CN202007410U - Novel tower crane base - Google Patents

Novel tower crane base Download PDF

Info

Publication number
CN202007410U
CN202007410U CN2011200233056U CN201120023305U CN202007410U CN 202007410 U CN202007410 U CN 202007410U CN 2011200233056 U CN2011200233056 U CN 2011200233056U CN 201120023305 U CN201120023305 U CN 201120023305U CN 202007410 U CN202007410 U CN 202007410U
Authority
CN
China
Prior art keywords
tower crane
central part
extremity piece
foundation
counterweight
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011200233056U
Other languages
Chinese (zh)
Inventor
王志才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2011200233056U priority Critical patent/CN202007410U/en
Application granted granted Critical
Publication of CN202007410U publication Critical patent/CN202007410U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a novel tower crane base including a central part, an end part and a counterweight. The seat of the central part is a square, and the upper end of the central part has a cross structure. The end part is provided with a mounting component which is connected with the central part through a steel hinge line to form a cross arm. The counterweight is installed on the tail end of the end part and is perpendicular to the end part. Five to seven channels are arranged in the central part and the end part, and the steel hinge line penetrates through the channels. The prefabricated-component assembled type tower crane base has the advantages of simple structure, one-time investment, enlarged application scope, and improved engineering efficiency. Moreover, the tower crane base can be repeatedly used, dismounted, mounted and transported, time for dismounting and mounting of the tower crane base can be shortened, and a large amount of money can be saved.

Description

A kind of novel foundation for tower crane
Technical field
The utility model relates to a kind of foundation for tower crane, and specifically a kind of novel foundation for tower crane belongs to the building implements field.
Background technology
Foundation for tower crane is the basis that the tower machine is installed.In the past, monolithic Cast-in-place concrete basis was adopted on fixed base tower crane (standard knot body of the tower) basis, and the manufacturing cycle is long, causes the installation tower machine time long, thereby also incurs loss through delay construction period.Whole foundation for tower crane is too big because of volume, can only once use, must remove with finishing, not only cause a large amount of wastes artificial, material, and in demolishing process, must adopt the explosion means, it is very dangerous to work, and has produced a large amount of bricks (begin most be with brick basis) discarded object simultaneously, causes environment pollution.
At present, foundation for tower crane changes the pin-connected panel foundation for tower crane on former whole concrete cast basis, this foundation for tower crane mainly connects to form spider by central part, transition piece, on the spider tail end, extremity piece is installed, the whole formation of counterweight foundation for tower crane is installed between extremity piece and the extremity piece, yet this design is very high for the counterweight requirement of tower machine, otherwise, install insecurely, produce looseningly in the course of the work, will cause serious potential safety hazard.
The utility model content
In order to address the above problem, the utility model has designed a kind of novel foundation for tower crane, and this basis lengthening is with regard to the brachium of each spider, and increase installation extremity piece, and counterweight is installed in the end of extremity piece, and vertical with extremity piece, thereby foundation for tower crane is installed firmly.
The technical solution of the utility model is: a kind of novel foundation for tower crane, form by central part, transition piece, extremity piece and counterweight; Described central part is that base is that square, upper end is criss-cross structure; Described extremity piece is provided with installed part; Installed part is connected to form spider by steel hinge line and central part; Described counterweight is installed in the end of extremity piece, and vertical with extremity piece; Be provided with the duct in described central part, transition piece and the extremity piece, the duct is provided with 5-7, and steel strand are in the duct.
Further, described counterweight is a trapezium structure;
Further, described transition piece, extremity piece cross section are for falling T-shaped or trapezoidal.
When this foundation for tower crane was installed rood beam tower machine, rood beam tower machine was installed on the foundation for tower crane by installed part, and when this foundation for tower crane was installed non-rood beam tower machine, free-standing tower machine was installed on the foundation for tower crane by connector.
Advantage of the present utility model is: prefabricated component pin-connected panel foundation for tower crane, and simple in structure, disposable input is to use repeatedly, demolition, installation, fortune have conveniently enlarged the scope of application, shorten the installation of tower machine, dismounting cycle greatly, but also save a large sum of funds spending, improved engineering efficient.
Description of drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is the sectional drawing of the utility model embodiment extremity piece 3;
Fig. 3 is the utility model embodiment counterweight 4 structural representations.
The specific embodiment
Below preferred embodiment of the present utility model is described, should be appreciated that preferred embodiment described herein only is used for description and interpretation the utility model, and be not used in qualification the utility model.
Embodiment 1
As shown in Figure 1, a kind of novel foundation for tower crane is made up of central part 1, extremity piece 3 and counterweight 4; Described central part 1 is that square, upper end is criss-cross structure for base; Described extremity piece 3 is provided with installed part 5; Extremity piece 3 is connected to form spider by steel hinge line and central part 1; Described counterweight 4 is installed in the end of extremity piece 3, and vertical with extremity piece 3; Be provided with the duct in described central part 1 and the extremity piece 3, the duct is provided with 5-7, and steel strand are in the duct; Counterweight is a trapezium structure; Transition piece 6, extremity piece 3 cross sections are for falling T-shaped or trapezoidal.
When this foundation for tower crane was installed rood beam tower machine, rood beam tower machine was installed on the foundation for tower crane by installed part, and when this foundation for tower crane was installed non-rood beam tower machine, free-standing tower machine was installed on the foundation for tower crane by connector.
It should be noted that at last: the above only is preferred embodiment of the present utility model, be not limited to the utility model, although the utility model is had been described in detail with reference to previous embodiment, for a person skilled in the art, it still can be made amendment to the technical scheme that aforementioned each embodiment put down in writing, and perhaps part technical characterictic wherein is equal to replacement.All within spirit of the present utility model and principle, any modification of being done, be equal to replacement, improvement etc., all should be included within the protection domain of the present utility model.

Claims (4)

1. a novel foundation for tower crane is characterized in that: be made up of central part, transition piece, extremity piece and counterweight; Described central part is that base is that square, upper end is criss-cross structure; Described extremity piece is provided with installed part; Installed part is connected to form spider by steel hinge line and central part; Described counterweight is installed in the end of extremity piece, and vertical with extremity piece; Be provided with the duct in described central part and the extremity piece, steel strand are in the duct.
2. a kind of novel foundation for tower crane according to claim 1 is characterized in that described counterweight is a trapezium structure
3. a kind of novel foundation for tower crane according to claim 1 is characterized in that described transition piece, extremity piece cross section are for falling T-shaped or trapezoidal.
4. concrete prefabricated assembly unit foundation for tower crane according to claim 1 is characterized in that the duct in described central part, transition piece and the extremity piece is provided with 5-7.
CN2011200233056U 2011-01-20 2011-01-20 Novel tower crane base Expired - Fee Related CN202007410U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200233056U CN202007410U (en) 2011-01-20 2011-01-20 Novel tower crane base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200233056U CN202007410U (en) 2011-01-20 2011-01-20 Novel tower crane base

Publications (1)

Publication Number Publication Date
CN202007410U true CN202007410U (en) 2011-10-12

Family

ID=44749065

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200233056U Expired - Fee Related CN202007410U (en) 2011-01-20 2011-01-20 Novel tower crane base

Country Status (1)

Country Link
CN (1) CN202007410U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102776839A (en) * 2012-07-23 2012-11-14 中铁四局集团第一工程有限公司 Reusable steel tube column foundation and construction method
WO2016203066A1 (en) * 2015-06-16 2016-12-22 Iconkrete 2012, S.L. Prefabricated concrete foundation and method for producing same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102776839A (en) * 2012-07-23 2012-11-14 中铁四局集团第一工程有限公司 Reusable steel tube column foundation and construction method
WO2016203066A1 (en) * 2015-06-16 2016-12-22 Iconkrete 2012, S.L. Prefabricated concrete foundation and method for producing same

Similar Documents

Publication Publication Date Title
CN203626080U (en) Self-resetting shear wall with replaceable coupling beam
CN201609922U (en) Pull type prefabricated small box girder iron core
CN202007410U (en) Novel tower crane base
CN204491828U (en) Can restore funcitons frame structure system
CN204491825U (en) Can restore funcitons Aseismic Structure System
CN204356910U (en) A kind of Space Free-Form Surface wood net shell assembling type node to wearing bolt
CN204491831U (en) Novel can restore funcitons frame-brace structure system
CN204174839U (en) Cellular junction steel plate-bis-limb steel pipe concrete combination column
CN203297765U (en) Integrated support and hanger capable of being assembled and connecting pieces thereof
CN201991014U (en) Concrete prefabricated assembly tower crane foundation
CN202850041U (en) Reinforcing steel support for colligation of large-scale raft plate and ribbed beam base reinforcing steel
CN202672484U (en) Steel pipe single-post structure
CN201713956U (en) Steel column fireproof structure
CN204238123U (en) A kind of triangular form section steel pipe regeneration concrete pier stud
CN202073117U (en) Underground continuous wall with arrangement of three round connective piles
CN201746847U (en) Combined multifunctional base of tower crane
CN202559369U (en) Novel tower crane foundation
CN208235587U (en) A kind of large-span deep foundation pit underground power house rack assembling construction platform
CN201367756Y (en) Armored concrete chimney with steel plate outer cylinder
CN205617659U (en) Brick -tape net
CN204753932U (en) Can assemble into floor that ceiling takes shape
CN204983401U (en) Built -in reinforcing regeneration brick aggregate concrete composite columns
CN203834504U (en) Structure of basement reverse construction method tower crane foundation
CN204754175U (en) Construction is with simply climbing a support
CN104499578A (en) Space free curved surface wooden reticulated shell assembly node of through bolt

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111012