CN201954106U CN2011200398082U CN201120039808U CN201954106U CN 201954106 U CN201954106 U CN 201954106U CN 2011200398082 U CN2011200398082 U CN 2011200398082U CN 201120039808 U CN201120039808 U CN 201120039808U CN 201954106 U CN201954106 U CN 201954106U
Authority
CN
China
Prior art keywords
support
flue gas
pipelines
desulphurization system
gas desulphurization
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011200398082U
Other languages
Chinese (zh)
Inventor
王永祥
吴其荣
丁开平
夏于红
吴涛
张曦和
陈四宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CPI Yuanda Environmental Protection Engineering Co Ltd
Original Assignee
CPI Yuanda Environmental Protection Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CPI Yuanda Environmental Protection Engineering Co Ltd filed Critical CPI Yuanda Environmental Protection Engineering Co Ltd
Priority to CN2011200398082U priority Critical patent/CN201954106U/en
Application granted granted Critical
Publication of CN201954106U publication Critical patent/CN201954106U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model discloses an integrated pipe frame of a flue gas desulfurization system. The integrated pipe frame comprises a support frame, wherein a straight bar which extends upwards is arranged at the top part of the support frame, pipeline brackets in horizontal arrangement are distributed on the straight bar, and supporting seats which are used for fixing pipelines are arranged on the pipeline brackets. The integrated pipe frame is provided with multiple pipeline brackets, multiple pipelines of the flue gas desulfurization system are respectively fixed on the pipeline brackets through the supporting seats, therefore, the integrated pipe frame can satisfy the requirement that multiple pipelines are laid simultaneously; meanwhile, the integrated pipe frame has the advantages of simple structure and little steel consumption, and the manufacture cost can be reduced.

Description

The comprehensive pipe support of flue gas desulphurization system
Technical field
The utility model belongs to flue gas desulphurization system equipment mounting technique field, power station, is specifically related to a kind of comprehensive pipe support that lays the flue gas desulphurization system pipeline.
Background technique
Flue gas desulphurization system is one of the capital equipment of power plant and system, wet method fume desulfurizing system generally is made up of flue gas system, tower absorption system, limestone preparation system, process water system, waste water system, desulfurizing byproduct processing system etc., more than each process system be distributed in different zones, each zone interrelates by the pipeline on the comprehensive pipe support that is laid in.According to sulfur removal technology and unit scale difference, on the comprehensive pipe support 10 ~ 25 pipelines are arranged approximately, the pipe material that different media adopts is also inequality, the pipeline that uses in the desulphurization system has carbon steel piping, Coating Steel Pipe, stainless steel pipeline, fiber reinforced plastic pipe, carbon steel line with rubber pipeline, UPVC pipeline etc., to the slurries pipeline, it lays also has certain slope requirement.
Traditional comprehensive pipe support is the door type structure, though it can satisfy the requirement that many pipelines lay simultaneously, its rolled steel dosage is more, and cost is higher; Because the pipeline of flue gas desulphurization system itself is more, require the pipe support system of installation also more, therefore be necessary comprehensive pipe support is optimized design, reduce the complexity of system, reduce rolled steel dosage, reduce cost.
Summary of the invention
In view of this, the utility model provides a kind of flue gas desulphurization system comprehensive pipe support, and more traditional comprehensive pipe support structure economical with materials reduces cost, and can satisfy the requirement that many pipelines lay simultaneously simultaneously.
The comprehensive pipe support of flue gas desulphurization system of the present utility model comprises supporting frame, and the top of support frame as described above is provided with upwardly extending straight-bar, is distributed with horizontally disposed support of pipelines on the straight-bar, and support of pipelines is provided with the bracket that is used for fixing pipeline.
Further, the T font supporting frame of support frame as described above for constituting by orthogonal crossbeam and support beam, described straight-bar is arranged on the crossbeam;
Further, be fixedly connected on the crossbeam by three angle steel bottom the described straight-bar;
Further, be symmetrical arranged two bearing diagonal beams on the described T font supporting frame, an end of bearing diagonal beam is connected with crossbeam, and the other end is connected with support beam;
Further, also be distributed with horizontally disposed support of pipelines on the described support beam, support of pipelines is provided with the bracket that is used for fixing pipeline;
Further, described support of pipelines is a shaped steel;
Further, described bracket is and the bolted U type of described shaped steel pipe collar.
The beneficial effects of the utility model are: comprehensive pipe support of the present utility model is provided with a plurality of supports of pipelines, many pipelines of flue gas desulphurization system are fixed on the support of pipelines by bracket respectively, therefore, the utility model can satisfy the requirement that many pipelines lay simultaneously; Simultaneously, the utility model is simple in structure, and rolled steel dosage is few, has reduced manufacture cost.
Description of drawings
In order to make the purpose of this utility model, technological scheme and advantage clearer, below in conjunction with accompanying drawing the utility model is described in further detail, wherein:
Fig. 1 is a structural representation of the present utility model.
Embodiment
Hereinafter with reference to accompanying drawing, preferred embodiment of the present utility model is described in detail.
Fig. 1 is a structural representation of the present utility model, as shown in the figure, the comprehensive pipe support of flue gas desulphurization system of the present utility model, comprise supporting frame, the top of support frame as described above is provided with upwardly extending straight-bar 1, be distributed with horizontally disposed support of pipelines 2 on the straight-bar 1, support of pipelines 2 is provided with the bracket 3 that is used for fixing pipeline 4.
As further improvement of the utility model, the T font supporting frame of support frame as described above for constituting by orthogonal crossbeam 5 and support beam 6, described straight-bar 1 is arranged on the crossbeam 5; Straight-bar 1 both sides all can be provided with among the support of pipelines 2(figure left side and be provided with 4, and the right side is provided with 1), but should guarantee as far as possible that the center of gravity of pipeline 4 and support beam 6 are on same vertical line; T font supporting frame materials are few and support force is strong, and its crossbeam 5 also provides comparatively broad platform, are convenient to cable and instrument setting thereon; Certainly, support frame as described above also can be other structural type.
As further improvement of the utility model, described straight-bar 1 bottom is fixedly connected on the crossbeam 5 by three angle steel 7; Straight-bar 1 is fixing more firm.
As further improvement of the utility model, be symmetrical arranged two bearing diagonal beams 8 on the described T font supporting frame, an end of bearing diagonal beam 8 is connected with crossbeam 5, and the other end is connected with support beam 6; Strengthened the stability of T font supporting frame.
As further improvement of the utility model, also be distributed with horizontally disposed support of pipelines 2 on the described support beam 6, support of pipelines 2 is provided with the bracket 3 that is used for fixing pipeline 4; The support of pipelines 2 of some is set, to improve the ability that installs pipeline additional of the present utility model to greatest extent on the support beam 6.
As further improvement of the utility model, described support of pipelines 2 is a shaped steel; Few and the good mechanical performance of shaped steel materials is such as channel-section steel, angle steel, I-steel etc.
As further improvement of the utility model, described bracket 3 is and the bolted U type of described shaped steel pipe collar; U type pipe collar is fixing tube 4 effectively, prevents that pipeline 4 from sliding or dropping, and itself and shaped steel removably connect simultaneously, and dismounting is comparatively convenient; Certainly bracket 3 also can be other structural type.
Explanation is at last, above embodiment is only unrestricted in order to the explanation the technical solution of the utility model, although by the utility model being described with reference to preferred embodiment of the present utility model, but those of ordinary skill in the art is to be understood that, can make various changes to it in the form and details, and the spirit and scope of the present utility model that do not depart from appended claims and limited.

Claims (7)

1. comprehensive pipe support of flue gas desulphurization system, it is characterized in that: comprise supporting frame, the top of support frame as described above is provided with upwardly extending straight-bar (1), be distributed with horizontally disposed support of pipelines (2) on the straight-bar (1), support of pipelines (2) is provided with the bracket (3) that is used for fixing pipeline (4).
2. the comprehensive pipe support of flue gas desulphurization system according to claim 1 is characterized in that: the T font supporting frame of support frame as described above for being made of orthogonal crossbeam (5) and support beam (6), described straight-bar (1) is arranged on the crossbeam (5).
3. the comprehensive pipe support of flue gas desulphurization system according to claim 2 is characterized in that: described straight-bar (1) bottom is fixedly connected on the crossbeam (5) by three angle steel (7).
4. the comprehensive pipe support of flue gas desulphurization system according to claim 2 is characterized in that: be symmetrical arranged two bearing diagonal beams (8) on the described T font supporting frame, an end of bearing diagonal beam (8) is connected with crossbeam (5), and the other end is connected with support beam (6).
5. the comprehensive pipe support of flue gas desulphurization system according to claim 2 is characterized in that: also be distributed with horizontally disposed support of pipelines (2) on the described support beam (6), support of pipelines (2) is provided with the bracket (3) that is used for fixing pipeline (4).
6. according to any comprehensive pipe support of described flue gas desulphurization system of claim 1 to 5, it is characterized in that: described support of pipelines (2) is a shaped steel.
7. the comprehensive pipe support of flue gas desulphurization system according to claim 6 is characterized in that: described bracket (3) is and the bolted U type of described shaped steel pipe collar.
CN2011200398082U 2011-02-16 2011-02-16 Integrated pipe frame of flue gas desulfurization system Expired - Lifetime CN201954106U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200398082U CN201954106U (en) 2011-02-16 2011-02-16 Integrated pipe frame of flue gas desulfurization system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200398082U CN201954106U (en) 2011-02-16 2011-02-16 Integrated pipe frame of flue gas desulfurization system

Publications (1)

Publication Number Publication Date
CN201954106U true CN201954106U (en) 2011-08-31

Family

ID=44498216

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200398082U Expired - Lifetime CN201954106U (en) 2011-02-16 2011-02-16 Integrated pipe frame of flue gas desulfurization system

Country Status (1)

Country Link
CN (1) CN201954106U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105422997A (en) * 2015-12-24 2016-03-23 广船国际有限公司 T-shaped pipe protecting frame
CN106439238A (en) * 2016-11-21 2017-02-22 无锡金顶石油管材配件制造有限公司 Petroleum pipeline rack
CN109268611A (en) * 2018-08-20 2019-01-25 大唐环境产业集团股份有限公司 A kind of wet desulphurization outdoor integrated pipe support pipe defroster and method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105422997A (en) * 2015-12-24 2016-03-23 广船国际有限公司 T-shaped pipe protecting frame
CN106439238A (en) * 2016-11-21 2017-02-22 无锡金顶石油管材配件制造有限公司 Petroleum pipeline rack
CN109268611A (en) * 2018-08-20 2019-01-25 大唐环境产业集团股份有限公司 A kind of wet desulphurization outdoor integrated pipe support pipe defroster and method

Similar Documents

Publication Publication Date Title
CN201954106U (en) Integrated pipe frame of flue gas desulfurization system
CN204370833U (en) Elements of Space Grid Truss supporting apparatus
CN204234481U (en) Dephosphorize by high pressure water pump set control system energy saver
CN104261042A (en) Transmission rail with guide wheels
CN201610978U (en) Pipe rack convenient for installing and repairing multilayer pipeline
CN201515179U (en) Installation unit of marine cable
CN204647550U (en) The rotary pipe lining device of Pipe installing
CN204429085U (en) A kind of desulfuration absorbing tower spray pipe device
CN103803792B (en) A kind of prefabricated rods dynamic collimation devices and methods therefor
CN201832522U (en) Novel wet-type desulphurization dust removal absorption tower
CN201214898Y (en) Low beam template reinforcement machine
CN101293177A (en) Vertical dismountable defroster
CN104445590B (en) The Float cylinder type of aerated mixing plant installs combined bay
CN203865232U (en) Transportation clamping fixture for large cylindrical steel structural member
CN203083496U (en) Angle rule for mounting trolley line bracket
CN105441160A (en) Device for removing ash and sulfur in coal by using oxygen-containing steam flow
CN202187456U (en) Counteracting bearing suspended-ceiling suspension device
CN207760124U (en) It is a kind of that the online stent system for replacing aeration flexible pipe can be achieved
CN102513959B (en) Installing and dismantling device of high temperature gas-cooled reactor discharging equipment
CN205777537U (en) A kind of upper and lower pressurizing unit of interior wall
CN208346630U (en) A kind of gap bridge pipeline K font door frame
CN201940154U (en) Air distribution and mass transfer device of desulfurizing tower
CN204073838U (en) The plumbing installation of a kind of wet desulphurization absorption tower prevention gypsum slurries overflow
CN201596461U (en) Guniting pipe of liquid column tower
CN205244612U (en) A horizontal suspension structure for protection of 220kV cable normal position

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20110831