CN201915117U - Emergency nitrogen supply control gas circuit structure - Google Patents

Emergency nitrogen supply control gas circuit structure Download PDF

Info

Publication number
CN201915117U
CN201915117U CN2010206530507U CN201020653050U CN201915117U CN 201915117 U CN201915117 U CN 201915117U CN 2010206530507 U CN2010206530507 U CN 2010206530507U CN 201020653050 U CN201020653050 U CN 201020653050U CN 201915117 U CN201915117 U CN 201915117U
Authority
CN
China
Prior art keywords
gas circuit
pneumatic butterfly
ball valve
nitrogen
valve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010206530507U
Other languages
Chinese (zh)
Inventor
滕晓飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Xinyu Color Plate Co Ltd
Original Assignee
Tianjin Xinyu Color Plate Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Xinyu Color Plate Co Ltd filed Critical Tianjin Xinyu Color Plate Co Ltd
Priority to CN2010206530507U priority Critical patent/CN201915117U/en
Application granted granted Critical
Publication of CN201915117U publication Critical patent/CN201915117U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Fluid-Pressure Circuits (AREA)

Abstract

The utility model discloses an emergency nitrogen supply control gas circuit structure. The structure mainly adopts the technical scheme that an emergency nitrogen inlet valve assembly is connected with the lower part of a first gas circuit, a first pneumatic butterfly valve assembly is connected with the lower part of a second gas circuit, a second pneumatic butterfly valve assembly is connected with the lower part of a third gas circuit, and the above parts are assembled into a whole through a connecting pipeline; a second ball valve is connected with one end of a control pipeline, and a first ball valve is connected with the other end of the control pipeline; the second ball valve is arranged in the connecting pipeline above emergency nitrogen inlet valves in a connected manner; and the middle of the control pipeline is connected and communicated with the space above first pneumatic butterfly valves and second pneumatic butterfly valves, and is integrated with the space through assembly. The structure has the advantages of reasonable design and convenience in use, and can guarantee the nitrogen supply for continuous production.

Description

Urgent for nitrogen control gas circuit structure
Affiliated technical field
The utility model relates to the operating structure of the urgent nitrogen supply system of a kind of annealing furnace, and is particularly a kind of urgent for nitrogen control gas circuit structure, is applicable to annealing furnace.
Background technology
At present, when the gas shield station power outage and nitrogen gas generating system take place is broken down, promptly can only enter annealing furnace from gas circuit one, can't supply with proportioning gas, cause production line to stop production for nitrogen.
Summary of the invention
Problem to be solved in the utility model is, overcomes the deficiencies in the prior art, provides a kind of urgent for nitrogen control gas circuit structure.This structure is not only reasonable in design, compact construction, and urgent nitrogen can be entered simultaneously from gas circuit one and gas circuit two, and guaranteeing the supply of nitrogen, simultaneously urgent nitrogen enters matching system by gas circuit three, guarantees carrying out continuously of production.
The technical solution adopted in the utility model is: gas circuit connects urgent nitrogen inlet valve assembly once, two times companies of gas circuit Pneumatic butterfly valve one assembly is connected Pneumatic butterfly valve two assemblies for three times with gas circuit, by the connection line general assembly is one, control pipeline one end connects ball valve two, the other end connects ball valve one, ball valve two is connected in the connection line of urgent nitrogen inlet valve top, control pipeline intermediate section is not connected with Pneumatic butterfly valve one, Pneumatic butterfly valve two tops, is assembled into one and constitutes.
During use, the utility model is connected with the liquid nitrogen vaporization device of urgent nitrogen gets final product.In the ordinary production, ball valve two is closed, ball valve one is opened and is got final product; When needing the urgent nitrogen of supply, ball valve one is closed, ball valve two is opened.Owing on Pneumatic butterfly valve one, the Pneumatic butterfly valve two hand-operating device is arranged all, when outage, can supply urgent nitrogen, guarantee carrying out continuously of production.
The beneficial effects of the utility model are, and are rational in infrastructure, easy to use, when outage and nitrogen gas generating system break down, can supply urgent nitrogen, and what guarantee to produce carries out continuously.
Description of drawings
Below in conjunction with drawings and Examples the utility model is further specified.
Fig. 1 is a structural representation of the present utility model.
Accompanying drawing number is: 1, urgent nitrogen inlet valve, 2, Pneumatic butterfly valve one, 3, Pneumatic butterfly valve two, 4, ball valve one, 5, the liquid nitrogen vaporization device of ball valve two, 6, urgent nitrogen, 7, the control pipeline, 8, gas circuit one, 9, gas circuit two, 10, gas circuit three, 11, connection line.
Embodiment
With reference to Fig. 1, gas circuit connects urgent nitrogen inlet valve 1 assembly for one 8 times, 29 times companies of gas circuit Pneumatic butterfly valve one 2 assemblies are connected Pneumatic butterfly valve 23 assemblies for 3 10 times with gas circuit, by connection line 11 general assemblies is one, control pipeline 7 one ends connect ball valve 25, the other end connects ball valve 1, ball valve 25 is connected in the connection line 11 of urgent nitrogen inlet valve 1 top, is connected with Pneumatic butterfly valve 1, Pneumatic butterfly valve 23 tops respectively in the middle of the control pipeline 7, is assembled into one and constitutes.
During use, the utility model is connected with the liquid nitrogen vaporization device 6 of urgent nitrogen gets final product.In the ordinary production, ball valve 25 is closed, ball valve 1 is opened and is got final product; When needing the urgent nitrogen of supply, ball valve 1 is closed, ball valve 25 is opened.Owing on the Pneumatic butterfly valve 1, Pneumatic butterfly valve 23 hand-operating device is arranged all, when outage and nitrogen gas generating system break down, can supply urgent nitrogen.
The urgent constructional feature of the utility model design: this architecture compactness for nitrogen control gas circuit structure, cost is low, overcomes the deficiency of original technology, and a kind of new gas path control method is provided, urgent nitrogen can be entered simultaneously from gas circuit 1 and gas circuit 29, guarantee the supply of nitrogen; During the nitrogen gas generating system fault of short period of time, can make urgent nitrogen normal for nitrogen from gas circuit 1, simultaneously urgent nitrogen enters matching system by gas circuit 3 10, and what guarantee to produce carries out continuously.

Claims (1)

1. the urgent nitrogen that supplies is controlled gas circuit structure, it is characterized in that: gas circuit connects urgent nitrogen inlet valve assembly once, two times companies of gas circuit Pneumatic butterfly valve one assembly is connected Pneumatic butterfly valve two assemblies for three times with gas circuit, by the connection line general assembly is one, control pipeline one end connects ball valve two, the other end connects ball valve one, ball valve two is connected in the connection line of urgent nitrogen inlet valve top, control pipeline intermediate section is not connected with Pneumatic butterfly valve one, Pneumatic butterfly valve two tops, is assembled into one and constitutes.
CN2010206530507U 2010-12-10 2010-12-10 Emergency nitrogen supply control gas circuit structure Expired - Fee Related CN201915117U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206530507U CN201915117U (en) 2010-12-10 2010-12-10 Emergency nitrogen supply control gas circuit structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206530507U CN201915117U (en) 2010-12-10 2010-12-10 Emergency nitrogen supply control gas circuit structure

Publications (1)

Publication Number Publication Date
CN201915117U true CN201915117U (en) 2011-08-03

Family

ID=44414925

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206530507U Expired - Fee Related CN201915117U (en) 2010-12-10 2010-12-10 Emergency nitrogen supply control gas circuit structure

Country Status (1)

Country Link
CN (1) CN201915117U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103539084A (en) * 2013-10-17 2014-01-29 山东金宇实业股份有限公司 Nitrogen system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103539084A (en) * 2013-10-17 2014-01-29 山东金宇实业股份有限公司 Nitrogen system

Similar Documents

Publication Publication Date Title
CN201915117U (en) Emergency nitrogen supply control gas circuit structure
CN201426002Y (en) Carbon dioxide laser gas control device
CN201650504U (en) Compressed natural gas spray rail for automobile
CN203612648U (en) Air-duct feed conveying system
CN202031538U (en) Unloading high-pressure anti-explosion solenoid valve
CN203641748U (en) Multipurpose valve for power construction vehicle
CN204644306U (en) Combustion gas in Biomass Gasification & Power Generation device is for amount automatic control system
CN201732664U (en) Double-power-source transformer
CN202281043U (en) Water circulating system
CN213629389U (en) Formaldehyde production steam distribution device
CN203306961U (en) Winch and safety gear linkage device
CN201664568U (en) PSA high efficiency starting device
CN202148561U (en) Two-path water cooling system for workshop
CN202688359U (en) Converter gas network-connected recycling device
CN205138075U (en) Can maintain empty system oxygen switched systems that divides of operation in valves malfunction
CN213541408U (en) Distributor for formaldehyde production
CN202900356U (en) Inlet valve middle structure
CN202221214U (en) Fractionating tower for oxygen making system
CN202756714U (en) Timing gas valve
CN208824208U (en) A kind of synthetic-ammonia transformation gas hydrogen sulfide content regulating device
CN201875161U (en) Pilot valve of reducing valve
CN201057358Y (en) Pile-up valve of compressed natural gas bottle
CN201844736U (en) Upper casing of glass lined bidirectional shell-tube condenser
CN202315637U (en) Novel public valve station pressure oil pipeline of pressure swing adsorption device
CN204681102U (en) Residential area distribution transforming load factor control device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110803