CN202082910U - Main steel frame node device for tower type supercritical boiler - Google Patents

Main steel frame node device for tower type supercritical boiler Download PDF

Info

Publication number
CN202082910U
CN202082910U CN2011201341880U CN201120134188U CN202082910U CN 202082910 U CN202082910 U CN 202082910U CN 2011201341880 U CN2011201341880 U CN 2011201341880U CN 201120134188 U CN201120134188 U CN 201120134188U CN 202082910 U CN202082910 U CN 202082910U
Authority
CN
China
Prior art keywords
post
pillar
hypomere
epimere
box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011201341880U
Other languages
Chinese (zh)
Inventor
于龙
孟宪国
娄德奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Boiler Co Ltd
Original Assignee
Harbin Boiler Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Boiler Co Ltd filed Critical Harbin Boiler Co Ltd
Priority to CN2011201341880U priority Critical patent/CN202082910U/en
Application granted granted Critical
Publication of CN202082910U publication Critical patent/CN202082910U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a main steel frame node device for a tower type supercritical boiler. The stress of the traditional pillar is smaller than 4000 tons, and a tower type boiler has the stress characteristics that the stress of a single rod piece is large, and the length of the rod piece is long. The device comprises a girder (1); each end of the girder is connected with a combination pillar (2); the lower end of the girder is connected with the lower part of the combination pillar through a vertical support (3); the combination pillar comprises a lower section pillar; the lower section pillar is connected with a lower section pillar end plate; the lower section pillar end plate is connected with an upper section pillar end plate through a bolt; the upper section pillar end plate is connected with an upper section pillar; both the lower section pillar and the upper section pillar are connected with ring-shaped stiffening bars; both the lower section pillar and the upper section pillar are connected with the end plates; the end plates are connected with box-shaped transition pieces through bolts; the box-shaped transition pieces are connected with connecting plates; and the box-shaped transition pieces and connecting pieces form vertical supporting. The device is used for the tower type supercritical boilers.

Description

Tower super critical boiler main steel frame node apparatus
Technical field:
Utility model relates to a kind of field of boilers that is used for; Be specifically related to a kind of tower super critical boiler main steel frame node apparatus that is used for.
Background technology:
The section that traditional bolt connects boiler steel structure beam, post, vertical support is generally H-shape cross section, general pillar is stressed to be below 4000 tons, because it is stressed big that the loading characteristic of tower boiler is single rod member, length is big, for example certain tower boiler steel construction pillar is stressed is more than 7000 ton, and traditional bolt connects the weight that boiler steel structure can't bear weight like this.
Summary of the invention:
The purpose of utility model provides a kind of method of attachment of connected node of box section, has increased the rigidity of structure.
Above-mentioned purpose realizes by following technical scheme:
Tower super critical boiler main steel frame node apparatus, its composition comprises: beam, described beam two ends connect one group of post respectively, described beam lower end connects the bottom of one group of post by vertical support, described one group of post comprises the hypomere post, described hypomere post connects hypomere styletable plate, described hypomere styletable plate connects epimere styletable plate by bolt, described epimere styletable plate connects the epimere post, described hypomere post and described epimere post all are connected the annular muscle of putting more energy into, described hypomere post all is connected end plate with described epimere post, described end plate is by the shape of bolt connecting box transition piece, described box-shaped transition piece connects connecting plate, and described box-shaped transition piece and described connector are formed described vertical support.
Described tower super critical boiler main steel frame node apparatus, adopt the part rigid joint to be connected between described hypomere post and the epimere post, adopt rigid joint to be connected between described one group of post and the described beam, the employing hinged joint is connected between described vertical support and described one group of post and the described beam.
Beneficial effect:
1. the utility model is because the difference of rod member section, the connected node of box section and traditional connected node have than big-difference, in order to increase the rigidity of structure, being connected between the Liang Yuzhu of tower boiler rigidly connects in addition, and that the connection between traditional Liang Yuzhu is generally is hinged.
The utility model resistance to overturning is good, is fit to than large span and than the rod member of long support length.
The device that the pillar of employing of the present utility model and the method for attachment of vertical support are formed can transmit larger axis power, the form of fracture of the structure of this product with respect to the more unusual economy of worker's shape section, be suitable for.
The reliable connection of the utility model energy guard box tee section rod member, transferring power is clearly reliable.
Process is in Jiutai 670MW tower boiler test run, and the utility model has solved the carrying problem of the connected node of tower boiler master steel construction.
Description of drawings:
Accompanying drawing 1 is the installation diagram of this product.
Accompanying drawing 2 is pillar and beam schematic diagrames that are rigidly connected in the accompanying drawing 1.
Accompanying drawing 3 is structural representations of pillar and vertical support connected node in the accompanying drawing 1.
Accompanying drawing 4 is front views of pillar connected node in the accompanying drawing 1.
Accompanying drawing 5 is vertical views of accompanying drawing 4.
The specific embodiment:
Embodiment 1:
A kind of tower super critical boiler main steel frame node apparatus, its composition comprises: beam 1, described beam 1 two ends connect one group of post 2 respectively, and described beam 1 lower end connects the bottom of one group of post by vertical support 3.
Described one group of post 2 comprises hypomere post 4, described hypomere post 4 connects hypomere styletable plate 5, described hypomere styletable plate 5 connects epimere styletable plate 7 by bolt 6, described epimere styletable plate 7 connects epimere post 8, described hypomere post and described epimere post all are connected the annular muscle 9 of putting more energy into, described hypomere post all is connected end plate 10 with described epimere post, and described end plate 10 is by shape of bolt connecting box transition piece 11, and described box-shaped transition piece 11 connects connecting plate 12.In order to increase the rigidity of structure, being connected between the Liang Yuzhu of tower boiler rigidly connects, and that the connection between traditional Liang Yuzhu is generally is hinged.
Embodiment 2:
Embodiment 1 described tower super critical boiler main steel frame node apparatus, described box-shaped transition piece and described connector are formed described vertical support.
Embodiment 3:
A kind of method of attachment of tower super critical boiler main steel frame node apparatus, use the mode of the node that is articulated and connected to connect the section that makes vertical support the connected node of vertical support and become the box section, the vertical support section is the 1.2mX1.2m box, principal post connected node in the pillar of support is connected the section that makes support with the mode that partly rigidly connects connected node become the 2.5mX2.5m box, one group of beam is made into the wide 1m--1.2m that is, highly be the following box of 3m, adopt the rigid joint ways of connecting to form main steel frame girder in one group of beam and pillar together.
Embodiment 4:
The described tower super critical boiler main steel frame node apparatus of above embodiment, adopt the partially rigid node to be connected between described hypomere post and the epimere post, adopt rigid joint to be connected between described one group of post and the described beam, the employing hinged joint is connected between described vertical support and described one group of post and the described beam.

Claims (2)

1. tower super critical boiler main steel frame node apparatus, its composition comprises: beam, it is characterized in that: described beam two ends connect one group of post respectively, described beam lower end connects the bottom of one group of post by vertical support, described one group of post comprises the hypomere post, described hypomere post connects hypomere styletable plate, described hypomere styletable plate connects epimere styletable plate by bolt, described epimere styletable plate connects the epimere post, described hypomere post and described epimere post all are connected the annular muscle of putting more energy into, described hypomere post all is connected end plate with described epimere post, described end plate is by the shape of bolt connecting box transition piece, described box-shaped transition piece connects connecting plate, and described box-shaped transition piece and described connector are formed described vertical support.
2. tower super critical boiler main steel frame node apparatus according to claim 1, it is characterized in that: adopt the part rigid joint to be connected between described hypomere post and the epimere post, adopt rigid joint to be connected between described one group of post and the described beam, the employing hinged joint is connected between described vertical support and described one group of post and the described beam.
CN2011201341880U 2011-04-30 2011-04-30 Main steel frame node device for tower type supercritical boiler Expired - Fee Related CN202082910U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201341880U CN202082910U (en) 2011-04-30 2011-04-30 Main steel frame node device for tower type supercritical boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201341880U CN202082910U (en) 2011-04-30 2011-04-30 Main steel frame node device for tower type supercritical boiler

Publications (1)

Publication Number Publication Date
CN202082910U true CN202082910U (en) 2011-12-21

Family

ID=45343537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201341880U Expired - Fee Related CN202082910U (en) 2011-04-30 2011-04-30 Main steel frame node device for tower type supercritical boiler

Country Status (1)

Country Link
CN (1) CN202082910U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102162637A (en) * 2011-04-30 2011-08-24 哈尔滨锅炉厂有限责任公司 Main steel frame node device of tower type supercritical boiler and connecting method
CN114701609A (en) * 2022-03-30 2022-07-05 中船黄埔文冲船舶有限公司 Shipborne train fixing device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102162637A (en) * 2011-04-30 2011-08-24 哈尔滨锅炉厂有限责任公司 Main steel frame node device of tower type supercritical boiler and connecting method
CN102162637B (en) * 2011-04-30 2015-07-08 哈尔滨锅炉厂有限责任公司 Main steel frame node device of tower type supercritical boiler and connecting method
CN114701609A (en) * 2022-03-30 2022-07-05 中船黄埔文冲船舶有限公司 Shipborne train fixing device

Similar Documents

Publication Publication Date Title
CN201842567U (en) Lifting frame for modular tube panel of waste heat boiler
CN201546435U (en) Bolted stayed cantilever scaffold
CN203188589U (en) Rigid-frame continuous beam zero block construction bracket supporting system
CN205189144U (en) Articulation node that reinforced concrete column and girder steel are connected
CN201581623U (en) Novel bowl-type steel tube scaffold
CN201874153U (en) Universal steel structure truss girder
CN202082910U (en) Main steel frame node device for tower type supercritical boiler
CN202064620U (en) Load-bearing frame of overhanging structure
CN201605868U (en) Communication tower
CN102162637A (en) Main steel frame node device of tower type supercritical boiler and connecting method
CN203021207U (en) Large-load multifunctional gantry crane capable of being flexibly spliced
CN202578109U (en) Double-upright-post type aluminum alloy accident repair tower
CN206599729U (en) A kind of Single column pier bridge anti-overturning devices based on structure self-balancing
CN207121993U (en) The hinged joint that a kind of reinforced concrete frame structure bracing members are reinforced
CN201738628U (en) Angle steel and steel bar combined iron tower
CN204575311U (en) Railway T-beam static test truss
CN203867271U (en) Straight reinforced double-ellipsoid combined chimney
CN202945540U (en) Aluminum alloy structural member for pedestrian overcrossing
CN202559814U (en) Iron tower
CN202925981U (en) 750kV composite material cross arm
CN202705932U (en) T-beam reinforced hanger frame structure
CN204419469U (en) A kind of tower cylinder connection set for Large-scale Wind Turbines
CN203247702U (en) Steel structural support
CN205132975U (en) Six pole web member connection plate connection structure on tower crane plane
CN202899037U (en) Bridge cantilever pouring construction movable suspended scaffolding provided with middle-lower crossbeam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111221

Termination date: 20170430

CF01 Termination of patent right due to non-payment of annual fee