressed tendons of continuous beam
CN105908631A (en) * 2016-05-11 2016-08-31 中铁十四局集团第二工程有限公司 Embedded type reinforced concrete combination part mud jacking filling device and construction method
CN109505259A (en) * 2018-12-25 2019-03-22 北京市政建设集团有限责任公司 A kind of bridge box and beam prestressing force vertical tube grouting method
CN113846569A (en) * 2021-11-01 2021-12-28 重庆交通建设(集团)有限责任公司 Continuous rigid frame segment vertical prestressed pipeline series vacuum pressure grouting method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747690A (en) * 2012-07-20 2012-10-24 中交二公局第三工程有限公司 Grouting construction method for vertical finish-rolling threaded steel U-shaped communicating tube
CN105568855A (en) * 2015-12-21 2016-05-11 中铁六局集团天津铁路建设有限公司 Construction method for vertical prestressed tendons of continuous beam
CN105908631A (en) * 2016-05-11 2016-08-31 中铁十四局集团第二工程有限公司 Embedded type reinforced concrete combination part mud jacking filling device and construction method
CN105908631B (en) * 2016-05-11 2017-12-19 中铁十四局集团第二工程有限公司 A kind of built-in type steel reinforced concrete joint portion mud jacking filling device and construction method
CN109505259A (en) * 2018-12-25 2019-03-22 北京市政建设集团有限责任公司 A kind of bridge box and beam prestressing force vertical tube grouting method
CN113846569A (en) * 2021-11-01 2021-12-28 重庆交通建设(集团)有限责任公司 Continuous rigid frame segment vertical prestressed pipeline series vacuum pressure grouting method

Similar Documents

Publication Publication Date Title
CN202164545U (en) Vertical prestressing pore canal communicating pipes and mud-jacking pipes
CN101260644B (en) Method of manufacture for simply supported girder box
CN206233596U (en) Building block exterior wall constructional column concrete casting device
CN104790291A (en) Prefabricated type bridge pier column and connecting method thereof
CN205839985U (en) Fabricated shear wall attachment means
CN204644863U (en) A kind of Steel Tubes For Bridge Application performance of concrete column confined construction steel pipe welding bushing pipe device
CN206570955U (en) A kind of prefabricated post single hole provisions for grouting
CN206616469U (en) Presstressed reinforcing steel mud jacking structure
CN204112525U (en) Band perps precast shear wall structure in strong concrete precast frame
CN103485333A (en) Corrugated hollow steel pipe friction pile and construction method thereof
CN209799173U (en) Assembly prefabricated component series sleeve connection structure
CN208763204U (en) A kind of vertical connecting structure of low layer assembled architecture prefabricated panel
CN103216030A (en) Method for splicing and connecting precast reinforced concrete floor slabs within span
CN208534081U (en) A kind of reconstruction structure of old building constructional column
CN201794167U (en) Reinforced concrete composite column with jointing elements
CN105155669A (en) Hidden beam floor constructional column structure and construction method thereof
CN104196023A (en) Precast concrete tubular pile tip with mechanical connection device and using method of precast concrete tubular pile tip
CN102518129B (en) Post pressure-grouting pre-stressed hollow square pile and manufacturing method thereof
CN205242441U (en) Oval contrary shaft of doing of suspension type
CN202247718U (en) Multifunctional corrugated prestressed deformation-resistance roadbed culvert pipe
CN204551897U (en) With the steel framework post of joint type linkage
CN103437349B (en) The construction method of steel concrete perfusion shaped pile
CN207525779U (en) A kind of assembly type pipe gallery pattern foundation pit supporting structure of recycling and structure external mold composite structure
CN204551245U (en) Prefabricated assembled pier column
CN205976532U (en) Sleeve grout connection structure and wall body

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120314

Termination date: 20120726