CN202117050U - Bearing foundation pile for marine large wind power generator and tower - Google Patents
Bearing foundation pile for marine large wind power generator and tower Download PDFInfo
- Publication number
- CN202117050U CN202117050U CN2011201935821U CN201120193582U CN202117050U CN 202117050 U CN202117050 U CN 202117050U CN 2011201935821 U CN2011201935821 U CN 2011201935821U CN 201120193582 U CN201120193582 U CN 201120193582U CN 202117050 U CN202117050 U CN 202117050U
- Authority
- CN
- China
- Prior art keywords
- pile
- branch
- stake
- bearing foundation
- load
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
A bearing foundation pile for a marine large wind power generator and a tower comprises a main pile, branch piles and inner piles. Symmetric inclined downward branch pile holes are distributed on corresponding lateral walls of the tubular main pile with a conical tip at the top end from bottom to top, the branch pile holes on the adjacent lateral walls are equidistant, tail ends in the symmetric branch pile holes are folded into the branch piles with V-shaped wedge grooves in a central hole of the tubular main pile, the inner piles with wedge top ends are arranged on the branch piles with the V-shaped wedge grooves folded in the central hole of the main pile, the inner piles are matched with the V-shaped wedge grooves formed by folding the tail ends of the branch piles and a tubular hole of the main pile, and a V-shaped wedge groove at the tail end of each inner pile is matched with adjacent sides and the wedge top end of the inner pile on the upper branch pile. The bearing foundation pile has the advantages that the bearing capacity of the foundation pile is improved drastically, and the bearing foundation pile is simple in structure and convenient in popularization and application.
Description
Technical field
The utility model relates to a kind of the load-bearing foundation pile that is used for marine large-scale wind driven generator and pylon, especially load-bearing foundation pile and goes into foundation pile pile body side behind the ground, overhanging a plurality of stakes go into ground branch load-bearing foundation pile.
Background technology
Large-scale Wind Turbines; Powerful blower fan group such as 3.6MW; Only the unit weight of generator adds three huge paddles and supports the towering pylon of large-scale wind driven generator just more than 300 ton, and the weight of whole Large-scale Wind Turbines is more than 500 tons.These weight are all carried by several square metres of areas of pylon bottom; So the load-bearing foundation pile of Large-scale Wind Turbines will carry very large overweight blower fan and pylon; Just must strengthen the quantity of going into the ground degree of depth or increase foundation pile of foundation pile; Support in the hope of the enough big frictional force of the support that obtains batholith or pile body top layer and basal layer; The load-bearing foundation pile of marine large-scale wind driven generator and pylon is except the gravity that will carry vertical direction, and in the time of also will carrying the wind-driven generator duty, the wind-force of horizontal direction passes to the lateral force of load-bearing foundation pile through generator, pylon.When this lateral force was worked owing to blower fan, seasonal wind direction changed, and the lateral force of generation is that 360 degree are comprehensive variable.Marine large-scale wind driven generator addressing generally will be considered wind energy grade, transportation installation, maintenance maintenance, the transmission of electricity transformation each economic target balance of wind field.Mostly be chosen in five kilometers on bank off sea with interior inshore, and the sanidal sea bed in inshore seabed basically all to be the silt alluvial form, supporting capacity is limited; Sea bed silt sediment deposit thickness can reach several one hundred meter; Select foundation pile to arrive at the batholith layer by the batholith load-bearing, this very uneconomical difficulty of construction is also very big, by the load-bearing basic norm of routine; Marine large-scale wind driven generator and pylon are the bearing platform supportings that is held up by a plurality of pile bodies of squeezing into the seabed.The frictional force that this bearing platform will have abundant stake and silt sediment deposit to produce is carried the gravity of vertical direction, also will have enough big area to carry lateral force.So the load-bearing foundation pile of marine large-scale wind driven generator and pylon is in wind power generating set is built, no matter be that duration or cost institute accounting part are all very big.
Summary of the invention
The utility model technical problem to be solved is exactly in order to overcome the defective that above-mentioned prior art exists, and a kind of load-bearing foundation pile and job practices thereof that can increase substantially the marine large-scale wind driven generator and the pylon of bearing capacity is provided.
The utility model can be realized through following technical scheme down.The load-bearing foundation pile of marine large-scale wind driven generator and pylon comprises king pile, branch stake and interior stake; On the corresponding sidewall of the tubulose king pile of apex cone point, the branch stake hole of the symmetry that distributes from bottom to top, branch stake hole is tilted to down; The branch stake hole equidistance of adjacent wall; In the branch stake hole of symmetry, put tail end and in tubulose king pile mesopore, close up the branch stake of carving groove for V-arrangement, the V-type of closing up in the king pile mesopore is carved in the branch stake of groove; That puts that the V-arrangement that closes up with branch stake tail end carves that groove and king pile cannulated match carves interior of shape top; An interior stake tail end is that V-arrangement is carved groove, and the V-arrangement of interior stake tail end is carved groove and adjacent side, and the interior stake in the last stake is carved the shape top and matched.Described king pile is that the segmentation of tubulose pile body connects; The tubulose pile body pipe wall thickness of described king pile is the 1/2=1/4 of tubulose pile body radius; Described tubulose king pile cross section is square; Described branch stake top is the single face tooth shape; Described branch stake center line and king pile center line angle are acute angle;
,
The load-bearing foundation pile of marine large-scale wind driven generator and pylon in the selected position that wind power generating set is installed, will be squeezed into the seabed with the king pile of awl point with piling machine; The interior configuration of a king pile stake, interior stake owing to the king pile length that need squeeze into the seabed is very long, is convenient manufacturing, transportation, installs, construct; The tubulose pile body of king pile is segmentation manufacturing and configuration branch stake, interior stake, and after the king pile location of band awl point was squeezed into, the tubulose king pile was connected with the king pile concentricity of band awl point on the water; Continuation is squeezed into the seabed with piling machine with pile body, reaches projected depth until the pile body of continuous connection, in the hiding king pile of branch stake this moment; In the [of tubulose king pile, squeeze into the push rod that matches with the pore aperture, the interior stake in the tubulose king pile pore is under the downward pushing of push rod, and interior stake is carved the shape top and tail end is closed up for the branch stake of V-shaped groove released to both sides; Stretch out king pile and survey wall outward, interior stake continues another side of pushing downwards under the downward pushing of push rod; It is the interior stake on the V-shaped groove that next stake tail end closes up, and a stake of another side is released to both sides, stretches out king pile and surveys wall outward; Push rod downwards all pushes out king pile with the branch stake of disposing in the tubulose king pile step by step and surveys wall outward, makes king pile sidewall behind the ground stretch out the branch stake of many group symmetries, the surface area of branch stake having increased load-bearing foundation pile and the area of carrying normal pressure outward; Can make the load-bearing foundation pile increase substantially bearing capacity; Thereby under equal load-up condition, compare with traditional load-bearing foundation pile, that can reduce the quantity of foundation pile significantly or reduce foundation pile goes into the ground degree of depth.
The marine large-scale wind driven generator of the utility model and the load-bearing foundation pile of pylon; Building on weak soil layer and sea bed, riverbed; Also can obtain the alternate application of popularity such as the load-bearing foundation pile of house, iron tower, offshore platform, overhead speedway, bridge, harbour; The architecture construction duration on weak soil layer and sea, the riverbed is shortened, and the underground foundation cost reduces significantly.
The marine large-scale wind driven generator of the utility model and the load-bearing foundation pile of pylon, except marine large fan, the supporting body that other are different is all within protection scope of the present invention.
Compared with prior art, this practicality has the following advantages.
After load-bearing foundation pile king pile is driven underground; On the king pile sidewall, squeeze the branch stake of stretching out behind the pile after driving; Reduce pressure and increase pile body surface to amass the frictional force that improves the load-bearing foundation pile except increasing bearing area; Also, basal layer is improved to the friction factor on pile body top layer, can improve the bearing capacity of load-bearing foundation pile greatly because the extruding of branch stake to basal layer arranged.
Simple in structure, easily manufactured, load-bearing foundation pile king pile and traditional foundation pile are as good as, and the piling mode is constant, and construction machinery is identical, and is easy to utilize.
Description of drawings
Fig. 1 is the structural representation of the utility model
Fig. 2 is the side-looking structural representation of Fig. 1
Fig. 3 goes into the structural representation of ground behind the branch for Fig. 1
Fig. 4 goes into the structural representation of ground behind the branch for Fig. 2
The specific embodiment
Combine embodiment that the utility model is described further with reference to the accompanying drawings.
Load-bearing foundation pile like Fig. 1, marine large-scale wind driven generator shown in Figure 2 and pylon is prefabricated the forming of concrete tubulose stake of skeleton by the sharp reinforcing bar of steel awl, is convenient manufacturing, transportation and on-the-spot installation, and the pile body of tubular sections is pressed the ability of vehicle and construction machinery; The standardization segmentation is made, and the prefabricated connector in tubulose stake two ends that segmentation is made is convenient to the job site and the tubulose stake of segmentation is connected into integral body piecemeal with the sharp king pile of steel awl is squeezed into the seabed in the piling process; The load-bearing foundation pile of marine large-scale wind driven generator and pylon comprises king pile 1, branch stake 2, interior stake 3, and king pile is with the concrete member of steel awl point and cage of reinforcement; Mould is built maintenance and is formed, and inlays the branch stake of steel tooth shape top, beveled tail end, the wedge top, carves the interior stake 3 concrete members of flute profile tail end; Build maintenance by mould and form, branch stake hole 4 is set on the king pile two corresponding sidewalls, the center line in branch stake hole and the angle of king pile center line are less than 90 degree; Branch stake hole 4 equidistance of king pile 1 adjacent wall; Inlay steel tooth shape top, the branch stake 2 of beveled tail end places in the branch stake hole, and the top of branch stake is hidden in the branch stake hole; The beveled tail end of two stakes on the corresponding sidewall; In the king pile [, close up for V-arrangement and carve groove, carve on the groove, put the interior stake 3 that top wedge, tail end are carved flute profile at the V-arrangement that branch stake tail end closes up; Carving in groove and the king pile pore of interior stake tail end; Interior wedge top in the last stake matches, and the branch stake hole of the corresponding sidewall of band sharp king pile of awl and tubulose king pile is provided with by said procedure in advance, and presets connector in the end of pile body.The sharp king pile of band awl is squeezed at desired location during piling; The tubulose king pile connects piecemeal to be squeezed into to presetting the degree of depth, in the king pile pore of going into ground, squeezes into the push rod that matches with king pile pore bore; Stake in push rod pushes in the king pile pore; In the V-arrangement that closes up of the wedge top pushing branch stake tail end of stake carve on the groove, make branch stake on the corresponding sidewall at the underground king pile lateral wall that is pushed out, push rod pushes from top to bottom; The branch stake of hiding in the branch stake hole on the king pile is stretched out on the king pile of going into ground from top to bottom one by one, accomplishes the load-bearing foundation pile construction of marine large-scale wind driven generator and pylon.
Claims (5)
1. the load-bearing foundation pile of marine large-scale wind driven generator and pylon comprises king pile, branch stake and interior stake; It is characterized in that; , on the corresponding sidewall of the tubulose king pile of apex cone point, the branch stake hole of the symmetry that distributes from bottom to top; Branch stake hole is tilted to down; The branch stake hole equidistance of adjacent wall in the branch stake hole of symmetry, is put tail end and in tubulose king pile mesopore, is closed up the branch stake of carving groove for V-arrangement; The V-type of closing up in the king pile mesopore is carved in the branch stake of groove; Put the V-arrangement that closes up with branch stake tail end and carve the interior stake of carving the shape top that groove and king pile cannulated match, interior stake tail end is that V-arrangement is carved groove, and the V-arrangement of interior stake tail end is carved in a groove and the last stake interior and carved the shape top and match.
2. the load-bearing foundation pile of marine large-scale wind driven generator as claimed in claim 1 and pylon is characterized in that; The tubulose pile body pipe wall thickness of described king pile is the 1/2=1/4 of tubulose pile body radius.
3. the load-bearing foundation pile of marine large-scale wind driven generator as claimed in claim 1 and pylon is characterized in that; Described king pile is that the segmentation of tubulose pile body connects.
4. the load-bearing foundation pile of marine large-scale wind driven generator as claimed in claim 1 and pylon is characterized in that; Described branch stake top is the single face tooth shape.
5. the load-bearing foundation pile of marine large-scale wind driven generator as claimed in claim 1 and pylon is characterized in that; Described branch stake center line and king pile center line angle are acute angle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011201935821U CN202117050U (en) | 2011-06-10 | 2011-06-10 | Bearing foundation pile for marine large wind power generator and tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011201935821U CN202117050U (en) | 2011-06-10 | 2011-06-10 | Bearing foundation pile for marine large wind power generator and tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202117050U true CN202117050U (en) | 2012-01-18 |
Family
ID=45458124
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011201935821U Expired - Fee Related CN202117050U (en) | 2011-06-10 | 2011-06-10 | Bearing foundation pile for marine large wind power generator and tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202117050U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535508A (en) * | 2012-03-23 | 2012-07-04 | 柳州相光科技有限责任公司 | Tensioning type fixing pile |
CN102817357A (en) * | 2011-06-10 | 2012-12-12 | 上海万德风力发电股份有限公司 | Load-bearing foundation piles for offshore large wind driven generators and towers and construction method of load-bearing foundation piles |
-
2011
- 2011-06-10 CN CN2011201935821U patent/CN202117050U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102817357A (en) * | 2011-06-10 | 2012-12-12 | 上海万德风力发电股份有限公司 | Load-bearing foundation piles for offshore large wind driven generators and towers and construction method of load-bearing foundation piles |
CN102535508A (en) * | 2012-03-23 | 2012-07-04 | 柳州相光科技有限责任公司 | Tensioning type fixing pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11352098B2 (en) | Method of assembling a floating wind turbine platform | |
CN108222049A (en) | A kind of offshore wind farm combined type single-pile foundation and its construction method | |
CN102660950A (en) | Guiding centralizer mechanism for single-pile foundation of offshore wind turbine | |
CN103866817B (en) | Water intake pumping station | |
CN101761090A (en) | Space truss multi-barrel base of offshore wind power unit | |
CN201891126U (en) | Independent pile foundation structure formed by non-uniform piles and bearing platform | |
CN105862907A (en) | Annular combination type super-large diameter offshore wind power single pile foundation and construction technology thereof | |
CN207749529U (en) | A kind of offshore wind farm combined type single-pile foundation | |
CN201502064U (en) | Offshore wind turbine steel structural foundation | |
CN201704699U (en) | Steel structure foundation system of offshore fan | |
CN202117050U (en) | Bearing foundation pile for marine large wind power generator and tower | |
CN105862906A (en) | Offshore wind power plant draught fan single pile foundation and construction method | |
CN102817357A (en) | Load-bearing foundation piles for offshore large wind driven generators and towers and construction method of load-bearing foundation piles | |
CN201593193U (en) | Space truss type multi-bucket foundation of seaborne wind-power generator unit | |
CN202416341U (en) | Steel truss automatically-standing seaborne anemometer tower | |
CN203960942U (en) | Water intake pumping station | |
CN103276743A (en) | Inhaul cable type multi-pile cylindrical foundation composite structure and construction method thereof | |
CN104372806A (en) | Mountain area reinforced concrete hollow-cone flexible wind power foundation and construction method thereof | |
Marsh | Greater role for composites in wind energy | |
CN206221154U (en) | Floating body power station | |
CN106320360A (en) | Prestressed self-locking anchor bolt reinforced variable-diameter single-pile fan foundation under offshore rock foundation condition and construction method thereof | |
CN103276744A (en) | Inhaul cable type multi-pile-aiding single-pile wind power foundation and construction method thereof | |
CN203320541U (en) | Guyed flanged multi-pile and bucket foundation composite structure | |
CN102454169A (en) | Solar photovoltaic power station foundation construction method | |
CN205776312U (en) | Circular combined super-large diameter offshore wind farm single-pile foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120118 Termination date: 20140610 |