CN202121254U - Cross arm lateral side clamp of double-fission double-suspension insulator string for erecting tower - Google Patents

Cross arm lateral side clamp of double-fission double-suspension insulator string for erecting tower Download PDF

Info

Publication number
CN202121254U
CN202121254U CN201120167782XU CN201120167782U CN202121254U CN 202121254 U CN202121254 U CN 202121254U CN 201120167782X U CN201120167782X U CN 201120167782XU CN 201120167782 U CN201120167782 U CN 201120167782U CN 202121254 U CN202121254 U CN 202121254U
Authority
CN
China
Prior art keywords
cross
jig
arm
screw mandrel
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201120167782XU
Other languages
Chinese (zh)
Inventor
陈永平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhangzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Original Assignee
Zhangzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhangzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd filed Critical Zhangzhou Power Supply Co of State Grid Fujian Electric Power Co Ltd
Priority to CN201120167782XU priority Critical patent/CN202121254U/en
Application granted granted Critical
Publication of CN202121254U publication Critical patent/CN202121254U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model discloses a cross arm lateral side clamp of a double-fission double-suspension insulator string for erecting a tower, which comprises two symmetrically arranged clamp bodies, wherein each clamp body comprises a lead screw device, a clamp cross arm module, an aluminum alloy hook head, and a connection piece arranged between the aluminum alloy hook head and a lead screw. A clamping groove, a connection hole and a through hole which is used for installing the lead screw are clamped in the cross arm and arranged on the clamp cross arm module, and the through hole used for installing the lead screw arranged on the clamp cross arm module is in a T-shaped structure. A positioning steering shaft is arranged on the lead screw, vertical to the lead screw, and clamped in the T-shaped through hole on the clamp cross arm module. The cross arm lateral side clamp has the advantages of not being restricted by structural limitation of the cross arm of an iron tower, and enabling clamping installation to be performed smoothly, thereby being flexible and convenient to install and wide in application range.

Description

The two suspension insulators of two divisions set up the cross-arm side jig of shaft tower
Technical field
The utility model relates to the two suspension insulator erection mode forthright shaft towers of a kind of two division and uses jig, and the two suspension insulators of particularly a kind of two divisions set up the cross-arm side jig of shaft tower.
Background technology
At at present 220kV and above transmission line, because transmission capacity is bigger, in order to suppress corona discharge and to reduce line reactance, that improves circuit send electric energy power, and newly-increased 220kV transmission line majority has adopted the two suspension insulator erection modes of double bundle conductor.But brought some stubborn problems also for thus the live line working of circuit: with 220GUZ31 drum type tower is example; Because 220GUZ31 drum type tower is two wiring on the same tower modes of returning; This sections tower is from the general safety structural design, and the cross-arm width is short, and cross-arm side shrouding area is big.If adopt common jig operation, stopped by two insulator string strings under the jig, can't the insulation pull-rod that have gib head be connected with the cross-arm jig; If adopt common side jig, because cross-arm side shrouding area is big, the cross-arm jig can only be installed in and the lead position on same vertical line not, and the insulation arm-tie also can't be connected with jig, so can't realize the charged for replacement insulator operation of this sections tower.
The utility model content
The purpose of the utility model is that the weak point according to prior art provides a kind of two suspension insulators of two divisions that do not receive iron tower cross-arm structure limitations restrict to set up the cross-arm side jig of shaft tower.
The two suspension insulators of a kind of two division set up the cross-arm side jig of shaft tower, comprise two jig body of two symmetric arrays, are connected with jockey between two jig body; Each jig body comprises lead screw device; Jig cross-arm module, aluminium alloy gib head, the connector between aluminium alloy gib head and the screw mandrel; Its structural feature is: described jig cross-arm module is provided with the draw-in groove that snaps in cross-arm; On jig cross-arm module, also be provided with the connecting hole that is used for fixing the jockey between two jig body, on jig cross-arm module, also be provided for installing the through hole of screw mandrel, the degree of depth of described draw-in groove trend, with the connecting hole of jockey, and the length direction that the through hole of screw mandrel is installed parallel; The through hole that being used to of being provided with on the described jig cross-arm module installed screw mandrel is a kind of T shape structure; Screw mandrel is provided with the location steering spindle, and described location steering spindle and screw mandrel are perpendicular, and positioning rotating shaft is stuck in the T shape through hole on the jig cross-arm module.
The two suspension insulators of two divisions of this structure set up the cross-arm side jig of shaft tower; Owing on jig cross-arm module, be provided with this T shape through hole; And the location steering spindle is set on screw mandrel, general side jig can only be installed in directly over the lead with the same vertical line of lead, receives force direction can only receive pulling force vertically downward; After the new jig Design Orientation steering spindle; The side jig can be done the vertical wires axis direction and do certain angle swing, thereby it is stressed to make screw mandrel tilt to the direction of lead, thereby makes jig not receive the restriction of iron tower cross-arm structure.
Described location steering spindle or for to constitute by a bearing pin that passes screw mandrel, or the location steering spindle that can be placed on the screw mandrel by cross constitutes.
Jockey between two jig body is a kind of length-adjustable connecting device.
Described length-adjustable connecting device is served as reasons above that and to be constituted along two pull bars of the jack in a row of its axial distribution or arm-tie, through two pull bars or arm-tie are connected the length that just can realize regulating jockey with respect to different jacks.
Described length-adjustable connecting device is for to be made up of the nut lead screw device.
The nut lead screw device of described adjustable in length includes one section hollow pipe, and the inner chamber at the hollow pipe two ends is provided with screw thread, is provided with two screw mandrels that are complementary with hollow pipe at the two ends of hollow pipe inner chamber, also is provided with the handle that is used to handle on the hollow pipe.
When shaking handle, can realize stretching and contract of the relative hollow pipe of two screw mandrels.
Connector between aluminium alloy gib head and the screw mandrel is articulated on the insulation arm-tie for insulation arm-tie, aluminium alloy gib head.
The aluminium alloy gib head is articulated on the insulation arm-tie; So just can avoid when the double bundle conductor of below and cross-arm jig installation site, top not on same vertical line; The shearing force that the insulation arm-tie will bear double bundle conductor; And if cause continue to tighten up the jig screw mandrel, the suffered shearing force of insulation arm-tie will continue increase, rupture because of shearing force is excessive easily.
Connector between aluminium alloy gib head and the screw mandrel or for the insulation jack line, hang a pulley in the lower end of screw mandrel, the insulation jack line hang on the pulley, then again with the aluminium alloy gib head hang on the insulation jack line on.
Adopt insulation jack line suspension aluminium alloy gib head, and the jack line that will insulate hangs on the pulley that is installed on the screw mandrel, so just can be as required adjustment voluntarily, thereby make jig be in good stress.
The connecting hole that is used for fixing the jockey between two jig body that on jig cross-arm module, is provided with is a screwed hole.
In sum, the advantage of the utility model is:
The two suspension insulators of two divisions of the utility model set up the cross-arm side jig of shaft tower; Can make side jig screw mandrel receive force direction perpendicular to traverse shaft to; The design that has added soft insulation jack line makes stressed connection of safety between jig and the lead; This kind side jig does not receive iron tower cross-arm structure limitations restrict, can carry out jig smoothly and install.Have convenient and flexible installation, have widely applicable advantage.
Description of drawings
Fig. 1 is that the two suspension insulators of the two divisions of the utility model set up the structural representation of the cross-arm side jig body of shaft tower.
Fig. 2 is the A place enlarged drawing of Fig. 1.
Fig. 3 is the structural representation behind the cross-arm side jig body swing certain angle.
Fig. 4 is the structural representation that two jig body link together.
Location steering spindle 12 jig cross-arm modules 121 draw-in grooves 122 connecting holes 123 of label declaration 1 jig body 11 lead screw device 111 screw mandrels 1111 screw mandrels are installed through hole 13 aluminium alloy gib heads 2 jockeys 3 connectors 4 pulleys of screw mandrel.
Specific embodiment
Below in conjunction with embodiment the utility model is done and to be further described.
Most preferred embodiment:
A kind of two suspension insulators of two divisions shown in Fig. 1-4 set up the cross-arm side jig of shaft tower, comprise between jig body 1, two jig body of two symmetric arrays being connected with jockey 2; Each jig body comprises lead screw device 11; Jig cross-arm module 12, aluminium alloy gib head 13, the connector 3 between aluminium alloy gib head 13 and the screw mandrel 111; Described jig cross-arm module 12 is provided with the draw-in groove 121 that snaps in cross-arm; On jig cross-arm module, also be provided with the connecting hole 122 that is used for fixing the jockey between two jig body, on jig cross-arm module, also be provided for installing the through hole 123 of screw mandrel, the degree of depth of described draw-in groove trend, with the connecting hole of jockey, and the length direction that the through hole of screw mandrel is installed parallel; The through hole that being used to of being provided with on the described jig cross-arm module installed screw mandrel is a kind of T shape structure; Screw mandrel is provided with location steering spindle 1111, and described location steering spindle and screw mandrel are perpendicular, and positioning rotating shaft is stuck in the T shape through hole on the jig cross-arm module.Described location steering spindle is to be made up of the location steering spindle that cross can be placed on the screw mandrel.Jockey between two jig body is a kind of length-adjustable connecting device.Described length-adjustable connecting device is for to be made up of the nut lead screw device.The nut lead screw device of described adjustable in length includes one section hollow pipe, and the inner chamber at the hollow pipe two ends is provided with screw thread, is provided with two screw mandrels that are complementary with hollow pipe at the two ends of hollow pipe inner chamber, also is provided with the handle that is used to handle on the hollow pipe.Connector 3 between aluminium alloy gib head and the screw mandrel hangs a pulley 4 for the insulation jack line in the lower end of screw mandrel, the insulation jack line hangs on the pulley, then the aluminium alloy gib head is hung on the insulation jack line again.
It is identical with prior art that present embodiment is not stated part.

Claims (8)

1. one kind pair is divided the cross-arm side jig that two suspension insulators set up shaft tower, comprises two jig body of two symmetric arrays, is connected with jockey between two jig body; Each jig body comprises lead screw device; Jig cross-arm module, aluminium alloy gib head, the connector between aluminium alloy gib head and the screw mandrel; It is characterized in that: described jig cross-arm module is provided with the draw-in groove that snaps in cross-arm; On jig cross-arm module, also be provided with the connecting hole that is used for fixing the jockey between two jig body, on jig cross-arm module, also be provided for installing the through hole of screw mandrel, the degree of depth of described draw-in groove trend, with the connecting hole of jockey, and the length direction that the through hole of screw mandrel is installed parallel; The through hole that being used to of being provided with on the described jig cross-arm module installed screw mandrel is a kind of T shape structure; Screw mandrel is provided with the location steering spindle, and described location steering spindle and screw mandrel are perpendicular, and positioning rotating shaft is stuck in the T shape through hole on the jig cross-arm module.
2. the two suspension insulators of two division according to claim 1 set up the cross-arm side jig of shaft tower; It is characterized in that: described location steering spindle or for to constitute by a bearing pin that passes screw mandrel, or the location steering spindle that can be placed on the screw mandrel by cross constitutes.
3. the two suspension insulators of two division according to claim 2 set up the cross-arm side jig of shaft tower, and it is characterized in that: the jockey between two jig body is a kind of length-adjustable connecting device.
4. the two suspension insulators of two division according to claim 3 set up the cross-arm side jig of shaft tower, and it is characterized in that: described length-adjustable connecting device is for to be made up of the nut lead screw device.
5. the two suspension insulators of two division according to claim 4 set up the cross-arm side jig of shaft tower; It is characterized in that: the nut lead screw device of described adjustable in length includes one section hollow pipe; Inner chamber at the hollow pipe two ends is provided with screw thread; Be provided with two screw mandrels that are complementary with hollow pipe at the two ends of hollow pipe inner chamber, also be provided with the handle that is used to handle on the hollow pipe.
6. the two suspension insulators of two division according to claim 5 set up the cross-arm side jig of shaft tower, it is characterized in that: the connector between aluminium alloy gib head and the screw mandrel is articulated on the insulation arm-tie for insulation arm-tie, aluminium alloy gib head.
7. the two suspension insulators of two division according to claim 5 set up the cross-arm side jig of shaft tower; It is characterized in that: the connector between aluminium alloy gib head and the screw mandrel or for the insulation jack line; Hang a pulley in the lower end of screw mandrel; The insulation jack line hangs on the pulley, then the aluminium alloy gib head is hung on the insulation jack line again.
8. according to claim 6 or 7 described two cross-arm side jigs that two suspension insulators set up shaft tower that divide, it is characterized in that: the connecting hole that is used for fixing the jockey between two jig body that on jig cross-arm module, is provided with is a screwed hole.
CN201120167782XU 2011-05-24 2011-05-24 Cross arm lateral side clamp of double-fission double-suspension insulator string for erecting tower Expired - Fee Related CN202121254U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201120167782XU CN202121254U (en) 2011-05-24 2011-05-24 Cross arm lateral side clamp of double-fission double-suspension insulator string for erecting tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201120167782XU CN202121254U (en) 2011-05-24 2011-05-24 Cross arm lateral side clamp of double-fission double-suspension insulator string for erecting tower

Publications (1)

Publication Number Publication Date
CN202121254U true CN202121254U (en) 2012-01-18

Family

ID=45462291

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201120167782XU Expired - Fee Related CN202121254U (en) 2011-05-24 2011-05-24 Cross arm lateral side clamp of double-fission double-suspension insulator string for erecting tower

Country Status (1)

Country Link
CN (1) CN202121254U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102611036A (en) * 2012-03-15 2012-07-25 福建省电力有限公司三明电业局 Spacing-adjustable cross arm fixator
CN102623927A (en) * 2012-03-31 2012-08-01 湖南省电力公司株洲电业局 Tool and method for charged replacement of multi-circuit double-split conductor insulators of 200kV line
CN103715628A (en) * 2013-12-16 2014-04-09 国家电网公司 Clamp for charged replacement of tangent tower insulators
CN103746313A (en) * 2013-12-16 2014-04-23 国家电网公司 Protection strengthening type wing-shaped fixture
CN105186366A (en) * 2015-09-21 2015-12-23 云南电网有限责任公司普洱供电局 Vertical double-hanging clamp
CN105186374A (en) * 2015-09-29 2015-12-23 国网浙江省电力公司金华供电公司 Line raising structure and universal support on 500kV power transmission line tower
CN105261993A (en) * 2015-09-30 2016-01-20 国家电网公司 Power transmission line aerial work lifting platform
CN108756435A (en) * 2018-07-21 2018-11-06 国家电网有限公司 Cross-arm locator
CN109580212A (en) * 2019-01-25 2019-04-05 广东电网有限责任公司 A kind of cross arm lateral side clamp tension test tool

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102611036A (en) * 2012-03-15 2012-07-25 福建省电力有限公司三明电业局 Spacing-adjustable cross arm fixator
CN102623927A (en) * 2012-03-31 2012-08-01 湖南省电力公司株洲电业局 Tool and method for charged replacement of multi-circuit double-split conductor insulators of 200kV line
CN102623927B (en) * 2012-03-31 2015-09-16 湖南省电力公司株洲电业局 Charged for replacement 220kV circuit multiloop double bundle conductor insulator tool and method
CN103715628B (en) * 2013-12-16 2017-01-11 国家电网公司 Clamp for charged replacement of tangent tower insulators
CN103715628A (en) * 2013-12-16 2014-04-09 国家电网公司 Clamp for charged replacement of tangent tower insulators
CN103746313A (en) * 2013-12-16 2014-04-23 国家电网公司 Protection strengthening type wing-shaped fixture
CN105186366A (en) * 2015-09-21 2015-12-23 云南电网有限责任公司普洱供电局 Vertical double-hanging clamp
CN105186374A (en) * 2015-09-29 2015-12-23 国网浙江省电力公司金华供电公司 Line raising structure and universal support on 500kV power transmission line tower
CN105261993A (en) * 2015-09-30 2016-01-20 国家电网公司 Power transmission line aerial work lifting platform
CN105261993B (en) * 2015-09-30 2019-02-26 国家电网公司 Transmission line of electricity lifting highrise operation platform
CN108756435A (en) * 2018-07-21 2018-11-06 国家电网有限公司 Cross-arm locator
CN109580212A (en) * 2019-01-25 2019-04-05 广东电网有限责任公司 A kind of cross arm lateral side clamp tension test tool
CN109580212B (en) * 2019-01-25 2024-02-13 广东电网有限责任公司 Cross arm side fixture tensile test instrument

Similar Documents

Publication Publication Date Title
CN202121254U (en) Cross arm lateral side clamp of double-fission double-suspension insulator string for erecting tower
CN106930594A (en) A kind of insulator crossarm and power tower
CN102694284A (en) Grounding wire clamp with universal joint
CN204885990U (en) Transmission line yoke plate hoisting device
CN203732572U (en) Telescopic high-altitude wire clamp
CN203747299U (en) Mountable and dismountable dual-purpose airfoil-profile clamping device
CN208142787U (en) Aluminium alloy aerial insulated cable fixes device
CN103779809B (en) The two oidiospore wire pitch operational method of charged adjustment
CN203491604U (en) High-voltage tension resistant insulator string auxiliary installation device
CN202260340U (en) Power distribution network overhead line insulation tower head hoisting tool
CN211239257U (en) Drainage line pair bracing strut convenient to installation
CN103606849B (en) Transmission tower multiple fission conductor live line working lifting device and special mould clamp thereof
CN202363811U (en) Cross arm clamping device for replacing insulator of direct-current 500kv straight-line string
CN211088959U (en) Distribution network uninterrupted operation integrated insulated wiring device
CN103762519B (en) A kind of dual-purpose wing type clamp apparatus of self-mountable & dismountuble
CN107425466A (en) Wire lifts insulating support and its application method
CN202423961U (en) Triangular hook for leads
CN111682450A (en) Universal clamp for live replacement of strain duplex insulator string and operation method
CN202423960U (en) Electrified insulator fastening tool
CN201473241U (en) Hoisting tool for overhead lines of power distribution network
CN221448049U (en) Strain clamp
CN214942960U (en) Tower pole body
CN220401395U (en) Cable support
CN219329597U (en) Double-split suspension clamp
CN218335017U (en) Ground wire ice-melting wiring device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120118

Termination date: 20180524

CF01 Termination of patent right due to non-payment of annual fee