CN202031111U - Storage yard structure on which impermeable geomembrane is laid - Google Patents

Storage yard structure on which impermeable geomembrane is laid Download PDF

Info

Publication number
CN202031111U
CN202031111U CN2011200548569U CN201120054856U CN202031111U CN 202031111 U CN202031111 U CN 202031111U CN 2011200548569 U CN2011200548569 U CN 2011200548569U CN 201120054856 U CN201120054856 U CN 201120054856U CN 202031111 U CN202031111 U CN 202031111U
Authority
CN
China
Prior art keywords
laid
impermeable geomembrane
geomembrane
seepage geomembrane
impermeable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011200548569U
Other languages
Chinese (zh)
Inventor
宋竞宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN2011200548569U priority Critical patent/CN202031111U/en
Application granted granted Critical
Publication of CN202031111U publication Critical patent/CN202031111U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model discloses a storage yard structure on which an impermeable geomembranes is laid, which comprises a storage yard area (1), wherein the impermeable geomembrane (2) is laid on the storage yard area (1) and is formed by combining smooth laid sections (3) and corrugated laid sections (4); and a covering layer (5) is laid on the impermeable geomembrane (2). According to the storage yard structure, through laying the impermeable geomembrane in a manner of being formed by combining the smooth laid sections and the corrugated laid sections, the impermeable geomembrane at the corrugated laid sections can achieve elastic expansion and contraction in the grinding process, the deformable amount of the impermeable geomembrane can be increased, and the impermeable geomembrane cannot be ripped under the circumstance of large foundation deformation, so a good protection effect is achieved. When the impermeable geomembrane is laid, a laid layer of the impermeable geomembrane is firstly ground, so the foundation deformation amplitude after decompression and the tensile deformation probability of the impermeable geomembrane can be reduced.

Description

Be equipped with the stockyard structure of anti-seepage geomembrane
Technical field
The utility model relates to a kind of stockyard leakage preventing structure, particularly a kind of stockyard structure that is equipped with anti-seepage geomembrane.
Background technology
At industrial domestic refuses such as alumina laterite stockyard, the refuse landfill landfill place of banking up, the discarded object of landfill all has in various degree pollution to environment owing to bank up, therefore in process, all can relate to the application of anti-seepage geomembrane to bank up landfill yard design, construction.Anti-seepage geomembrane is generally laid in the landfill area of banking up by designing requirement, and the major function of the anti-seepage geomembrane fluid seepage that the industrial domestic refuse of landfill produces that is to prevent to bank up to reach the protection surrounding enviroment, prevents the contaminated purpose of underground water.Can find out the importance of laying anti-seepage geomembrane link in work progress thus.At present, the laying method of anti-seepage geomembrane is the Ground Treatment of going ahead of the rest, and lays anti-seepage geomembrane then, geomembrane is covered again, and cladding material generally adopts clay, carries out cal rolling at last.Yet there is defective in this method, and when cal rolling carried out, ground produced differential settlement owing to be compacted meeting.When differential settlement acquired a certain degree, anti-seepage geomembrane distortion may occur even by drawing crack, particularly at the perimeter strip place, because the border is generally fixed end, anti-seepage geomembrane is increased by the possibility of drawing crack, and this will bring hidden danger to environmental protection.
The utility model content
The technical problems to be solved in the utility model is: a kind of stockyard structure that is equipped with anti-seepage geomembrane that can prevent that when cal rolling anti-seepage geomembrane from breaking is provided, can overcomes the deficiencies in the prior art.
The technical solution of the utility model: it comprises the zone, stockyard, is equipped with anti-seepage geomembrane on the zone, stockyard, and anti-seepage geomembrane is made up of smooth laying section and the collocation of gauffer laying section, is equipped with covering layer on anti-seepage geomembrane.
Laying anti-seepage geomembrane is on the substratum through rolling.
The edge of anti-seepage geomembrane is fixed on the perimeter strip in zone, stockyard, is provided with gauffer on the perimeter strip next door and lays section.
Compared with the prior art; the utility model passes through laying anti-seepage geomembrane is a whole section and the gauffer laying section collocation composition form laid; the anti-seepage geomembrane of gauffer laying section just can be realized elastic telescopic in the process of rolling like this; increase its deformable amount; make anti-seepage geomembrane under the bigger situation of foundation deformation, also can not reached the better protect effect by drawing crack.Earlier it being laid layer when laying anti-seepage geomembrane rolls, can reduce post-decompression foundation deformation amplitude like this, reduce the stretcher strain probability of anti-seepage geomembrane, gauffer is laid section be arranged on the perimeter strip next door, anti-seepage geomembrane can also have elasticity surplus preferably on one side under fixing situation like this, has reduced perimeter strip place anti-seepage geomembrane and has been prone to the probability that breaks.
Figure of description
Fig. 1 is a structural representation of the present utility model.
The specific embodiment
Embodiment: as shown in Figure 1, the first step rolls the substratum 6 that zone, stockyard 1 needs to lay anti-seepage geomembrane 2 places, makes its coefficient of consolidation that reaches designing requirement and characteristic value of foundation bearing capacity; Second step when laying anti-seepage geomembrane 2, was laid to the worker with anti-seepage geomembrane 2 and becomes shown in Figure 1 and lay the structures that section 3 and gauffer are laid section 4 collocation by smooth, and gauffer is laid section 4 and also be can be waveform, and its wavelength, the concrete engineering of crest height root are actual definite.In the 3rd step, it is fixing that anti-seepage geomembrane 2 is anchored into perimeter strip 7, and gauffer laying section 4 is adjacent with perimeter strip 7.The 4th step covered with 5 pairs of anti-seepage geomembranes 2 of covering layer, with machinery covering layer was rolled at last, and covering layer 5 generally can adopt barrier properties cohesive soil preferably.

Claims (3)

1. stockyard structure that is equipped with anti-seepage geomembrane, it comprises zone, stockyard (1), on zone, stockyard (1), be equipped with anti-seepage geomembrane (2), it is characterized in that: anti-seepage geomembrane (2) is made up of smooth laying section (3) and gauffer laying section (4) collocation, is equipped with covering layer (5) on anti-seepage geomembrane (2).
2. the stockyard structure that is equipped with anti-seepage geomembrane according to claim 1 is characterized in that: anti-seepage geomembrane (2) is laid on the substratum (6) through rolling.
3. the stockyard structure that is equipped with anti-seepage geomembrane according to claim 1 is characterized in that: the edge of anti-seepage geomembrane (2) is fixed on the perimeter strip (7) of zone, stockyard (1), is provided with gauffer on perimeter strip (7) next door and lays section (4).
CN2011200548569U 2011-03-04 2011-03-04 Storage yard structure on which impermeable geomembrane is laid Expired - Fee Related CN202031111U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200548569U CN202031111U (en) 2011-03-04 2011-03-04 Storage yard structure on which impermeable geomembrane is laid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200548569U CN202031111U (en) 2011-03-04 2011-03-04 Storage yard structure on which impermeable geomembrane is laid

Publications (1)

Publication Number Publication Date
CN202031111U true CN202031111U (en) 2011-11-09

Family

ID=44893413

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200548569U Expired - Fee Related CN202031111U (en) 2011-03-04 2011-03-04 Storage yard structure on which impermeable geomembrane is laid

Country Status (1)

Country Link
CN (1) CN202031111U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104179167A (en) * 2013-05-21 2014-12-03 贵阳铝镁设计研究院有限公司 Method and structure for pond closure of ash storage yard
CN104452778A (en) * 2014-11-12 2015-03-25 攀枝花钢城集团有限公司 Metallurgical slag storage yard processing method
CN115341584A (en) * 2022-08-30 2022-11-15 西南交通大学 Composite impermeable layer structure of bottom side slope of solid waste landfill

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104179167A (en) * 2013-05-21 2014-12-03 贵阳铝镁设计研究院有限公司 Method and structure for pond closure of ash storage yard
CN104179167B (en) * 2013-05-21 2016-02-10 贵阳铝镁设计研究院有限公司 A kind of lime-ash stockyard close storehouse method and structure
CN104452778A (en) * 2014-11-12 2015-03-25 攀枝花钢城集团有限公司 Metallurgical slag storage yard processing method
CN115341584A (en) * 2022-08-30 2022-11-15 西南交通大学 Composite impermeable layer structure of bottom side slope of solid waste landfill

Similar Documents

Publication Publication Date Title
CN104863184B (en) A kind of refuse landfill seepage control system extending Leachate site breakdown time and preparation method thereof
CN203200794U (en) Landfill impervious structure with old garbage as base
CN203603174U (en) Waterproof structure in basement top slab descending area
CN203174616U (en) Clay foundation rain falling and water saving system
CN101718089A (en) Combined vacuum preloading method foundation treatment construction method
CN201517217U (en) Anti-seepage structure for petroleum chemical industry area
CN202031111U (en) Storage yard structure on which impermeable geomembrane is laid
CN105507347A (en) New and old baseplate seamless connecting structure and construction method thereof
CN111424480A (en) Construction waste improved expansive soil roadbed structure and construction method thereof
CN109024458A (en) A kind of coal mine subsidence land landscape revetment and the construction method of water-bed antiseepage
CN105983562A (en) High-dimensional landfill method of waste landfill
CN201074314Y (en) Reservoir bottom seepage-control structure
CN207211175U (en) A kind of seepage proof curtain structure for releasing collapsible loess foundation settlement by soaking
CN202124863U (en) Screw anchor excavated composite foundation
CN103669421A (en) Landfill surface sealing system
CN104499508B (en) A kind of special side slope geomembrane fixed structure of landfill yard and fixing means thereof
CN202755438U (en) Integrative structure with functions of anchoring, drainage and flood interception in refuse landfill
CN204000919U (en) A kind of novel from drainage type tower-crane foundation structure
CN208455647U (en) Soft Rock Slope ecological safeguard structure
CN206873465U (en) Protection discharge structure for landfill slopes impervious barrier
CN207092156U (en) A kind of seepage proof curtain for releasing collapsible loess foundation settlement by soaking is with level every infiltration level structure
CN201581417U (en) Geomembrane anti-seepage structure for collapsible loess regions
CN205046561U (en) Domatic compaction structure of filling
CN201292616Y (en) Water drain water proof protective plate
CN203960759U (en) A kind of off-load formula rigidity culvert structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111109

Termination date: 20150304