CN202281043U - Water circulating system - Google Patents
Water circulating system Download PDFInfo
- Publication number
- CN202281043U CN202281043U CN201120375660XU CN201120375660U CN202281043U CN 202281043 U CN202281043 U CN 202281043U CN 201120375660X U CN201120375660X U CN 201120375660XU CN 201120375660 U CN201120375660 U CN 201120375660U CN 202281043 U CN202281043 U CN 202281043U
- Authority
- CN
- China
- Prior art keywords
- pipeline
- valve
- water
- water pump
- cooling tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Other Air-Conditioning Systems (AREA)
- Compressor (AREA)
Abstract
The utility model discloses a water circulating system, which comprises water cooling towers, water pumps, an air compressor system, a water system for a workshop and pipelines. A first water cooling tower is connected with a first water pump. The first water cooling tower and a second water cooling tower are both connected with a second water pump. The second water cooling tower is connected with a third water pump. The first water pump is connected with the air compressor system through a fifth pipeline. The third water pump is connected with the water system for the workshop through a sixth pipeline. A seventh pipeline is connected with the fifth pipeline and the sixth pipeline and provided with a seventh valve and an eighth valve. One end of an eighth pipeline is connected with a seventh pipeline, and the other end of the eighth pipeline is connected with the second water pump. The air compressor system is connected with the first water cooling tower through a ninth pipeline, the ninth pipeline is provided with a tenth valve. The water system for the workshop is connected with the second water cooling tower through a tenth pipeline, and the tenth pipeline is provided with an eleventh valve. The water circulating system can reduce equipment investment and energy consumption and is flexible in use.
Description
Technical field
The utility model relates to a kind of circulation.
Background technique
Traditional circulation comprises cooling tower, water pump, air compressor system, workshop water system and pipeline; Air compressor system and workshop water system all have a stand by pump, and two cover systems have four pumps, and two pumps uses two pumps subsequent use; No matter producing consumption must have two pumps to move simultaneously; Equipment investment is high, and energy-output ratio is big, and uses dumb.Fig. 1 is the structural representation of traditional circulation.
The model utility content
The technical problem that the utility model will solve provides a kind of circulation.
For solving the problems of the technologies described above, the technological scheme that the utility model is taked is: a kind of circulation comprises cooling tower, water pump, air compressor system, workshop water system and pipeline.
First cooling tower is connected with first water pump through first pipeline, and first valve is arranged on first pipeline;
First cooling tower is connected with second water pump through second pipeline, and second valve is arranged on second pipeline;
Second cooling tower is connected with second water pump through the 3rd pipeline, and the 3rd valve is arranged on the 3rd pipeline;
Second cooling tower is connected with the 3rd water pump through the 4th pipeline, and the 4th valve is arranged on the 4th pipeline;
First water pump is connected with air compressor system through the 5th pipeline, and the 5th valve is arranged on the 5th pipeline;
The 3rd water pump is connected with the workshop water system through the 6th pipeline, and the 6th valve is arranged on the 6th pipeline;
The 5th pipeline is connected with the 7th pipeline between the 5th valve and air compressor system, and the 7th valve and the 8th valve are arranged on the 7th pipeline;
The 7th pipeline is connected with the 6th pipeline between the 6th valve and workshop water system;
The 8th pipeline is connected with the 7th pipeline between the 7th valve and the 8th valve, and the other end of the 8th pipeline is connected with second water pump, and the 9th valve is arranged on the 8th pipeline;
Air compressor system is connected with first cooling tower through the 9th pipeline, and the tenth valve is arranged on the 9th pipeline;
The workshop water system is connected with second cooling tower through the tenth pipeline, on the tenth pipeline the 11 valve is arranged.
When closing second valve, the 3rd valve, the 9th valve, the 7th valve and the 8th valve, air compressor system and workshop water system were separately used when other valves were in open mode, this moment first water pump and the 3rd water pump operation, second water pump cuts out.
When air compressor system and workshop water system were separately used, second water pump can be as the stand by pump of workshop water system as the stand by pump of air compressor system.If first water pump breaks down, close first valve and the 5th valve, open second valve, the 9th valve and the 7th valve, then second water pump is air compressor system work.If the 3rd water pump breaks down, close the 4th valve and the 6th valve, open the 3rd valve, the 9th valve and the 8th valve, then second water pump is workshop water system work.
When closing first valve, the 5th valve, the 4th valve and the 6th valve, air compressor system and workshop water system merged and use when other valves were in open mode, this moment second water pump operation, first water pump and the 3rd water pump are closed.
Adopt the beneficial effect that technique scheme produced to be:
Can save a stand by pump, thereby reduce equipment investment, hour can only open a pump producing consumption, save the energy, two cover systems can switch at any time, easy to use flexibly.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the utility model is done further detailed explanation.
Fig. 1 is the structural representation of traditional circulation;
Fig. 2 is the structural representation of the utility model;
1 is first cooling tower, and 2 is second cooling tower, and 3 is first water pump, and 4 is second water pump, and 5 is the 3rd water pump, and 6 is air compressor system; 7 is the workshop water system, and 8 is first valve, and 9 is second valve, and 10 is the 3rd valve, and 11 is the 4th valve, and 12 is the 5th valve; 13 is the 9th valve, and 14 is the 6th valve, and 15 is the 7th valve, and 16 is the 8th valve, and 17 is the 11 valve, and 18 is the tenth valve; 20 is first pipeline, and 21 is second pipeline, and 22 is the 3rd pipeline, and 23 is the 8th pipeline, and 24 is the 7th pipeline; 25 is the 6th pipeline, and 26 is the 4th pipeline, and 27 is the 5th pipeline, and 28 is the 9th pipeline, and 29 is the tenth pipeline.
Embodiment
Embodiment 1:
A kind of circulation comprises cooling tower, water pump, air compressor system, workshop water system and pipeline.First cooling tower (1) is connected with first water pump (3) through first pipeline (20), and first valve (8) is arranged on first pipeline (20);
First cooling tower (1) is connected with second water pump (4) through second pipeline (21), and second valve (9) is arranged on second pipeline (21);
Second cooling tower (2) is connected with second water pump (4) through the 3rd pipeline (22), and the 3rd valve (10) is arranged on the 3rd pipeline (22);
Second cooling tower (2) is connected with the 3rd water pump (5) through the 4th pipeline (26), and the 4th valve (11) is arranged on the 4th pipeline (26);
First water pump (3) is connected with air compressor system (6) through the 5th pipeline (27), and the 5th valve (12) is arranged on the 5th pipeline (27);
The 3rd water pump (5) is connected with the workshop water system through the 6th pipeline (25), and the 6th valve (14) is arranged on the 6th pipeline (25);
The 5th pipeline (27) is connected with the 7th pipeline (24) between the 5th valve (12) and air compressor system (6), and the 7th valve (15) and the 8th valve (16) are arranged on the 7th pipeline (24);
The 7th pipeline (27) is connected with the 6th pipeline (25) between the 6th valve (14) and workshop water system (7);
The 8th pipeline (23) is connected with the 7th pipeline (24) between the 7th valve (15) and the 8th valve (16), and the other end of the 8th pipeline (23) is connected with second water pump (4), and the 9th valve (13) is arranged on the 8th pipeline (23);
Air compressor system (6) is connected with first cooling tower (1) through the 9th pipeline (28), and the tenth valve (18) is arranged on the 9th pipeline (28);
Workshop water system (7) is connected with second cooling tower (2) through the tenth pipeline (29), and the tenth pipeline has the 11 valve (17) on (29).
Claims (1)
1. circulation; Comprise cooling tower, water pump, air compressor system, workshop water system and pipeline; It is characterized in that: first cooling tower (1) is connected with first water pump (3) through first pipeline (20), and first valve (8) is arranged on first pipeline (20);
First cooling tower (1) is connected with second water pump (4) through second pipeline (21), and second valve (9) is arranged on second pipeline (21);
Second cooling tower (2) is connected with second water pump (4) through the 3rd pipeline (22), and the 3rd valve (10) is arranged on the 3rd pipeline (22);
Second cooling tower (2) is connected with the 3rd water pump (5) through the 4th pipeline (26), and the 4th valve (11) is arranged on the 4th pipeline (26);
First water pump (3) is connected with air compressor system (6) through the 5th pipeline (27), and the 5th valve (12) is arranged on the 5th pipeline (27);
The 3rd water pump (5) is connected with the workshop water system through the 6th pipeline (25), and the 6th valve (14) is arranged on the 6th pipeline (25);
The 5th pipeline (27) is connected with the 7th pipeline (24) between the 5th valve (12) and air compressor system (6), and the 7th valve (15) and the 8th valve (16) are arranged on the 7th pipeline (24);
The 7th pipeline (24) is connected with the 6th pipeline (25) between the 6th valve (14) and workshop water system (7);
The 8th pipeline (23) is connected with the 7th pipeline (24) between the 7th valve (15) and the 8th valve (16), and the other end of the 8th pipeline (23) is connected with second water pump (4), and the 9th valve (13) is arranged on the 8th pipeline (23);
Air compressor system (6) is connected with first cooling tower (1) through the 9th pipeline (28), and the tenth valve (18) is arranged on the 9th pipeline (28);
Workshop water system (7) is connected with second cooling tower (2) through the tenth pipeline (29), and the tenth pipeline has the 11 valve (17) on (29).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201120375660XU CN202281043U (en) | 2011-09-28 | 2011-09-28 | Water circulating system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201120375660XU CN202281043U (en) | 2011-09-28 | 2011-09-28 | Water circulating system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202281043U true CN202281043U (en) | 2012-06-20 |
Family
ID=46227211
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201120375660XU Expired - Fee Related CN202281043U (en) | 2011-09-28 | 2011-09-28 | Water circulating system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202281043U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104819616A (en) * | 2015-03-31 | 2015-08-05 | 宁波杭州湾新区祥源动力供应有限公司 | Refrigeration system for grid-connected reduction of energy consumption of circulation cooling water |
-
2011
- 2011-09-28 CN CN201120375660XU patent/CN202281043U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104819616A (en) * | 2015-03-31 | 2015-08-05 | 宁波杭州湾新区祥源动力供应有限公司 | Refrigeration system for grid-connected reduction of energy consumption of circulation cooling water |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202281043U (en) | Water circulating system | |
CN203404143U (en) | Two-branch-cylinder simultaneous system controlled by proportional valve | |
CN203516263U (en) | Hydraulic circuit device | |
CN204911199U (en) | Desulfurization demister washing water installation | |
CN201723770U (en) | Three-way ball valve | |
CN203848711U (en) | Flexibly adjusted cool water tower device | |
CN202812293U (en) | Double-stop single-drain combined valve | |
CN203285747U (en) | Tandem type circulating water device for high-temperature centrifugal pump | |
CN202381669U (en) | Cooling device for pre-pressing speed reducing machine | |
CN203683090U (en) | Secondary recovery device for sulfur hexafluoride | |
CN203615654U (en) | Mounting structure for safety valves and pressure container in air conditioner refrigeration system | |
CN203395330U (en) | Valve convenient for opening | |
CN202123118U (en) | Energy-saving device of extruder | |
CN203374820U (en) | Irrigation outlet valve | |
CN202628643U (en) | Improved multiple directional control valve of hydraulic equipment | |
CN203346951U (en) | Hydraulic testing multifunctional energy-saving device for pressure container | |
CN201950437U (en) | Detaching tool for valve glands and motor fans | |
CN201697277U (en) | Intelligent conversion device for central air conditioner | |
CN201876051U (en) | Cooling device | |
CN203498904U (en) | Draining and anti-freezing mechanism of water pipeline | |
CN202055287U (en) | Water circulation and drainage pump sharing system with compulsory water supply function | |
CN203927010U (en) | Water tank final controlling element makes up a prescription | |
CN207751147U (en) | A kind of idle call compressed air source unit | |
CN206206128U (en) | A kind of air compressor machine reforming unit | |
CN205172795U (en) | Spiral case pressure relief device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C56 | Change in the name or address of the patentee | ||
CP03 | Change of name, title or address |
Address after: 055550, Hebei province Xingtai Cao Zhuang management area, the Eastern District Patentee after: Hebei Kai Kai Biotechnology Co., Ltd. Address before: 055550 large industrial park, Cao Zhuang, Hebei, Xingtai Patentee before: Hebei Shukai Veterinary Medicine Technology Co.,Ltd. |
|
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120620 Termination date: 20170928 |
|
CF01 | Termination of patent right due to non-payment of annual fee |