CN202001061U - Rapid transit railway tunnel vault loess gully protective construction - Google Patents

Rapid transit railway tunnel vault loess gully protective construction Download PDF

Info

Publication number
CN202001061U
CN202001061U CN201120129960XU CN201120129960U CN202001061U CN 202001061 U CN202001061 U CN 202001061U CN 201120129960X U CN201120129960X U CN 201120129960XU CN 201120129960 U CN201120129960 U CN 201120129960U CN 202001061 U CN202001061 U CN 202001061U
Authority
CN
China
Prior art keywords
loess
tunnel
construction
coombe
rigidity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201120129960XU
Other languages
Chinese (zh)
Inventor
高杨
杨建民
喻渝
刘阳
黄棋
赵辉雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201120129960XU priority Critical patent/CN202001061U/en
Application granted granted Critical
Publication of CN202001061U publication Critical patent/CN202001061U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

A rapid transit railway tunnel vault loess gully protective construction is capable of effectively preventing loess from being washed out so as to protect the safety of a tunnel body structure below a gully, and comprises the tunnel body structure (10). Rigidity bite piles (20) are respectively arranged at the two sides of the tunnel body structure (10), the lower ends of the rigidity bite piles (20) extend into a round basement gravel soil layer, and the upper ends of the rigidity bite piles (20) are connected with a reinforced concrete open channel (21) to form an integral structure.

Description

High-speed railway tunnel vault loess coombe protective construction
Technical field
The utility model relates to the high-speed railway tunnel, and particularly a kind of high-speed railway tunnel vault loess coombe protective construction is applicable to that shallow embedding loess tunnel vault coombe, coombe bottom are positioned at the protection of the loess coombe of tunnel vault.
Background technology
Build railway tunnel work in the loess area, because the situation that the tunnel passes from the coombe below inevitably can appear in the topography and landform character that the distinctive coombe of loess is extremely grown.Because loess very easily is subjected to water to wash away the erosion incision, processing does not with great difficulty cause the tunnel vault to expose, and ditch oozes under water then, has influence on the safety of tunnel structure.For the high-speed railway tunnel, seem more important.
Traditional management measure generally is first at tunnel vault certain limit backfill cement-soil, the tunnel upper coombe is changed dose admittedly, carries out tunnel excavation then.The advantage of this processing method is easy construction, and therefore similar engineering in the past adopts more; Shortcoming is when face of land water environment degradation or when the water yield was big, the cement-soil of backfill was washed away seriously, and the cement-soil upstream forms easily that sapping, downstream are easily counter draws, and causes potential safety hazard to construction of tunnel.For the high-speed railway tunnel, requiring has higher safety assurance, should adopt safe more reliable treatment measures.
The utility model content
Technical problem to be solved in the utility model provides a kind of high-speed railway tunnel vault loess coombe protective construction, can prevent effectively that loess from washing away, thus the safety of tunnel, protection coombe below body construction.
The technical scheme that its technical problem that solves the utility model adopts is as follows:
High-speed railway of the present utility model tunnel vault loess coombe protective construction, comprise the tunnel body construction, it is characterized in that: the both sides of described tunnel body construction are respectively arranged with the rigidity interlock stake that substrate circle gravel soil layer is stretched in its lower end, and the top and the steel concrete open channel of each rigidity interlock stake connect into overall structure.
The beneficial effects of the utility model are, can effectively protect the safety of tunnel, coombe below body construction, prevent that loess from washing away, and need not renovate on a large scale coombe, and engineering quantity is little.And adopt simple device to make that the interlock pile driving construction is simple in loess area.
Description of drawings
This manual comprises following two width of cloth accompanying drawings:
Fig. 1 is the profile of the utility model high-speed railway tunnel vault loess coombe protective construction;
Fig. 2 is the cross-sectional view of interlock stake in the utility model high-speed railway tunnel vault loess.
Component shown in the figure, toponym and pairing mark: tunnel body construction 10, rigidity interlock stake 20, reinforced concrete pile 21, plain concrete pile 22, steel concrete open channel 21.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further specified.
With reference to Fig. 1, high-speed railway tunnel vault loess coombe protective construction, comprise tunnel body construction 10, be respectively arranged with its lower end in the both sides of tunnel body construction 10 and stretch into the rigidity interlock stake 20 of substrate circle gravel soil layer, the top and the steel concrete open channel 21 of each rigidity interlock stake 20 connect into overall structure.The safety of tunnel, coombe below body construction can be effectively protected in rigidity interlock stake 20, prevents that loess from washing away.
With reference to Fig. 1, generally, described rigidity interlock stake 20 two rows that respectively are horizontally arranged at interval in tunnel body construction 10 both sides.With reference to Fig. 2, described rigidity interlock stake 20 is made of the plain concrete pile 22 of horizontal equi-spaced apart setting and the reinforced concrete pile 21 that is snapped between adjacent two plain concrete piles 22.
Embodiment:
Wear the large-scale coombe in a face of land under the tunnel, the Zheng Xi high ferro Hanguguan Pass, because after even speedway is built suddenly, changed original surface water runoff conditions, strengthened the water yield that flows into coombe and water erosion, souring to coombe, freeway toll station and living area effluent discharge have aggravated this adverse effect, directly threaten coombe below safety for tunnel engineering, and then long term will cause the tunneling environment in the collapsible loess to worsen, and jeopardize operation security.Be tunnel safety during assurance construction and the operation, must renovate coombe and coombe below tunnel trunk country rock.
Adopt the rigidity interlock stake 20 of diameter 100cm, 20 fens plain concrete piles 22 of rigidity interlock stake and reinforced concrete pile 21, adjacent interlock stake interlock amount 0.2m, sequence of construction is, elder generation's construction plain concrete pile 22, reinforced concrete pile 21 construction after, form occlusion structure by cutting plain concrete pile 22 part concrete.Should strict control construction error, particularly vertical direction in the interlock pile driving construction, guarantee the interlock effect, and control 22 initial setting times of plain concrete pile well.
Prevent sapping at rigidity interlock stake 20 downstream fill block stone throwings.
Establish the thick steel concrete open channel of 0.5m 21 in order to draining in rigidity interlock stake 20, pave starting point and terminal point vertical skirt all is set, steel concrete open channel 21 canals are established deformation joint one every 10m, stitch wide 1~2cm, deformation joint is established waterstop and bituminous wood filament plate, and one deck EVA splash guard is laid in the open channel bottom.
The utlity model has safety good, can protect effectively that top, loess tunnel hole coombe is washed away by water, engineering quantity is little and the characteristics of short construction period.As finish long 2024 meters interlock stake, and performing in construction under the prerequisite of adequate preparation, the construction period only is 30 days, and can guarantee that high-speed railway passenger normally passes through in the construction period tunnel.So can avoid interference effectively, help giving full play to the transport benefits of existing railway to railway operation.
Some principles of the above the utility model high-speed railway tunnel vault loess coombe protective construction that just explains through diagrams, be not be the utility model to be confined to shown in and in described concrete structure and the scope of application, so every the corresponding modify and equivalent that might be utilized all belongs to the claim that the utility model is applied for.

Claims (3)

1. high-speed railway tunnel vault loess coombe protective construction, comprise tunnel body construction (10), it is characterized in that: the both sides of described tunnel body construction (10) are respectively arranged with the rigidity interlock stake (20) that substrate circle gravel soil layer is stretched in its lower end, and the top of each rigidity interlock stake (20) and steel concrete open channel (21) connect into overall structure.
2. high-speed railway as claimed in claim 1 tunnel vault loess coombe protective construction is characterized in that: described rigidity interlock stake (20) two rows that respectively are horizontally arranged at interval in tunnel body construction (10) both sides.
3. high-speed railway as claimed in claim 1 tunnel vault loess coombe protective construction is characterized in that: described rigidity interlock stake (20) is made of the plain concrete pile (22) of horizontal equi-spaced apart setting and the reinforced concrete pile (21) that is snapped between adjacent two plain concrete piles (22).
CN201120129960XU 2011-04-28 2011-04-28 Rapid transit railway tunnel vault loess gully protective construction Expired - Lifetime CN202001061U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201120129960XU CN202001061U (en) 2011-04-28 2011-04-28 Rapid transit railway tunnel vault loess gully protective construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201120129960XU CN202001061U (en) 2011-04-28 2011-04-28 Rapid transit railway tunnel vault loess gully protective construction

Publications (1)

Publication Number Publication Date
CN202001061U true CN202001061U (en) 2011-10-05

Family

ID=44703806

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201120129960XU Expired - Lifetime CN202001061U (en) 2011-04-28 2011-04-28 Rapid transit railway tunnel vault loess gully protective construction

Country Status (1)

Country Link
CN (1) CN202001061U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103334451A (en) * 2013-07-10 2013-10-02 中铁第四勘察设计院集团有限公司 Underneath-passing channel formed between high-speed rail piers through secant pile walls and method thereof
CN105649000A (en) * 2016-01-13 2016-06-08 大连市市政设计研究院有限责任公司 Back pressure backfilling shallow-buried excavation construction method for tunnel undercrossing gully

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103334451A (en) * 2013-07-10 2013-10-02 中铁第四勘察设计院集团有限公司 Underneath-passing channel formed between high-speed rail piers through secant pile walls and method thereof
CN105649000A (en) * 2016-01-13 2016-06-08 大连市市政设计研究院有限责任公司 Back pressure backfilling shallow-buried excavation construction method for tunnel undercrossing gully

Similar Documents

Publication Publication Date Title
CN104806272B (en) Tunnel shunting combined type guarded drainage integrated system and construction method and using method
CN204572015U (en) A kind of tunnel shunting combined type waterproof and water drainage system
CN103422511B (en) A kind of reinforcement method for transmission tower shallow base foundation under composite soft soil foundation
CN104480974B (en) Reverse seepage drain system suitable for upstream type tailings pond and upstream type tailings pond
CN204023501U (en) A kind of reinforcement Anti-seeping technology structure for earth and rockfill dam
CN104631475A (en) Safe and fast construction method of down-traversing river shallow depth bored tunnel
CN102080381B (en) Method for managing landslip of side slope landslide for transformer substation
CN207267975U (en) A kind of bed stabilization structure for being used under shield tunnel wear river
CN101598028A (en) Lining structure for super large section water-rich loess tunnel of high-speed railroad
CN104594287A (en) Ecological and economic bank protection structure
CN109024458A (en) A kind of coal mine subsidence land landscape revetment and the construction method of water-bed antiseepage
CN205530580U (en) System for collection is prevented osmosis membrane anchor, is cut flood and current as an organic whole
CN208934002U (en) A kind of barrier wall structure
CN202001061U (en) Rapid transit railway tunnel vault loess gully protective construction
CN203007961U (en) Gabion cofferdam structure
CN102031742B (en) roadbed longitudinal crack treatment method based on convex tenon type cement grouting geomembrane belt
CN107761668A (en) A kind of strand Bin Ku makes ground type bank protection structure and its construction process
CN204676485U (en) A kind of Eco-economic Type bank protection structure
CN208455647U (en) Soft Rock Slope ecological safeguard structure
CN207176627U (en) Large-scale earthing concrete block
CN205875096U (en) Enrockment is from dam break
CN205742221U (en) A kind of dark beam type anchor-pull brace structure being applicable to loosely-packed covering layer slope
CN102031757A (en) Method for constructing bottom plate guide layer of jacked-in frame bridge
CN210122706U (en) Check dam structure of hydraulic and hydroelectric engineering
CN204715424U (en) Diaphragm wall seam is anti-streams enclosure device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20111005

CX01 Expiry of patent term