CN201998323U - Reinforcing steel bar binding jig for precast box beam bottom web plates - Google Patents

Reinforcing steel bar binding jig for precast box beam bottom web plates Download PDF

Info

Publication number
CN201998323U
CN201998323U CN2011200636080U CN201120063608U CN201998323U CN 201998323 U CN201998323 U CN 201998323U CN 2011200636080 U CN2011200636080 U CN 2011200636080U CN 201120063608 U CN201120063608 U CN 201120063608U CN 201998323 U CN201998323 U CN 201998323U
Authority
CN
China
Prior art keywords
web
steel bar
reinforcing steel
crossbeam
base plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011200636080U
Other languages
Chinese (zh)
Inventor
范琦
黄炳文
舒建辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 25th Bureau Group Co Ltd
Beijing Rail Transit Engineering Construction Co Ltd of China Railway 16th Bureau Group Co Ltd
China Railway Urban Construction Group Co Ltd
Second Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Original Assignee
China Railway 25th Bureau Group Construction and Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 25th Bureau Group Construction and Installation Engineering Co Ltd filed Critical China Railway 25th Bureau Group Construction and Installation Engineering Co Ltd
Priority to CN2011200636080U priority Critical patent/CN201998323U/en
Application granted granted Critical
Publication of CN201998323U publication Critical patent/CN201998323U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a reinforcing steel bar binding jig for precast box beam bottom web plates. The reinforcing steel bar binding jig comprises a bottom plate binding portion and a web plate binding portion, the bottom plate binding portion comprises a plurality of bottom plate concrete foundations, a crossbeam and bottom plate reinforcing steel bar positioning grooves, the crossbeam is erected on the bottom plate concrete foundations, the bottom plate reinforcing steel bar positioning grooves are fixed on the crossbeam, an opening of each bottom plate reinforcing steel bar positioning groove is upward so as to be used for positioning bottom plate reinforcing steel bars, the web plate binding portion comprises two sets of web plate concrete foundations, supports and a plurality of web plate reinforcing steel bar positioning grooves, the two sets of web plate concrete foundations are respectively disposed on two sides of the crossbeam, the two sets of supports are respectively movably connected to the two sets of web plate concrete foundations and located above the web plate concrete foundations, the supports can transversely move on the web plate concrete foundations, the web plate reinforcing steel bar positioning grooves are fixed on the inner wall of each group of supports, and an opening of each web plate reinforcing steel bar positioning groove is inward so as to be used for positioning web plate reinforcing steel bars. The reinforcing steel bar binding jig can greatly shorten time for making beam pedestals and box beam formworks, and saves construction cost of beam yards.

Description

The steel bar binding clamping fixture of web at the bottom of a kind of prefabricated case beam
Technical field
The utility model relates to the steel bar binding clamping fixture of web at the bottom of a kind of prefabricated case beam.
Background technology
At present, the process of web reinforcement colligation of the beam prefabricated end of case generally is to finish in the template of case beam.The defective that this colligation mode exists is:
It is oversize that the web reinforcement process of binding takies time of beam making bench and box-beam plate at the bottom of the prefabricated case beam, is unfavorable for the turnover utilization of beam making bench and box-beam plate, can not save beam field construction cost effectively.
The utility model content
The technical problems to be solved in the utility model provides the steel bar binding clamping fixture of web at the bottom of a kind of prefabricated case beam, can significantly reduce the time that takies beam making bench and box-beam plate, saves beam field construction cost.
For solving the problems of the technologies described above, the technical solution of the utility model is:
The steel bar binding clamping fixture of web at the bottom of a kind of prefabricated case beam comprises base plate colligation part and web colligation part,
Described base plate colligation partly comprises some underplate concretes basis, crossbeam, base plate reinforcing bar locating slot, described beam erection is on described some underplate concretes basis, described some base plate reinforcing bar locating slots are fixed on the described crossbeam, described each base plate reinforcing bar locating slot opening upwards is used for the positioning plate reinforcing bar;
Described web colligation partly comprises two groups of web concrete bases, support and some web reinforcement locating slots, described two groups of web concrete bases are arranged at the both sides of described crossbeam respectively, described two pack supports are movably connected on described two groups of web concrete bases respectively, and be positioned at the top on described web concrete basis, described support can be traversing on described web concrete basis, described some web reinforcement locating slots are fixed on the inwall of described every pack support, described each web reinforcement locating slot opening is inside, is used to locate web reinforcement.
As improvement, also be provided with some base plate positioning pipes that are used for the positioning plate spilled water hole on the crossbeam described in the utility model; Also be provided with some web positioning pipes that are used to locate the web air vent on the inwall of described every pack support.
Preferably, the utility model underplate concrete basis and web concrete basis are the concrete bar shaped basis that is bar shaped.
Preferably, crossbeam described in the utility model is the shaped steel crossbeam; Described support is a steel bracket; Described base plate positioning pipe is the base plate positioning steel tube; Described web positioning pipe is the web positioning steel tube.
Therefore compared with prior art, the utility model has following beneficial effect:
Changed the construction technology of traditional direct assembling reinforcement on beam making bench; significantly reduced the time that takies beam making bench and box-beam plate; and can quick and precisely locate web reinforcement position at the bottom of the case beam, preformed hole and built-in fitting position; improved reinforcing bar binding efficient; in addition; whole mold can be processed into according to the appearance and size and the reinforcing bar protection thickness of web at the bottom of the prefabricated case beam, and is very easy to use.
Description of drawings
Accompanying drawing described herein is used to provide further understanding of the present utility model, constitutes the application's a part, does not constitute to improper qualification of the present utility model, in the accompanying drawings:
Fig. 1 is the structural representation of the utility model embodiment.
The specific embodiment
Describe the utility model in detail below in conjunction with accompanying drawing and specific embodiment, be used for explaining the utility model in this illustrative examples of the present utility model and explanation, but not as to qualification of the present utility model.
Be illustrated in figure 1 as the embodiment of the steel bar binding clamping fixture of web at the bottom of a kind of prefabricated case beam described in the utility model, comprise base plate colligation part and web colligation part, the base plate colligation partly comprises some underplate concretes basis 11, crossbeam 3, base plate reinforcing bar locating slot 51, crossbeam 3 is set up on some underplate concretes basis 11, some base plate reinforcing bar locating slots 51 are fixed on the crossbeam 3, each base plate reinforcing bar locating slot 51 opening upwards is used for the positioning plate reinforcing bar; The web colligation partly comprises two groups of web concrete bases 12, support 2 and some web reinforcement locating slots 52, two groups of web concrete bases 12 are arranged at the both sides of crossbeam 3 respectively, two pack supports 2 are movably connected on two groups of web concrete bases 12 respectively, and be positioned at the top on web concrete basis 12, support 2 can be traversing on web concrete basis 12, some web reinforcement locating slots 52 are fixed on the inwall of every pack support 2, each web reinforcement locating slot 52 opening is inside, is used to locate web reinforcement.
As improvement, in the present embodiment, also be provided with some base plate positioning pipes 6 that are used for the positioning plate spilled water hole on the crossbeam 3; Also be provided with some web positioning pipes 4 that are used to locate the web air vent on the inwall of every pack support 2.
In the present embodiment, the concrete bar shaped basis that is bar shaped is all adopted on underplate concrete basis 11 and web concrete basis 12, can save the part construction cost like this; Crossbeam 3 adopts the shaped steel crossbeam, support 2 adopts steel bracket, and base plate positioning pipe 6 adopts the base plate positioning steel tube, and web positioning pipe 4 adopts the web positioning steel tube, the rigidity of crossbeam 3, support 2, base plate positioning pipe 6, web positioning pipe 4 is better like this, can satisfy the rigidity requirement of whole mold better.
During concrete enforcement, can determine the size of mold according to the overall dimensions of the actual prefabricated case beam in beam field, also can determine the quantity and the position of base plate positioning pipe 6, web positioning pipe 4 according to the spilled water hole on the web at the bottom of the actual prefabricated case beam, air vent, in addition, can carry out the painting processing in the steel construction outside for the anticorrosion of mold.Web reinforcement is after colligation is finished on the mold at the bottom of the prefabricated case beam, can be with after the traversing laterally certain distance of support 2, utilize the anti-suspension bracket of straddle truck and reinforcing bar with prefabricated case beam at the bottom of web reinforcement integral body hang in template.
More than technical scheme that the utility model embodiment is provided be described in detail, used specific case herein principle and the embodiment of the utility model embodiment are set forth, the explanation of above embodiment only is applicable to the principle that helps to understand the utility model embodiment; Simultaneously, for one of ordinary skill in the art, according to the utility model embodiment, the part that on the specific embodiment and range of application, all can change, in sum, this description should not be construed as restriction of the present utility model.

Claims (8)

1. the steel bar binding clamping fixture of web at the bottom of the prefabricated case beam is characterized in that: comprise base plate colligation part and web colligation part,
Described base plate colligation partly comprises some underplate concretes basis, crossbeam, base plate reinforcing bar locating slot,
Described beam erection on described some underplate concretes basis,
Described some base plate reinforcing bar locating slots are fixed on the described crossbeam, and described each base plate reinforcing bar locating slot opening upwards is used for the positioning plate reinforcing bar;
Described web colligation partly comprises two groups of web concrete bases, support and some web reinforcement locating slots,
Described two groups of web concrete bases are arranged at the both sides of described crossbeam respectively,
Described two pack supports are movably connected on described two groups of web concrete bases respectively, and are positioned at the top on described web concrete basis, and described support can be traversing on described web concrete basis,
Described some web reinforcement locating slots are fixed on the inwall of described every pack support, and described each web reinforcement locating slot opening is inside, is used to locate web reinforcement.
2. the steel bar binding clamping fixture of web at the bottom of the prefabricated case beam according to claim 1 is characterized in that: also be provided with some base plate positioning pipes that are used for the positioning plate spilled water hole on the described crossbeam.
3. the steel bar binding clamping fixture of web at the bottom of the prefabricated case beam according to claim 1 is characterized in that: also be provided with some web positioning pipes that are used to locate the web air vent on the inwall of described every pack support.
4. the steel bar binding clamping fixture of web at the bottom of the prefabricated case beam according to claim 1 is characterized in that: described underplate concrete basis and web concrete basis are the concrete bar shaped basis that is bar shaped.
5. the steel bar binding clamping fixture of web at the bottom of the prefabricated case beam according to claim 1 is characterized in that: described crossbeam is the shaped steel crossbeam.
6. the steel bar binding clamping fixture of web at the bottom of the prefabricated case beam according to claim 1 is characterized in that: described support is a steel bracket.
7. the steel bar binding clamping fixture of web at the bottom of the prefabricated case beam according to claim 2 is characterized in that: described base plate positioning pipe is the base plate positioning steel tube.
8. the steel bar binding clamping fixture of web at the bottom of the prefabricated case beam according to claim 3 is characterized in that: described web positioning pipe is the web positioning steel tube.
CN2011200636080U 2011-03-11 2011-03-11 Reinforcing steel bar binding jig for precast box beam bottom web plates Expired - Fee Related CN201998323U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200636080U CN201998323U (en) 2011-03-11 2011-03-11 Reinforcing steel bar binding jig for precast box beam bottom web plates

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200636080U CN201998323U (en) 2011-03-11 2011-03-11 Reinforcing steel bar binding jig for precast box beam bottom web plates

Publications (1)

Publication Number Publication Date
CN201998323U true CN201998323U (en) 2011-10-05

Family

ID=44701095

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200636080U Expired - Fee Related CN201998323U (en) 2011-03-11 2011-03-11 Reinforcing steel bar binding jig for precast box beam bottom web plates

Country Status (1)

Country Link
CN (1) CN201998323U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102935661A (en) * 2012-11-29 2013-02-20 甘肃路桥建设集团有限公司 Shaping rack
CN103374884A (en) * 2012-04-19 2013-10-30 北京鑫畅路桥建设有限公司 Reinforcement cage producing device and reinforcement cage producing method
CN103507157A (en) * 2012-06-29 2014-01-15 中铁二十二局集团第三工程有限公司 Prefabricated T beam rib plate reinforcement steel bar locating frame
CN105235064A (en) * 2015-08-31 2016-01-13 中建市政工程有限公司 Reinforcing bar banding stretching rack for pre-stressed concrete prefabricated box girder
CN105313221A (en) * 2015-11-17 2016-02-10 中国建筑土木建设有限公司 Box girder web reinforcing bar positioning device and construction method thereof
CN106142338A (en) * 2016-06-30 2016-11-23 中交航局第四工程有限公司 A kind of prefabricated case beam framework of steel reinforcement loose tool binding construction method
CN106182404A (en) * 2016-07-08 2016-12-07 中铁十九局集团第三工程有限公司 A kind of box beam steel bar binding clamping fixture
CN106863587A (en) * 2017-03-02 2017-06-20 中国葛洲坝集团第工程有限公司 Many rib three dimension prestressing pregroove marks body reinforcement installation stands and installation method
CN115070935A (en) * 2022-06-30 2022-09-20 上海东华建设管理有限公司 Prefabricated bridge approach box girder reinforcement binding positioner of high pile pier

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103374884A (en) * 2012-04-19 2013-10-30 北京鑫畅路桥建设有限公司 Reinforcement cage producing device and reinforcement cage producing method
CN103374884B (en) * 2012-04-19 2015-06-24 北京鑫畅路桥建设有限公司 Reinforcement cage producing device and reinforcement cage producing method
CN103507157A (en) * 2012-06-29 2014-01-15 中铁二十二局集团第三工程有限公司 Prefabricated T beam rib plate reinforcement steel bar locating frame
CN103507157B (en) * 2012-06-29 2015-12-30 中铁二十二局集团第三工程有限公司 Precast T-Beam floor steel bar positioning frame
CN102935661A (en) * 2012-11-29 2013-02-20 甘肃路桥建设集团有限公司 Shaping rack
CN105235064A (en) * 2015-08-31 2016-01-13 中建市政工程有限公司 Reinforcing bar banding stretching rack for pre-stressed concrete prefabricated box girder
CN105313221A (en) * 2015-11-17 2016-02-10 中国建筑土木建设有限公司 Box girder web reinforcing bar positioning device and construction method thereof
CN105313221B (en) * 2015-11-17 2017-07-07 中国建筑土木建设有限公司 A kind of box girder web bar reinforcement positioning device and its construction method
CN106142338A (en) * 2016-06-30 2016-11-23 中交航局第四工程有限公司 A kind of prefabricated case beam framework of steel reinforcement loose tool binding construction method
CN106182404A (en) * 2016-07-08 2016-12-07 中铁十九局集团第三工程有限公司 A kind of box beam steel bar binding clamping fixture
CN106863587A (en) * 2017-03-02 2017-06-20 中国葛洲坝集团第工程有限公司 Many rib three dimension prestressing pregroove marks body reinforcement installation stands and installation method
CN106863587B (en) * 2017-03-02 2022-08-09 中国葛洲坝集团第一工程有限公司 Multi-rib three-dimensional prestress prefabricated groove body steel bar installation rack and installation method
CN115070935A (en) * 2022-06-30 2022-09-20 上海东华建设管理有限公司 Prefabricated bridge approach box girder reinforcement binding positioner of high pile pier

Similar Documents

Publication Publication Date Title
CN201998323U (en) Reinforcing steel bar binding jig for precast box beam bottom web plates
CN104196055B (en) Outer wall of basement lower die board construction method
CN205967008U (en) Bending mould quick change structure
CN204094924U (en) A kind of adjustable multiplex prefabricated board die
CN202299401U (en) Assembling structure of building wall surface template
CN202324646U (en) Pipeline check device for concrete pumping and jacking construction in steel-pipe concrete column pipe
CN105155838B (en) A kind of quick detachable high-strength building formwork
CN202291037U (en) Steel tube bending mould
CN209533739U (en) A kind of energy-saving prefabricated component assembly type overlapping board mold
CN201972715U (en) Integrated ditch cable trough mould frame
CN201989232U (en) Steel bar binding model for top plate of precast box girder
CN206011406U (en) One kind is without cold-heat bridge body of wall board mold
CN202388594U (en) Grouting line
CN205171986U (en) Modular template
CN204894178U (en) Bolt fast -assembling brickmaking mould
CN204382575U (en) A kind of plastic pipe double molds forming machine
CN203924694U (en) Biogas charging and discharging pond die special for concrete
CN2900666Y (en) Concrete upright colume with concrete bracket and capable of rear placing steel bracket
CN202378153U (en) Wall plate making machine with sliding bottom plate
CN202727092U (en) Plugging device for position of straight rib of side mold of precast concrete component of wall
CN202654935U (en) Desulfurization dust collector for turbogrid tower
CN202192678U (en) Dual purpose concrete anti-compression test die
CN201931532U (en) Hole-forming mode switching device for sleeper mold
CN201313120Y (en) Forming mould of junction box
CN202247722U (en) Ditch cable trench formwork

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY 25TH BUREAU GROUP CO., LTD.

Effective date: 20120319

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20120319

Address after: 510600, No. 8 West Republican Road, Guangzhou, 5-7, Yuexiu District

Co-patentee after: CHINA RAILWAY 25TH BUREAU GROUP Co.,Ltd.

Patentee after: CONSTRUCTION INSTALLATION ENGINEERING CO., LTD. OF CHINA RAILWAY 25TH BUREAU Group

Address before: 510600, room 8, 511 Gonghe West Road, Guangdong, Guangzhou, Yuexiu District

Patentee before: Construction Installation Engineering Co., Ltd. of China Railway 25th Bureau Group

ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY URBAN CONSTRUCTION GROUP CO., LTD. C

Free format text: FORMER OWNER: CHINA RAILWAY 25TH BUREAU GROUP CO., LTD.

Effective date: 20141219

C41 Transfer of patent application or patent right or utility model
C56 Change in the name or address of the patentee

Owner name: THE 2ND ENGINEERING CO., LTD. OF CHINA RAILWAY URB

Free format text: FORMER NAME: CONSTRUCTION INSTALLATION ENGINEERING CO., LTD. OF CHINA RAILWAY NO.25 BUREAU GROUP

CP03 Change of name, title or address

Address after: 510600, No. 8, 5-7 West Gonghe Road, Guangzhou, Guangdong Province, Yuexiu District

Co-patentee after: CHINA RAILWAY 25TH BUREAU GROUP Co.,Ltd.

Patentee after: China Railway Urban Construction Group Second Engineering Co.,Ltd.

Address before: 510600, No. 8 West Republican Road, Guangzhou, 5-7, Yuexiu District

Co-patentee before: CHINA RAILWAY 25TH BUREAU GROUP Co.,Ltd.

Patentee before: Construction Installation Engineering Co., Ltd. of China Railway 25th Bureau Group

TR01 Transfer of patent right

Effective date of registration: 20141219

Address after: 510600, No. 8, 5-7 West Gonghe Road, Guangzhou, Guangdong Province, Yuexiu District

Patentee after: China Railway Urban Construction Group Second Engineering Co.,Ltd.

Patentee after: CHINA RAILWAY URBAN CONSTRUCTION GROUP Co.,Ltd.

Patentee after: CHINA RAILWAY 16TH BUREAU GROUP BEIJING ENGINEERING Co.,Ltd.

Patentee after: CHINA RAILWAY 25TH BUREAU GROUP Co.,Ltd.

Address before: 510600, No. 8, 5-7 West Gonghe Road, Guangzhou, Guangdong Province, Yuexiu District

Patentee before: China Railway Urban Construction Group Second Engineering Co.,Ltd.

Patentee before: CHINA RAILWAY 25TH BUREAU GROUP Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111005

Termination date: 20170311

CF01 Termination of patent right due to non-payment of annual fee