CN201857619U - Protective pile foundation - Google Patents

Protective pile foundation Download PDF

Info

Publication number
CN201857619U
CN201857619U CN2010206085551U CN201020608555U CN201857619U CN 201857619 U CN201857619 U CN 201857619U CN 2010206085551 U CN2010206085551 U CN 2010206085551U CN 201020608555 U CN201020608555 U CN 201020608555U CN 201857619 U CN201857619 U CN 201857619U
Authority
CN
China
Prior art keywords
foundation
pile
building
construction
fender pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010206085551U
Other languages
Chinese (zh)
Inventor
程龙先
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority to CN2010206085551U priority Critical patent/CN201857619U/en
Application granted granted Critical
Publication of CN201857619U publication Critical patent/CN201857619U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model relates to the field of civil engineering, in particular to a protective pile foundation. In the adopted technical scheme, the protective pile foundation comprises protective piles, the protective piles are arranged in an area between a foundation of an existing road or construction and a foundation of a new road or construction, and baffle plates are arranged among the protective piles. By adopting the technical scheme, the protective piles can prevent the foundation of the existing road or construction from collapsing during pit or trough construction, and can further support the baffle plates effectively, thereby the baffle plates can shield and isolate a soil layer of the foundation of the existing road or construction from a soil layer of the foundation of the new road or construction, and loosening of the foundation of the existing road or construction due to inter-pile soil collapse can be prevented.

Description

A kind of protection pile foundation
Technical field
The utility model relates to field of civil engineering, is specifically related to a kind of protection pile foundation.
Background technology
With road China rapid economy development, the transportation network of China is more and more closeer, and it is intensive that the building of structure come more.In road of newly building or building engineering; usually can run into from existing road or the very near situation of building; then the construction of new construction inevitably can have influence on existing engineering; especially in the foundation ditch of new construction, the groove construction; the ground regular meeting of the roadbed of existing road and building is because safeguard procedures and cave-in accident takes place improperly, all causes for the people's life and property and seriously influences.
The utility model content
The purpose of this utility model provides a kind of protection pile foundation, can effectively avoid ground occurring in closing on existing road or constructure construction procedure and cave in, and guarantees construction safety.
For achieving the above object, the utility model has adopted following technical scheme: a kind of protection pile foundation, comprise fender pile, fender pile is located at the zone between the ground of the ground of existing road or building and newly-built road or building, is provided with baffle plate between each fender pile.
By above technical scheme, fender pile can avoid the ground of existing road or building to subside in the process of construction foundation pit or groove, the while fender pile is supporting baffle effectively, help baffle plate the soil layer of the ground of existing road or building and the soil layer of newly-built road or structure foundation are stopped isolation, prevent from that the inter-pile soil body from collapsing to collapse to cause the loosening of existing road or structure foundation.
Description of drawings
Fig. 1 is the structural representation of this device.
The specific embodiment
A kind of protection pile foundation comprises fender pile 10, and fender pile 10 is located at the zone between the ground of the ground of existing road or building 30 and newly-built road or building 40, is provided with baffle plate 20 between each fender pile 10.The zone that fender pile 10 is located between the ground of the ground of existing road or building 30 and newly-built road or building 40 can avoid the ground of existing road or building to subside in work progress.The baffle plate 20 that is provided with between fender pile 10 can effectively prevent ground loosening caving in work progress that the inter-pile soil body collapses and collapses and cause existing road or building 30.
Fender pile 10 surrounds the U-shaped zone of protection to the extension of the both sides of newly-built road or building 40, baffle plate 20 verticals between each fender pile 10 are located at fender pile 10 near existing road or building one side and the layout that joins end to end, and are around in the side margins place of fender pile 10.So just between existing road or building 30 and newly-built road or building 40, formed an isolation strip; reduce to produce in the work progress ground loosening that the ground high vibration causes existing road or building 30 greatly, protected the ground of existing road or building 30.
Further, described fender pile 10 is the stake of reinforced concrete structure circular hole, and the top of fender pile 10 is concordant with the ground basal plane of existing road or building 30.Can guarantee the isolating and protecting effect of fender pile 10 like this, simultaneously influence minimum, pour into steel concrete after fender pile 10 adopts manually digging holes for what the ground to existing road or building 30 of guaranteeing to construct produced.

Claims (4)

1. one kind is protected pile foundation, it is characterized in that: comprise fender pile (10), fender pile (10) is located at the zone between the ground of the ground of existing road or building (30) and newly-built road or building (40), is provided with baffle plate (20) between each fender pile (10).
2. a kind of protection pile foundation according to claim 1 is characterized in that: described fender pile (10) and baffle plate (20) surround the U-shaped zone of protection to the extension of the both sides of newly-built road or building (40).
3. a kind of protection pile foundation according to claim 1 is characterized in that: described fender pile (10) is the stake of reinforced concrete structure circular hole, and the top of fender pile (10) is concordant with the ground basal plane of existing road or building (30).
4. a kind of protection pile foundation according to claim 1, it is characterized in that: baffle plate (20) vertical between described each fender pile (10) is located at fender pile (10) near existing road or building one side and the layout that joins end to end, and is around in the side margins place of fender pile (10).
CN2010206085551U 2010-11-16 2010-11-16 Protective pile foundation Expired - Fee Related CN201857619U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010206085551U CN201857619U (en) 2010-11-16 2010-11-16 Protective pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010206085551U CN201857619U (en) 2010-11-16 2010-11-16 Protective pile foundation

Publications (1)

Publication Number Publication Date
CN201857619U true CN201857619U (en) 2011-06-08

Family

ID=44103429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010206085551U Expired - Fee Related CN201857619U (en) 2010-11-16 2010-11-16 Protective pile foundation

Country Status (1)

Country Link
CN (1) CN201857619U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114611A (en) * 2013-03-01 2013-05-22 同济大学 Multistage cut-off method for underpass high-speed rail bridge opening deformation
CN111395059A (en) * 2020-03-23 2020-07-10 中铁二院工程集团有限责任公司 Light roadbed structure crossing karez, design and construction method
CN111926866A (en) * 2020-08-20 2020-11-13 同济大学 Obstacle encountering implementation method for reinforcing isolation pile in shield construction near high-speed railway
CN113187555A (en) * 2021-04-30 2021-07-30 安徽建筑大学 Method for reducing surface subsidence range caused by underground mining in plain mining area
CN113530597A (en) * 2021-07-22 2021-10-22 淮北矿业(集团)有限责任公司 Stress barrier type mining subsidence area earth surface structure protection method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114611A (en) * 2013-03-01 2013-05-22 同济大学 Multistage cut-off method for underpass high-speed rail bridge opening deformation
CN111395059A (en) * 2020-03-23 2020-07-10 中铁二院工程集团有限责任公司 Light roadbed structure crossing karez, design and construction method
CN111926866A (en) * 2020-08-20 2020-11-13 同济大学 Obstacle encountering implementation method for reinforcing isolation pile in shield construction near high-speed railway
CN113187555A (en) * 2021-04-30 2021-07-30 安徽建筑大学 Method for reducing surface subsidence range caused by underground mining in plain mining area
CN113187555B (en) * 2021-04-30 2023-06-23 安徽建筑大学 Method for reducing surface subsidence range caused by underground mining of plain mining area
CN113530597A (en) * 2021-07-22 2021-10-22 淮北矿业(集团)有限责任公司 Stress barrier type mining subsidence area earth surface structure protection method

Similar Documents

Publication Publication Date Title
CN203320532U (en) Protection device of nearby pile foundation close to deep foundation pit
CN201857619U (en) Protective pile foundation
CN104452809A (en) Ultra-shallow buried tunnel cover-excavation construction method
CN205742175U (en) A kind of steel construction protection wall of bored pile
CN105507610B (en) The lower base isolation reinforcement method for digging increasing layer of existing pile foundation building
CN202689031U (en) Deep foundation pit retaining and protecting retaining wall
CN203547753U (en) Profile steel concrete shaft wall base
CN203716046U (en) Steel trestle for earthwork transportation of foundation pit
CN204266132U (en) Adopt the railway Frame Pier crossbeam of D type beam
CN201991009U (en) Deep foundation pit shoring system using poured slope-supporting piles and anchor ropes
CN101899831B (en) Active variable-stiffness leveling pile and construction method thereof
CN202745063U (en) Deep foundation pit steel plate pile and anchor cable shoring system construction structure
CN104405402A (en) Symmetric middle separation wall construction method for hidden type middle wall multi-arch tunnel
CN204040042U (en) A kind of super large ultra-deep support with manually dug piles structure
CN203049588U (en) Pit-in-pit cylindrical mould
CN215165641U (en) Supporting structure adopting combination of triangular supports and Larsen steel sheet piles
CN201972711U (en) Device for controlling deformation of near metro tunnel caused by super-deep foundation pit evacuation in soft soil areas
CN206308700U (en) A kind of Traffic Engineering Construction slope protection device
CN207512723U (en) A kind of structure construction for promoting diaphram wall surface concrete quality
CN106978796B (en) Method for rapidly stabilizing dam
CN203891045U (en) Leakage blocking and grouting device between deep foundation pit fender posts
CN202577344U (en) L-shaped retaining wall structure
CN202543948U (en) Support device for excavation of deep foundation pit of piping trench of urban main road
CN102900026A (en) Construction method for protecting bridge surface by reinforcing elevated bridge foundation at tunnel excavation section
CN202881930U (en) Reusable steel guide wall used on underground diaphragm wall grooving construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110608

Termination date: 20131116