CN204551245U - Prefabricated assembled pier column - Google Patents

Prefabricated assembled pier column Download PDF

Info

Publication number
CN204551245U
CN204551245U CN201520253464.3U CN201520253464U CN204551245U CN 204551245 U CN204551245 U CN 204551245U CN 201520253464 U CN201520253464 U CN 201520253464U CN 204551245 U CN204551245 U CN 204551245U
Authority
CN
China
Prior art keywords
pier column
hole
precast
reinforcement
precast pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520253464.3U
Other languages
Chinese (zh)
Inventor
黄国斌
周良
查义强
冀振龙
姜海西
沙丽新
闫兴非
朱鹏志
李雪峰
胡方健
张斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Investment Construction Development Co Ltd Of Shanghai Highway
Shanghai Urban Construction Design Research Institute Co ltd
Original Assignee
Investment Construction Development Co Ltd Of Shanghai Highway
Shanghai Urban Construction Design Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Investment Construction Development Co Ltd Of Shanghai Highway, Shanghai Urban Construction Design Research Institute Co ltd filed Critical Investment Construction Development Co Ltd Of Shanghai Highway
Priority to CN201520253464.3U priority Critical patent/CN204551245U/en
Application granted granted Critical
Publication of CN204551245U publication Critical patent/CN204551245U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of prefabricated assembled pier column, at least comprise the precast pier column of the stackable setting of more piece, each saves described precast pier column and is respectively arranged with multiple through hole along its length; The inwall of described through hole is respectively arranged with uneven regular lines; The diameter of described through hole is greater than the diameter of connecting reinforcement; Epoxide-resin glue is provided with between the adjacent face of the described precast pier column that superposition is arranged; Each superposing setting saves the described through hole one_to_one corresponding setting of described precast pier column; Run through respectively in each corresponding described through hole arranged and be provided with described connecting reinforcement; Fill with respectively in the described through hole being provided with described connecting reinforcement and be provided with high-strength slurry.The utility model has that bond strength between precast pier column is good, construction cost is lower, construction speed beneficial effect faster.

Description

Prefabricated assembled pier column
Technical field
The utility model relates to bridge construction technical field, particularly relates to a kind of prefabricated assembled pier column.
Background technology
Compared with cast in situs pier column or overall pier column, assembly pier column have can scale prefabricated, transport and easy for installation, the advantage such as the construction period is short, obtain applying more widely in bridge construction field.
At present, for highly higher precast pier column, prefabricated more piece pier column is carried out assembled mode and connects by usual employing.But this assembled method of attachment often needs embedded bar branch sleeve in pier column prefabricated subsection.Along with the increase of pier column height, the joint number of pier column also needs to increase, and needs the also corresponding increase of pre-buried reinforcing steel bar connecting sleeve tube quantity simultaneously, and the increase of reinforcing steel bar connecting sleeve tube quantity substantially increases the cost manufacturing pier column.On the other hand, the precast assembly mode of embedded bar branch sleeve requires higher to construction precision and grouting quality, to the accurate location between each parts and grouting requirement in assembling construction process, the application of above-mentioned method of attachment is subject to certain restrictions.
Another kind of precast assembly method of attachment relatively more conventional at present, connects in aggregates by the mode wearing prestress wire in the through hole that column is reserved by column prefabricated subsection.As Chinese patent CN102363946A discloses a kind of precast assembling upright post supporting platform structure and assembled positioning process thereof, column is made up of some prefabricated stand column section assemblings, positioning through hole is provided with in each prefabricated stand column sections, the connection plane of cushion cap is fixedly installed prestressing force parts, prestressing force parts are double makees keeper, runs through and is arranged in positioning through hole.This method of attachment overcomes in first kind of way the problem needing embedded bar branch sleeve, but owing to needing to arrange prestress wire in the through hole of column prefabricated subsection, relative to traditional cast-in-situ concrete bridge pier, the cost of the pier column of this method of attachment wants high a lot.In addition, need carry out the operation such as stretch-draw, grouting to preload tension wire, complicated construction technique during site operation, the engineering time is longer.
Therefore, those skilled in the art need badly in a kind of precast pier column of research joint and do not need to arrange that prestress wire, construction cost are lower, construction speed prefabricated assembled pier column faster.
Utility model content
Because the above-mentioned defect of prior art, the utility model proposes that a kind of bond strength is good, construction cost is lower, construction speed prefabricated assembled pier column faster.
For achieving the above object, the utility model provides a kind of prefabricated assembled pier column, at least comprises the precast pier column of the stackable setting of more piece, and each saves described precast pier column and is respectively arranged with multiple through hole along its length; The inwall of described through hole is respectively arranged with uneven regular lines; The diameter of described through hole is greater than the diameter of connecting reinforcement; Epoxide-resin glue is provided with between the adjacent face of the described precast pier column that superposition is arranged; Each superposing setting saves the described through hole one_to_one corresponding setting of described precast pier column; Run through respectively in each corresponding described through hole arranged and be provided with described connecting reinforcement; Fill with respectively in the described through hole being provided with described connecting reinforcement and be provided with high-strength slurry.
Preferably, the regular lines of described through-hole wall is corrugated.
Preferably, the diameter of described connecting reinforcement is 28-40mm.
Preferably, described connecting reinforcement is the tendon that many reinforcing bars are formed.
The beneficial effects of the utility model:
Prefabricated assembled pier column of the present utility model, due to not need between contiguous prefabricated pier column embedded bar adapter sleeve, also prestress wire need be set in through hole, only need adopt the through each joint precast pier column of generic connectivity reinforcing bar, both the cost of production of precast pier column had been reduced, additionally reduce due to the workload at the scene spent by tension steel strand, simplify construction technology, accelerate construction speed.
On the other hand, owing to being provided with epoxide-resin glue between each joint precast pier column, the setting of epoxide-resin glue improves the sealing between each joint precast pier column, also improves the durability of pier column simultaneously, extends the application life of pier column.
The method of attachment of prefabricated assembled pier column of the present utility model, by running through the connecting reinforcement be arranged in each joint precast pier column, improve the bond strength between each joint precast pier column, ensure that the intensity of pier column.
Because through-hole wall is provided with concavo-convex regular lines in order, strengthens the bond strength between connecting reinforcement, high-strength slurry and precast pier column, improve the intensity of pier column.
Be described further below with reference to the technique effect of accompanying drawing to design of the present utility model, concrete structure and generation, to understand the purpose of this utility model, characteristic sum effect fully.
Accompanying drawing explanation
Fig. 1 is the main TV structure schematic diagram of the pier column of the utility model one embodiment.
Fig. 2 is the plan structure schematic diagram of precast pier column in Fig. 1.
Fig. 3 is the arrangement of reinforcement section structure schematic diagram of precast pier column in Fig. 1.
Detailed description of the invention
The utility model provides a kind of prefabricated assembled pier column, and in one embodiment, as shown in Figure 1 to Figure 3, this pier column comprises the first precast pier column 1, second precast pier column 5 and the 3rd precast pier column 6 of the stackable setting of three joints.
That often saves precast pier column is respectively arranged with multiple through hole 11 along its length, and the inwall of multiple through hole 11 is respectively arranged with uneven regular lines.In order to reduce the difficulty of processing of through-hole wall rule lines, in the present embodiment, the regular lines of through-hole wall is set to corrugated.Can arrive the bottom of pier column for the ease of the high-strength slurry 4 poured in through hole smoothly, guarantee the intensity of pier column, the diameter of through hole 11 is set to the diameter being greater than connecting reinforcement 3, preferred through-hole diameter about 5mm larger than the diameter of connecting reinforcement.
As shown in Figure 1, formed because pier column is superposed by the first precast pier column 1, second precast pier column 5 and the 3rd precast pier column 6, in order to strengthen the durability of pier column, between the first precast pier column 1, second precast pier column 5 and the contact surface of the 3rd precast pier column 6, be provided with epoxide-resin glue 2.
When first precast pier column 1, second precast pier column 5 and the superposition of the 3rd precast pier column 6 are placed, should ensure that through hole 11 one_to_one corresponding on it is arranged, so that the plugging of connecting reinforcement 3.
Run through respectively in each corresponding through hole 11 arranged of the first precast pier column 1, second precast pier column 5 that superposition is placed and the 3rd precast pier column 6 and be provided with connecting reinforcement 3, this connecting reinforcement 3 is for having the plain bars of some strength, and the first precast pier column 1, second precast pier column 5 and the 3rd precast pier column connect as one by this connecting reinforcement 3.In order to ensure the intensity of pier column, the diameter of connecting reinforcement is preferably 28-40mm.
In other embodiments, connecting reinforcement also can adopt the tendon be made up of many reinforcing bars, and the external diameter of tendon should meet the intensity of pier column.
As shown in Figure 3, the first precast pier column 1, second precast pier column 5 and the 3rd precast pier column 6 are reinforced concrete member, often save in precast pier column be also respectively arranged with many for strengthen precast pier column joint in reinforcing bar 12.
As shown in Figure 2, in order to strengthen the intensity of pier column further, all filling with in the multiple through holes 11 being provided with connecting reinforcement 3 and being provided with high-strength slurry 4.Diameter due to through hole is set to the diameter being greater than connecting reinforcement, and high-strength slurry can flow into the bottom of pier column from the top of pier column, improve the bond strength between each joint precast pier column, ensure that the intensity of pier column.
Prefabricated assembled pier column of the present utility model, due to not need between contiguous prefabricated pier column embedded bar adapter sleeve, also prestress wire need be set in through hole, adopt the through each joint precast pier column of generic connectivity reinforcing bar, both the cost of production of precast pier column had been reduced, additionally reduce due to the workload at the scene spent by tension steel strand, simplify construction technology, accelerate construction speed.
On the other hand, owing to being provided with epoxide-resin glue between each joint precast pier column, the setting of epoxide-resin glue improves the durability of pier column, extends the application life of pier column.
Because through-hole wall is provided with concavo-convex regular lines in order, strengthens the bond strength between connecting reinforcement, high-strength slurry and precast pier column, improve the intensity of pier column.
The utility model also proposed a kind of method of attachment of prefabricated assembled pier column.In one embodiment, comprise the steps:
Step one, processes the first precast pier column 1, second precast pier column 5 and the 3rd precast pier column 6, and reserves multiple through hole 11 at the length direction of each joint precast pier column, and the inwall of each through hole 11 arranges uneven regular lines respectively.In order to reduce the difficulty of processing of through-hole wall rule lines, in the present embodiment, the regular lines of through-hole wall is processed as corrugated.Can arrive the bottom of pier column smoothly for the ease of the high-strength slurry poured in through hole, the diameter of through hole is processed as the diameter being greater than connecting reinforcement and is about 5mm.
Wherein, each joint precast pier column is reinforced concrete member, often save in precast pier column be respectively arranged with many for strengthen precast pier column joint in reinforcing bar 12.It is prefabricated that precast pier column preferably completes batch at precasting yard according to designing requirement in advance, and be transported to job site and install.
Step 2, the installation of precast pier column, first the first precast pier column 1 is fixed on ground precalculated position, and epoxide-resin glue 2 is applied on the upper surface of the first precast pier column 1, then the second precast pier column 5 is arranged on the upper surface of the first precast pier column 1, and makes the through hole on the second precast pier column 5 and the through hole one_to_one corresponding on the first precast pier column 1.Above-mentioned this setup, both ensure that the durability of pier column, was also convenient to plugging of later stage connecting reinforcement simultaneously.
Step 3, repeats above-mentioned step, is arranged at by the 3rd precast pier column 6 on the upper surface of the second precast pier column 5.
Step 4, inserted by the through hole of many connecting reinforcements 3 respectively from the 3rd precast pier column 6 being positioned at pier column topmost, connecting reinforcement 3 runs through the through hole in the first precast pier column 5 and the second precast pier column 6 being arranged at its underpart.In order to ensure the intensity of pier column, the diameter of connecting reinforcement is preferably 28-40mm.
Step 5, establishes high-strength slurry 4 toward interior filling of each through hole 11 being inserted with connecting reinforcement 3.Diameter due to through hole 11 is greater than the diameter of connecting reinforcement 3, and high-strength slurry 4 can flow into the bottom of pier column from the top of the 3rd precast pier column 6, be full of the gap between through hole 11 and connecting reinforcement 3, thus is connected as one by three joint precast pier columns.
In other embodiments, connecting reinforcement also can adopt the tendon be made up of many reinforcing bars.The external diameter of tendon should meet the intensity of pier column.
The method of attachment of prefabricated assembled pier column of the present utility model, by running through the connecting reinforcement be arranged in each joint precast pier column, improve the bond strength between each joint precast pier column, ensure that the intensity of pier column.
Due to not need between precast pier column sections embedded bar adapter sleeve, also prestress wire need be set in through hole, only need to adopt the through each joint precast pier column of generic connectivity reinforcing bar, both the cost of production of precast pier column had been reduced, additionally reduce due to the workload at the scene spent by tension steel strand, simplify construction technology, accelerate construction speed.
On the other hand, owing to being provided with epoxide-resin glue between each joint precast pier column, the setting of epoxide-resin glue improves the sealing between each joint precast pier column, also improves the durability of pier column simultaneously, extends the application life of pier column.
Because through-hole wall is provided with concavo-convex regular lines in order, strengthens the bond strength between connecting reinforcement, high-strength slurry and precast pier column, improve the intensity of pier column.
More than describe preferred embodiment of the present utility model in detail.Should be appreciated that those of ordinary skill in the art just can make many modifications and variations according to design of the present utility model without the need to creative work.Therefore, all technician in the art according to design of the present utility model on the basis of existing technology by the available technical scheme of logical analysis, reasoning, or a limited experiment, all should by the determined protection domain of claims.

Claims (4)

1. a prefabricated assembled pier column, at least comprises the precast pier column of the stackable setting of more piece, it is characterized in that, each saves described precast pier column and is respectively arranged with multiple through hole along its length; The inwall of described through hole is respectively arranged with uneven regular lines; The diameter of described through hole is greater than the diameter of connecting reinforcement; Epoxide-resin glue is provided with between the adjacent face of the described precast pier column that superposition is arranged; Each superposing setting saves the described through hole one_to_one corresponding setting of described precast pier column; Run through respectively in each corresponding described through hole arranged and be provided with described connecting reinforcement; Fill with respectively in the described through hole being provided with described connecting reinforcement and be provided with high-strength slurry.
2. prefabricated assembled pier column as claimed in claim 1, is characterized in that, the regular lines of described through-hole wall is corrugated.
3. prefabricated assembled pier column as claimed in claim 2, is characterized in that, the diameter of described connecting reinforcement is 28-40mm.
4. prefabricated assembled pier column as claimed in claim 2, is characterized in that, described connecting reinforcement is the tendon that many reinforcing bars are formed.
CN201520253464.3U 2015-04-22 2015-04-22 Prefabricated assembled pier column Active CN204551245U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520253464.3U CN204551245U (en) 2015-04-22 2015-04-22 Prefabricated assembled pier column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520253464.3U CN204551245U (en) 2015-04-22 2015-04-22 Prefabricated assembled pier column

Publications (1)

Publication Number Publication Date
CN204551245U true CN204551245U (en) 2015-08-12

Family

ID=53826378

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520253464.3U Active CN204551245U (en) 2015-04-22 2015-04-22 Prefabricated assembled pier column

Country Status (1)

Country Link
CN (1) CN204551245U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790291A (en) * 2015-04-22 2015-07-22 上海市城市建设设计研究总院 Prefabricated type bridge pier column and connecting method thereof
CN105951600A (en) * 2016-06-07 2016-09-21 上海公路投资建设发展有限公司 Splicing and positioning method and device for prefabricated stand column and bearing platform

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790291A (en) * 2015-04-22 2015-07-22 上海市城市建设设计研究总院 Prefabricated type bridge pier column and connecting method thereof
CN105951600A (en) * 2016-06-07 2016-09-21 上海公路投资建设发展有限公司 Splicing and positioning method and device for prefabricated stand column and bearing platform

Similar Documents

Publication Publication Date Title
CN104790291A (en) Prefabricated type bridge pier column and connecting method thereof
CN104746422B (en) A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method
CN101831875A (en) Precast assembly process of prestressed concrete cylindrical hollow pier
CN106381925A (en) Prefabricated reinforced concrete column and column splice joint with sleeves
CN106592440B (en) A kind of construction method of prefabricated subsection type bridge pier
CN202000251U (en) Cylindrical hollow prefabricated prestressed concrete pier structure
CN103850363B (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN103452350B (en) Assembling electronic workshop and construction method thereof
CN105507470A (en) Periphery-overlapped integral fabricated floor and construction method thereof
CN204551245U (en) Prefabricated assembled pier column
CN208379425U (en) A kind of assembly concrete pier column structure
CN103603435B (en) A kind of assembly concrete antidetonation beam column frame and construction method thereof
CN105735466A (en) Prefabricated wall column one-segment type steel rib connection structure and method
CN206844316U (en) A kind of assembled steel reinforced concrete column with well and post splicing node
CN105369987A (en) Steel bar lap joint structure containing FRP constraint ring
CN206352391U (en) Socket joint type key slot type Quick Release support system
CN105484151A (en) Structure for enhancing connection among prefabricated concrete segments and construction method thereof
CN109267489B (en) Construction method for cable-stayed bridge cable tower anchoring area
CN106968381A (en) With the prefabricated shear wall and overlapping plate node of Combined grouting sleeve connection
CN202164545U (en) Vertical prestressing pore canal communicating pipes and mud-jacking pipes
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN109403366A (en) A kind of assembly concrete-filled steel tube pile foundation and its construction method
CN206408515U (en) Precast pier section assembling structure
CN103938533B (en) The construction method of Simply supported non-uniform structure
CN205369005U (en) Joint construction of annular cross -section prefabricating bridge pier and cushion cap

Legal Events