CN201892535U - Settling amount monitoring device for power tunnel - Google Patents

Settling amount monitoring device for power tunnel Download PDF

Info

Publication number
CN201892535U
CN201892535U CN2010206005843U CN201020600584U CN201892535U CN 201892535 U CN201892535 U CN 201892535U CN 2010206005843 U CN2010206005843 U CN 2010206005843U CN 201020600584 U CN201020600584 U CN 201020600584U CN 201892535 U CN201892535 U CN 201892535U
Authority
CN
China
Prior art keywords
monitoring device
settling amount
amount monitoring
power tunnel
acquisition unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010206005843U
Other languages
Chinese (zh)
Inventor
王承
姜芸
王强
李海
闵红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI ZHONGQU ELECTRIC ENERGY SAVING TECHNOLOGY Co Ltd
Shanghai Municipal Electric Power Co
Original Assignee
SHANGHAI ZHONGQU ELECTRIC ENERGY SAVING TECHNOLOGY Co Ltd
Shanghai Municipal Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI ZHONGQU ELECTRIC ENERGY SAVING TECHNOLOGY Co Ltd, Shanghai Municipal Electric Power Co filed Critical SHANGHAI ZHONGQU ELECTRIC ENERGY SAVING TECHNOLOGY Co Ltd
Priority to CN2010206005843U priority Critical patent/CN201892535U/en
Application granted granted Critical
Publication of CN201892535U publication Critical patent/CN201892535U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model relates to a settling amount monitoring device for a power tunnel. The settling amount monitoring device comprises a static water level, a data acquisition unit, a communication network, a host computer and a cable, wherein the static water level is connected with the data acquisition unit through the cable, and the data acquisition unit is connected with the host computer through the communication network. Compare with the prior art, the utility model has the advantage that settling amount monitoring device for the power tunnel can monitor the settling amount in the power tunnel in real-time.

Description

A kind of settling amount monitoring device of electric power tunnel
Technical field
The utility model relates to a kind of settling amount monitoring device, especially relates to a kind of settling amount monitoring device of electric power tunnel.
Background technology
Along with the sustainable development of national economy and steadily improving of living standards of the people, the demand of electric power is continued to rise, with regard to the area, Shanghai, implementing after a series of mistakes keep away peak electricity consumption measure in 2007, power consumption still fixes at last at 2021.8 ten thousand kilowatts, increases by 9.4% on a year-on-year basis.So huge power consumption will be the major test to power equipment.Simultaneously, the upcoming 2010 World Fair will be the test once huger to Electrical Safety undoubtedly.So certainly will require strategically planning of science activities and overall management to be carried out in the allotment and the transmission of electric power resource.Just require downtown area increase cable ratio, major trunk roads electric wire to go into ground in the engineering philosophy of " 15 " urban power network planning.Electric power tunnels a large amount of under this background will arise at the historic moment, build as the Expo electric power tunnel is nervous, as 500 kilovolt of three woods transformer station be about to building by Pudong New District to 500 kilovolts of Expo transformer stations that building, about 15.25 kilometers of total length, 6.2 meters of maximum tube wall external diameters, whole process is established 14 active wells altogether, links to each other with the Long Yanglu tunnel that has built up, tunnel, Tibet road therebetween.
Meanwhile we should clearly recognize electric power tunnel because geologic media of living in is abominable; the various construction activities of periphery are frequent; the increase of tunnel Years Of Service; as not protecting targetedly to electric power tunnel; will bring serious threat to Electrical Safety; and cause abominable social influence easily; yet at present; domestic research work to all kinds of electric power tunnel running safety monitorings aspect also relatively lags behind; and the research of the subway tunnel safe operation protection aspect similar with it starts to walk early; and comparatively great successes have been got; safe operation to subway tunnel provides technology and jural guarantee, is worth electric power tunnel operation protection department to use for reference.Wherein the settling amount monitoring level to electric power tunnel is in than low level always.
Summary of the invention
The purpose of this utility model is exactly the settling amount monitoring device that a kind of electric power tunnel is provided for the defective that overcomes above-mentioned prior art existence.
The purpose of this utility model can be achieved through the following technical solutions:
A kind of settling amount monitoring device of electric power tunnel, it is characterized in that, comprise hydrostatic level, data acquisition unit, communication network, host computer, cable, described hydrostatic level is connected with data acquisition unit by cable, and described data acquisition unit is connected with host computer by communication network.
Described hydrostatic level is the RJ-S type condenser type hydrostatic level that southern auspicious dam engineering is monitored branch office's development.
Described communication network is GPRS network or 3G network.
Described data acquisition unit is a DATA GeoLogger DT515 automatic data collection device.
Compared with prior art, the utlity model has the settling amount of real-time monitoring electric power tunnel.
Description of drawings
Fig. 1 is a structural representation of the present utility model.
Embodiment
Below in conjunction with the drawings and specific embodiments the utility model is elaborated.
Embodiment
As shown in Figure 1, a kind of settling amount monitoring device of electric power tunnel, it is characterized in that, comprise hydrostatic level 1, data acquisition unit 2, communication network 3, host computer 4, cable, described hydrostatic level 1 is connected with data acquisition unit 2 by cable, and described data acquisition unit 2 is connected with host computer 4 by communication network.Described communication network is GPRS network or 3G network.
Described hydrostatic level 1 is the RJ-S type condenser type hydrostatic level that southern auspicious dam engineering is monitored branch office's development.Hydrostatic level 1 adopts the capacitor induction type hydrostatic level, and this instrument is according to the method for connecting pipe principle, measures the relative variation that elevation and liquid level are installed in each measuring point container contents device bottom surface.Try to achieve the relative settlement amount of each point by calculating again with respect to basic point.Hydrostatic level 1 is arranged in the girth joint position of pipeline section, respectively arranges 1 in the both sides of joint, for cut and cover method, then along backplane, and respectively arranges 1 in the subsiding crack both sides.

Claims (4)

1. the settling amount monitoring device of an electric power tunnel, it is characterized in that, comprise hydrostatic level, data acquisition unit, communication network, host computer, cable, described hydrostatic level is connected with data acquisition unit by cable, and described data acquisition unit is connected with host computer by communication network.
2. the settling amount monitoring device of a kind of electric power tunnel according to claim 1 is characterized in that, described hydrostatic level is the RJ-S type condenser type hydrostatic level that southern auspicious dam engineering is monitored branch office's development.
3. the settling amount monitoring device of a kind of electric power tunnel according to claim 1 is characterized in that, described communication network is GPRS network or 3G network.
4. the settling amount monitoring device of a kind of electric power tunnel according to claim 1 is characterized in that, described data acquisition unit is a DATA GeoLogger DT515 automatic data collection device.
CN2010206005843U 2010-11-10 2010-11-10 Settling amount monitoring device for power tunnel Expired - Fee Related CN201892535U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206005843U CN201892535U (en) 2010-11-10 2010-11-10 Settling amount monitoring device for power tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206005843U CN201892535U (en) 2010-11-10 2010-11-10 Settling amount monitoring device for power tunnel

Publications (1)

Publication Number Publication Date
CN201892535U true CN201892535U (en) 2011-07-06

Family

ID=44222009

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206005843U Expired - Fee Related CN201892535U (en) 2010-11-10 2010-11-10 Settling amount monitoring device for power tunnel

Country Status (1)

Country Link
CN (1) CN201892535U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104635600A (en) * 2015-01-13 2015-05-20 北京交通大学 Magnetic static leveling settlement automatic monitoring system
CN105297791A (en) * 2015-10-26 2016-02-03 贾晓轻 Substation monitoring system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104635600A (en) * 2015-01-13 2015-05-20 北京交通大学 Magnetic static leveling settlement automatic monitoring system
CN105297791A (en) * 2015-10-26 2016-02-03 贾晓轻 Substation monitoring system

Similar Documents

Publication Publication Date Title
CN201892527U (en) Pipe section joint opening monitoring device for electric power tunnels
CN102692885B (en) Monitoring drainage control method of stray current
CN203104460U (en) Power line carrier communication simulation test system
CN103217953A (en) System and method for temperature control and crack prevention intelligent monitoring of concrete dam
CN201237502Y (en) Automated monitoring system for dry sands of tailings reservoir
CN106885602A (en) Transmission tower dynamic response monitoring system and its application under a kind of wind action
CN205785327U (en) Urban Underground pipe gallery dynamic monitoring based on Internet of Things and early warning system
CN109405924A (en) A kind of online remote supervision system of drainage pipeline networks liquid level and method
CN105258728A (en) Iron tower online monitoring method and system
CN206470003U (en) A kind of offshore wind power generation basic utility automation safety monitoring assembly
CN204374177U (en) A kind of transmission line wire insulator contamination real-time monitoring system
CN201892535U (en) Settling amount monitoring device for power tunnel
CN111970382A (en) Iron tower safety monitoring and early warning system
CN103835360B (en) Automatic drainage system of box culvert road
CN201892519U (en) Structural crack monitoring device for electric power tunnels
CN203455440U (en) High-voltage single core cable protective layer grounding online monitoring device
CN204269106U (en) A kind of tunnel-type change monitoring system based on CORS base station
CN206223915U (en) A kind of ground insulator discharge monitoring device of double-current sensor
CN209085710U (en) A kind of online remote supervision system of drainage pipeline networks liquid level
CN203151743U (en) Intelligent short message data transmission sensor based on geotechnical engineering monitoring
CN202214741U (en) Wireless self-networked steel support stress monitoring system
CN203396492U (en) Temperature-control anti-cracking intelligent monitoring device of concrete dam
CN202119821U (en) Recognizing device of polarity electrification of DC transmission circuit
CN204374737U (en) A kind of water supply well management control system
CN102392256A (en) Wind/solar/electric complementary network anticorrosion system for buried steel pipelines

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110706

Termination date: 20111110