CN202109752U - Induction furnace capable of blowing inert gases towards the inside of furnace - Google Patents

Induction furnace capable of blowing inert gases towards the inside of furnace Download PDF

Info

Publication number
CN202109752U
CN202109752U CN2011202015817U CN201120201581U CN202109752U CN 202109752 U CN202109752 U CN 202109752U CN 2011202015817 U CN2011202015817 U CN 2011202015817U CN 201120201581 U CN201120201581 U CN 201120201581U CN 202109752 U CN202109752 U CN 202109752U
Authority
CN
China
Prior art keywords
inert gas
furnace
air brick
stove
induction furnace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011202015817U
Other languages
Chinese (zh)
Inventor
王小运
王建恩
崔荣广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HANDAN DEVELOPMENT DISTRICT XINFU METALLURGY TECHNOLOGY CO LTD
Original Assignee
HANDAN DEVELOPMENT DISTRICT XINFU METALLURGY TECHNOLOGY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HANDAN DEVELOPMENT DISTRICT XINFU METALLURGY TECHNOLOGY CO LTD filed Critical HANDAN DEVELOPMENT DISTRICT XINFU METALLURGY TECHNOLOGY CO LTD
Priority to CN2011202015817U priority Critical patent/CN202109752U/en
Application granted granted Critical
Publication of CN202109752U publication Critical patent/CN202109752U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Furnace Details (AREA)

Abstract

The utility model discloses an induction furnace capable of blowing inert gases towards the inside of the furnace, which comprises a furnace body (1) and a furnace lining (5), wherein 1-5 ventilating bricks (2) are embedded at the bottom of the furnace lining (5); the height of each ventilating brick is equal to or slightly higher than the thickness of the furnace lining at the bottom; inert gas conveying pipe through holes with the same quantity as that of the ventilating bricks (2) are arranged at the bottom of the furnace body (1); an inert gas conveying pipe (3) is arranged at the lower part of the ventilating bricks (2), and extends out of the bottom of the furnace body (1) through the inert gas conveying pipe through holes to be communicated with an inert gas source; and a layer of ventilating lining (6) is tamped at the upper part of the furnace lining at the bottom and the ventilating bricks (2) respectively. The induction furnace capable of blowing inert gases towards the inside of the furnace has the service life up to hundreds of heats.

Description

A kind of can be in stove the induction furnace of blown inert gas
Technical field
The utility model relates to a kind of induction furnace, especially a kind of can be in stove the induction furnace of blown inert gas.
Background technology
For improving steel product quality, steel mill has adopted BOTTOM ARGON BLOWING refining techniques in outer ladle refining of stove and the electric furnace stove mostly in recent years, has received very good effect.Particularly smelt special rolling-mill sections such as high-grade alloy steel, stainless steel, ultra-low-carbon steel, can reach deoxidation, the degassing, decarburization removal non-metallic inclusion, make alloying even through ar blowing refining in the stove.Argon can make product on mechanical property, obviously improve in the stove, and especially plasticity and toughness have solved problems such as splitting gas that steel, casting produce and casting crack, and product quality is obviously improved, and metallographic structure is clearly better.So in electric furnace steel making, list Argon technology in the stove in important process.But electric furnace steel making is long the duration of heat, and every heat was smelted 40-120 minute, the particularly innovation of electric furnace liner material and development, and the life-span in furnace life is brought up to hundreds of stoves.Be difficult to satisfy the life cycle of whole stove labour the service life of the critical component air brick of Argon technology in the stove, and the development of restriction electric furnace smelting special rolling-mill section becomes the focus that expert and insider pay close attention to.Therefore develop reach a kind of service life hundreds of heats can be in stove the induction furnace of blown inert gas, be the present technical issues that need to address.
Summary of the invention
The utility model technical problem to be solved provide a kind of can be in stove the induction furnace of blown inert gas.
The technical scheme that the utility model solves its technical problem is:
A kind of can be in stove the induction furnace of blown inert gas; Comprise body of heater and furnace lining; Be inlaid with 1-5 air brick in the bottom of furnace lining; The height of air brick equals or a little more than the thickness of bottom furnace lining, is provided with the inert gas appendix that equates with air brick quantity in the bottom of body of heater through the hole, is provided with the inert gas appendix in the bottom of air brick; The inert gas appendix is communicated with outward and with the inert gas source of the gas through the furnace bottom that above-mentioned inert gas appendix stretches out body of heater through the hole, and the ventilative wadding of one deck has been made on the top of furnace lining and air brick firm by ramming in the bottom.
The technical scheme that the utility model solves its technical problem can also be:
The utility model is provided with the mica paper bed course between furnace lining and body of heater.
The described air brick of the utility model is made up of spill housing and magnesia, the high alumina matter or the magnalium fire resistant materials that are filled in the spill housing; Described inert gas appendix is connected fixing with the bottom of spill housing and the inert gas appendix is communicated with the inner chamber of spill housing; Top, coat at the refractory material of air brick has one deck paraffin, in the baker process, and melted paraffin wax; Form miniature gas cell, be beneficial to the winding-up of inert gas.
The described air brick of the utility model is diffusion-type, slit-type or compound air brick.
The described paraffin of the utility model is 58# paraffin, and the thickness of paraffin layer is 1-2mm.
The material of the described spill housing of the utility model is pottery or high-melting-point alloy.
The thickness of the described ventilative wadding of the utility model is the 50-250 millimeter.
Compared with prior art, the utlity model has following advantage: air brick is not corroded by molten steel directly, and the long service life of air brick, permeability are stablized, air brick does not stop up, easy to operate, smelting safety, have stopped the bleed-out accident and have taken place.Have the air brick of on induction furnace, installing now and can only use a stove labour, the life-span is only within 100 heats.The utility model is " a kind of gas is blown into the blowing method in the induction furnace ", and its air brick can use 2-3 stove labour, and can reach more than the hundreds of heat service life of air brick.
Description of drawings
Fig. 1 is the structural representation of the utility model.
The specific embodiment
As shown in the figure; A kind of can be in stove the induction furnace of blown inert gas; Comprise body of heater 1 and furnace lining 5, it is characterized in that: be inlaid with 1-5 air brick 2 in the bottom of furnace lining 5, the height of air brick 2 equals or a little more than the thickness of bottom furnace lining; Be provided with the inert gas appendix that equates with air brick 2 quantity in the bottom of body of heater 1 and pass through the hole; Be provided with inert gas appendix 3 in the bottom of air brick 2, inert gas appendix 3 is communicated with outward and with the inert gas source of the gas through the furnace bottom that above-mentioned inert gas appendix stretches out body of heater 1 through the hole, and the ventilative wadding 6 of one deck has been made on the top of furnace lining and air brick 2 firm by ramming in the bottom.
Between furnace lining 5 and body of heater 1, be provided with mica paper bed course 4.
Described air brick 2 is made up of spill housing and magnesia, the high alumina matter or the magnalium fire resistant materials that are filled in the spill housing; Described inert gas appendix is connected fixing with the bottom of spill housing and the inert gas appendix is communicated with the inner chamber of spill housing; Top, coat at the refractory material of air brick 2 has one deck paraffin, in the baker process, and melted paraffin wax; Form miniature gas cell, be beneficial to the winding-up of inert gas.
Described air brick 2 is diffusion-type, slit-type or compound air brick.
Described paraffin is 58# paraffin, and the thickness of paraffin layer is 1-2mm.
The material of described spill housing is pottery or high-melting-point alloy.
The thickness of described ventilative wadding 6 is the 50-250 millimeter.

Claims (7)

  1. One kind can be in stove the induction furnace of blown inert gas; Comprise body of heater (1) and furnace lining (5); It is characterized in that: be inlaid with 1-5 air brick (2) in the bottom of furnace lining (5); The height of air brick (2) equals or a little more than the thickness of bottom furnace lining; Be provided with the inert gas appendix that equates with air brick (2) quantity in the bottom of body of heater (1) and pass through the hole; Be provided with inert gas appendix (3) in the bottom of air brick (2), inert gas appendix (3) is communicated with outward and with the inert gas source of the gas through the furnace bottom that above-mentioned inert gas appendix stretches out body of heater (1) through the hole, and the ventilative wadding (6) of one deck has been made on the top of furnace lining and air brick (2) firm by ramming in the bottom.
  2. 2. according to claim 1 a kind of can be in stove the induction furnace of blown inert gas, it is characterized in that: between furnace lining (5) and body of heater (1), be provided with mica paper bed course (4).
  3. 3. according to claim 1 and 2 a kind of can be in stove the induction furnace of blown inert gas; It is characterized in that: described air brick (2) is made up of spill housing and magnesia, the high alumina matter or the magnalium fire resistant materials that are filled in the spill housing; Described inert gas appendix is connected fixing with the bottom of spill housing and the inert gas appendix is communicated with the inner chamber of spill housing, in the top, coat of the refractory material of air brick (2) one deck paraffin is arranged.
  4. 4. according to claim 3 a kind of can be in stove the induction furnace of blown inert gas, it is characterized in that: described air brick (2) is diffusion-type, slit-type or compound air brick.
  5. 5. according to claim 3 a kind of can be in stove the induction furnace of blown inert gas, it is characterized in that: described paraffin is 58# paraffin, the thickness of paraffin layer is 1-2mm.
  6. 6. according to claim 3 a kind of can be in stove the induction furnace of blown inert gas, it is characterized in that: the material of described spill housing is pottery or high-melting-point alloy.
  7. 7. according to claim 3 a kind of can be in stove the induction furnace of blown inert gas, it is characterized in that: the thickness of described ventilative wadding (6) is the 50-250 millimeter.
CN2011202015817U 2011-06-15 2011-06-15 Induction furnace capable of blowing inert gases towards the inside of furnace Expired - Fee Related CN202109752U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011202015817U CN202109752U (en) 2011-06-15 2011-06-15 Induction furnace capable of blowing inert gases towards the inside of furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011202015817U CN202109752U (en) 2011-06-15 2011-06-15 Induction furnace capable of blowing inert gases towards the inside of furnace

Publications (1)

Publication Number Publication Date
CN202109752U true CN202109752U (en) 2012-01-11

Family

ID=45435189

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011202015817U Expired - Fee Related CN202109752U (en) 2011-06-15 2011-06-15 Induction furnace capable of blowing inert gases towards the inside of furnace

Country Status (1)

Country Link
CN (1) CN202109752U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104654784A (en) * 2015-01-06 2015-05-27 株洲火炬工业炉有限责任公司 Method and device for stirring zinc liquid and protecting smelting through inert gas

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104654784A (en) * 2015-01-06 2015-05-27 株洲火炬工业炉有限责任公司 Method and device for stirring zinc liquid and protecting smelting through inert gas

Similar Documents

Publication Publication Date Title
CN103486859B (en) A kind of interior thorax lining casting method of induction heater
CN202109752U (en) Induction furnace capable of blowing inert gases towards the inside of furnace
CN203700396U (en) Chromium-iron alloy smelting blast furnace crucible
CN102901350B (en) Metal melting furnace
CN201214672Y (en) Single nozzle refining furnace
CN102230055A (en) Induction furnace capable of blowing inert gas towards inside of furnace
CN205077079U (en) Cooling wall for "bosh of blast furnace
CN204718378U (en) A kind of coreless induction furnace
CN202522062U (en) Copper and copper alloy intermediate-frequency induction melting furnace
CN202246739U (en) Steel structure liner for dip pipe of RH refining furnace
CN102775159A (en) Permeable dry stamp mass for furnace bottom of intermediate frequency furnace
CN203657467U (en) Aluminum and aluminum alloy melting composite crucible for medium-frequency induction furnace
CN201335602Y (en) Magnesium alloy heat preservation molding furnace
CN204043400U (en) A kind of bottom convertor isolating and protecting device
CN201296772Y (en) Electrode billet oxidation prevention device
CN206385200U (en) A kind of intermediate frequency fire door rushes argon protective device
CN206739900U (en) A kind of large-scale energy-saving electric melting magnesium furnace
CN201828148U (en) Integrated nose brick
CN201506765U (en) Furnace door on clean type coke furnace
CN104596286B (en) A kind of bottom convertor isolating and protecting device
CN203021627U (en) Furnace bottom structure of ferro-nickel furnace with power of more than 16500 KW
CN103759535B (en) Method for manufacturing heat-insulation layers of coil of medium-frequency vacuum smelting furnace
CN203947146U (en) A kind of minute silver stove of precious metals containing lead blowing
CN202181315U (en) Built-in argon gas pipe in vacuum finery
CN103113118A (en) Novel steel tapping hole filler

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120111

Termination date: 20170615

CF01 Termination of patent right due to non-payment of annual fee