CN202047825U - Mining steel pipe support filled with concrete - Google Patents

Mining steel pipe support filled with concrete Download PDF

Info

Publication number
CN202047825U
CN202047825U CN 201120120432 CN201120120432U CN202047825U CN 202047825 U CN202047825 U CN 202047825U CN 201120120432 CN201120120432 CN 201120120432 CN 201120120432 U CN201120120432 U CN 201120120432U CN 202047825 U CN202047825 U CN 202047825U
Authority
CN
China
Prior art keywords
steel pipe
support
concrete
arch
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201120120432
Other languages
Chinese (zh)
Inventor
王东升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Datun Energy Holding Co Ltd
Original Assignee
Shanghai Datun Energy Holding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Datun Energy Holding Co Ltd filed Critical Shanghai Datun Energy Holding Co Ltd
Priority to CN 201120120432 priority Critical patent/CN202047825U/en
Application granted granted Critical
Publication of CN202047825U publication Critical patent/CN202047825U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a mining steel pipe support filled with concrete, belonging to the mine support system. An arc support is comprised; the arc support is composed of an arc steel pipe and concrete filled within the arc steel pipe; fixed steel plates fixed with the arc support are arranged at two ends of the arc support; pedestals are also comprised; and the two ends of the arc support and the fixed steel plates fixed with the two ends of the arc support are together fixed in the pedestals. The beneficial effects are that the structure is simple; compression strength is large; installation and maintenance are convenient; and usage coat is relatively low.

Description

A kind of mining steel pipe support of fill concrete
Technical field
The utility model relates to the mine support system, specifically is a kind of mining steel pipe support of fill concrete.
Background technology
In recent years, because coal resources reduce, exploitation develops into the deep by superficial part gradually.But along with the intensification of mining depth, the pressure that mine bore is increasing, and huge pressure not only may be thrown into the tunnel with the considerable damage coal petrography, destroys roadway support system and surrounding rock structure, and merit threatens to underground work personnel's life.Traditional steel structure support is along with its supporting intensity of increase of the degree of depth does not reach instructions for use.If make the steel structure support chap merely, not only weight is excessive, and cost also increases greatly.
Summary of the invention
For overcoming the above-mentioned deficiency of prior art, the utility model provides a kind of mining steel pipe support of fill concrete can well solve the problem of present existence.
The utility model is realized with following technical scheme: a kind of mining steel pipe support of fill concrete, comprise arch support, and described arch support is made up of arch steel pipe and the concrete that is filled in the arch steel pipe; At the arch support two ends fixation steel plate that is fixed together with arch support is arranged, also comprise base, the two ends of arch support reach and are fixed in the base with its fixation steel plate that is fixed together.
Add concrete in steel pipe, make concrete that restraint forces arranged, such structure makes outside pressure be born jointly by steel pipe concrete inner with it, and filling effect makes the anti-pressure ability of support be far longer than steel pipe or the independent action effect of coagulation support.
The beneficial effects of the utility model are: simple in structure, have high-strength supporting capacity, and bending rigidity is big, is difficult for torsional deformation, has not only improved bearing capacity but also unlikely cost and has improved.
Description of drawings
Below in conjunction with drawings and Examples the utility model is further specified.
Fig. 1 is the utility model structural representation.
Among the figure: 1, steel pipe, 2, fixation steel plate, 3, base, 4, concrete.
The specific embodiment
As shown in Figure 1, a kind of arch support of mining steel pipe support of fill concrete is made up of arch steel pipe 1 and the concrete 4 that is filled in the arch steel pipe; At the arch support two ends fixation steel plate 2 that is fixed together with arch support is arranged, also comprise base 3, the two ends of arch support reach and are fixed in the base 3 with its fixation steel plate that is fixed together 2.Have the through hole that cooperates with arch steel pipe 1 on fixation steel plate 2, through hole is passed at the two ends of arch support and fixation steel plate 2 welds together.Base 3 is a concrete bed, and the two ends of arch support are cast in the concrete bed together with fixation steel plate 2.Purpose with fixation steel plate is the stress surface that increases steel pipe and cement base, so that make support more firm.
Concrete preparation method is: the existing arch that tube bending is become to need, with cement pump concrete is injected in the steel pipe, and treat that concrete setting delivers to underworkings after solid.Prop up with temporary support device earlier and be filled with concrete steel pipe support, again fixation steel plate 2 is enclosed within the steel pipe lower end and welds.In with concrete fixation steel plate being cast in then, so complete concrete steel pipe support has just been finished.The steel pipe concrete bracket supporting should be reserved deformation space, and country rock can be out of shape in pressure release.

Claims (3)

1. the mining steel pipe support of a fill concrete comprises arch support, it is characterized in that: described arch support is made up of arch steel pipe (1) and the concrete (4) that is filled in the arch steel pipe; At the arch support two ends fixation steel plate (2) that is fixed together with arch support is arranged, also comprise base (3), the two ends of arch support reach and are fixed in the base (3) with its fixation steel plate that is fixed together (2).
2. the mining steel pipe support of a kind of fill concrete according to claim 1, it is characterized in that: have the through hole that cooperates with arch steel pipe (1) on fixation steel plate (2), through hole is passed at the two ends of arch support and fixation steel plate (2) welds together.
3. the mining steel pipe support of a kind of fill concrete according to claim 1, it is characterized in that: described base (3) is a concrete bed, and the two ends of arch support are cast in the concrete bed together with fixation steel plate (2).
CN 201120120432 2011-04-21 2011-04-21 Mining steel pipe support filled with concrete Expired - Fee Related CN202047825U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201120120432 CN202047825U (en) 2011-04-21 2011-04-21 Mining steel pipe support filled with concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201120120432 CN202047825U (en) 2011-04-21 2011-04-21 Mining steel pipe support filled with concrete

Publications (1)

Publication Number Publication Date
CN202047825U true CN202047825U (en) 2011-11-23

Family

ID=44988136

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201120120432 Expired - Fee Related CN202047825U (en) 2011-04-21 2011-04-21 Mining steel pipe support filled with concrete

Country Status (1)

Country Link
CN (1) CN202047825U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677806A (en) * 2016-12-12 2017-05-17 中国矿业大学 Pipe type shed frame supporting structure used for down-hole roadway and tunnel
CN111042839A (en) * 2019-12-18 2020-04-21 江苏采元科技有限公司 Anti-seismic support and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677806A (en) * 2016-12-12 2017-05-17 中国矿业大学 Pipe type shed frame supporting structure used for down-hole roadway and tunnel
CN106677806B (en) * 2016-12-12 2019-03-26 中国矿业大学 A kind of tubular type canopy frame support structure for underworkings, tunnel
CN111042839A (en) * 2019-12-18 2020-04-21 江苏采元科技有限公司 Anti-seismic support and construction method thereof
CN111042839B (en) * 2019-12-18 2021-03-16 江苏采元科技有限公司 Anti-seismic support and construction method thereof

Similar Documents

Publication Publication Date Title
CN104533482B (en) A kind of reinforcement means improving gob side entry driving fender stability
CN2878511Y (en) Tensile compression combined self-anchored rock anchor rod
CN108868856B (en) Energy-absorbing anchoring method of high-impact-resistant large-deformation energy-absorbing anchoring tray assembly
CN103527201B (en) Coal mine shaft lining pit shaft steel pipe concrete bracket and concrete pipe sheet suspension device
CN102352601A (en) Tunnel type composite anchorage
CN101270667A (en) Surrounding rock supporting method for ultra-strong or strong or medium rock burst tunnel section deep imbedded in underground chamber
CN104847354B (en) A kind of method that strip coal pillar performance is lifted using slip casting combined supporting anchor pole
CN202047825U (en) Mining steel pipe support filled with concrete
CN101975074B (en) Soft rock roadway anchored concrete filled steel tube anti-floor heave device and construction method thereof
CN101082281A (en) Method for controlling deformation of surrounding rocks of gallery influenced by overhead mining
CN103147772B (en) Method for supporting steel strip connecting bridge of arch-shaped soft rock roadway with large section
CN209493940U (en) A kind of roofbolt construction arrangement of architectural engineering
CN205778957U (en) A kind of delayed section of support system of workings subject to dy namic pressure
CN206129286U (en) Deep soft rock roadway under high stress high strength support
CN205387946U (en) Closed support
CN204419187U (en) Vertical deep supporting and protection structure
CN202187288U (en) Compound tunnel anchorage
CN201588643U (en) Multi-corrosion resistant anchor rod
CN203515625U (en) Flexible metal anchor rod
CN103498685B (en) Very soft rock roadway base plate and two helps release window supporting device
CN103557007B (en) Cross the construction method of geological anomaly zone soft-rock tunnel smashed to pieces
CN202417550U (en) Soft rock roadway supporting structure capable of being grouted repeatedly
CN204825924U (en) Square steel tube concrete waist rail
CN206785400U (en) A kind of buffer-type high intensity mine support system
CN202866002U (en) Steel reinforced concrete non-embedded type pillar base

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111123

Termination date: 20130421