CN111926866A - Obstacle encountering implementation method for reinforcing isolation pile in shield construction near high-speed railway - Google Patents

Obstacle encountering implementation method for reinforcing isolation pile in shield construction near high-speed railway Download PDF

Info

Publication number
CN111926866A
CN111926866A CN202010844334.2A CN202010844334A CN111926866A CN 111926866 A CN111926866 A CN 111926866A CN 202010844334 A CN202010844334 A CN 202010844334A CN 111926866 A CN111926866 A CN 111926866A
Authority
CN
China
Prior art keywords
piles
isolation
pile
speed railway
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010844334.2A
Other languages
Chinese (zh)
Other versions
CN111926866B (en
Inventor
王炳龙
狄宏规
杜伟
吴挺
盛灿军
储成伍
夏杰
周顺华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN202010844334.2A priority Critical patent/CN111926866B/en
Publication of CN111926866A publication Critical patent/CN111926866A/en
Application granted granted Critical
Publication of CN111926866B publication Critical patent/CN111926866B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Hydrology & Water Resources (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及铁路施工防护技术领域,尤其涉及一种临近高速铁路盾构施工隔离桩加固的遇障实施方法,该方法在临近高速铁路盾构施工过程中,根据被保护对象和隔离桩断开平面位置关系的不同,采用不同类型的隔离桩进行加固。针对临近高速铁路盾构施工穿越各种复杂障碍物问题,提出了针对性的隔离桩加固方案,安全经济、科学可行,可有效控制盾构施工引起的高速铁路线路变形,确保邻近高速铁路的运营安全和新建盾构隧道的施工安全;不仅可为类似工程提供有益参考,对提高临近高速铁路施工的建设水平与科技创新能力,引领我国高速铁路运营安全保障技术也具有重要意义。

Figure 202010844334

The invention relates to the technical field of railway construction protection, in particular to an obstacle implementation method for reinforcement of isolation piles adjacent to high-speed railway shield construction. Depending on the positional relationship, different types of isolation piles are used for reinforcement. Aiming at the problem that the shield construction of the nearby high-speed railway passes through various complex obstacles, a targeted isolation pile reinforcement scheme is proposed, which is safe, economical, scientific and feasible. It can effectively control the deformation of the high-speed railway line caused by the shield construction and ensure the operation of the adjacent high-speed railway Safety and construction safety of new shield tunnels; not only can provide a useful reference for similar projects, but also have important significance for improving the construction level and technological innovation ability of adjacent high-speed railway construction, and leading my country's high-speed railway operation safety assurance technology.

Figure 202010844334

Description

一种临近高速铁路盾构施工隔离桩加固的遇障实施方法A kind of obstacle implementation method for reinforcement of isolation piles in shield construction near high-speed railway

技术领域technical field

本发明涉及铁路施工防护技术领域,尤其涉及一种临近高速铁路盾构施工隔离桩加固的遇障实施方法。The invention relates to the technical field of railway construction protection, in particular to an obstacle implementation method for reinforcement of isolation piles adjacent to shield construction of high-speed railways.

背景技术Background technique

随着我国经济的快速发展,城市化进程发展迅速,在既有高速铁路周边开展邻近工程活动不可避免,邻近工程势必会对既有高铁的运营造成一定影响。然而,高速铁路对线下工程变形要求极为严格,对于无砟轨道高速铁路,邻近高铁施工引起的高速铁路线路变形仅容许2mm。如何有效地控制邻近工程施工对高铁线下结构及行车安全的影响已成为高铁建设中必须面对的问题,在临近高速铁路盾构施工时,常采用门式隔离桩进行加固,但在布置过程中,常因道路、桥梁墩基、管线等既有建(构)筑物无法实施,因此,针对临近高速铁路盾构施工,急需提出一种隔离桩遇障实施方法,有效控制盾构施工对高速铁路的影响,确保高速铁路线下结构及行车安全。With the rapid development of my country's economy and the rapid development of urbanization, it is inevitable to carry out adjacent engineering activities around the existing high-speed railway, and the adjacent engineering will inevitably have a certain impact on the operation of the existing high-speed railway. However, high-speed railways have extremely strict requirements on off-line engineering deformation. For ballastless high-speed railways, the deformation of high-speed railway lines caused by the construction of adjacent high-speed railways is only allowed to be 2mm. How to effectively control the impact of adjacent engineering construction on the structure and driving safety of the high-speed railway line has become a problem that must be faced in the construction of high-speed railways. In the shield construction of adjacent high-speed railways, portal isolation piles are often used for reinforcement, but during the layout process It is often impossible to implement existing structures (structures) such as roads, bridge pier foundations, pipelines, etc. Therefore, for shield construction near high-speed railways, it is urgent to propose an implementation method for isolation piles in case of obstacles to effectively control the impact of shield construction. The impact of the high-speed railway ensures the safety of the structure and traffic under the high-speed railway line.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于,提出了一种临近高速铁路盾构施工隔离桩加固的遇障实施方法,根据被保护对象和隔离桩断开平面位置关系的不同进行分类加固,克服了门式隔离桩遇障无法实施的问题,有效减小了盾构施工对临近待保护对象的影响,确保施工安全。The purpose of the present invention is to propose an implementation method for the reinforcement of isolation piles in shield construction near high-speed railways in case of obstacles. It can effectively reduce the impact of shield construction on nearby objects to be protected and ensure construction safety.

本发明的目的可通过以下技术方案来实现:The object of the present invention can be realized through the following technical solutions:

一种临近高速铁路盾构施工隔离桩加固的遇障实施方法,包括:A method for implementing obstacles in the reinforcement of isolation piles adjacent to shield construction of high-speed railways, comprising:

在临近高速铁路盾构施工过程中,根据被保护对象和隔离桩断开平面位置关系的不同,采用不同类型的隔离桩进行加固。In the process of shield tunnel construction near the high-speed railway, different types of isolation piles are used for reinforcement according to the difference in the positional relationship between the protected object and the disconnected plane of the isolation pile.

优选的,包括:Preferred include:

S1:首先通过数值计算,确定钻孔灌注桩的直径、长度、间距以及横撑的尺寸、间距;S1: First, determine the diameter, length, spacing of bored piles, and the size and spacing of transverse braces through numerical calculation;

S2:在临近被保护对象盾构施工普通段,采用门式隔离桩进行加固;当待保护对象位于隔离桩断开处的同侧时,采用L型隔离桩进行加固;当被保护对象位于隔离桩断开处的对侧时,采用双排隔离桩进行加固;当遇见连续分布的复杂障碍物,采用L型隔离桩和双排隔离桩相结合的方式进行加固。S2: In the ordinary section of shield construction adjacent to the protected object, use portal isolation piles for reinforcement; when the object to be protected is located on the same side of the isolation pile disconnection, use L-shaped isolation piles for reinforcement; when the protected object is located in the isolation pile Double-row isolation piles are used for reinforcement when the pile is on the opposite side of the disconnection; when encountering complex obstacles that are continuously distributed, a combination of L-shaped isolation piles and double-row isolation piles is used for reinforcement.

更优选的,所述门式隔离桩通过以下方法得到:在盾构隧道的两侧分别间隔施工一排钻孔灌注桩,所述钻孔灌注桩的顶部设置有冠梁,两侧的钻孔灌注桩采用横撑连接,形成门式隔离桩。More preferably, the portal isolation pile is obtained by the following method: constructing a row of bored cast-in-situ piles at intervals on both sides of the shield tunnel, the top of the bored cast-in-situ pile is provided with a crown beam, and the boreholes on both sides are provided with a crown beam. The cast-in-place piles are connected by transverse braces to form portal isolation piles.

更优选的,所述L型隔离桩通过以下方法得到:More preferably, the L-shaped isolation pile is obtained by the following method:

将钻孔灌注桩顶部设置冠梁,并与非断开处的门式隔离桩之间设置水平斜撑,水平斜撑间采用横撑连,形成L型隔离桩。A crown beam is set on the top of the bored cast-in-place pile, and horizontal diagonal braces are set between the non-disconnected portal isolation piles, and horizontal bracing is used to connect the horizontal diagonal braces to form an L-shaped isolation pile.

更优选的,所述双排隔离桩通过以下方法得到:More preferably, the double-row isolation piles are obtained by the following methods:

首先设置前后两排钻孔灌注桩,在所述钻孔灌注桩的顶部设置冠梁,前后钻孔灌注桩之间设置系梁,后排桩与门式隔离桩顺接,形成双排隔离桩。First, two rows of front and rear bored cast-in-place piles are set, crown beams are set on the top of the bored cast-in-situ piles, tie beams are set between the front and rear bored cast-in-situ piles, and the rear row of piles are connected with the portal isolation piles to form double-row isolation piles .

优选的,所述被保护对象包括但不限于高铁桥梁墩基。Preferably, the protected objects include but are not limited to high-speed rail bridge pier foundations.

优选的,所述隔离桩底部设置有护筒。Preferably, a protective tube is provided at the bottom of the isolation pile.

在本发明的一些优选的具体实施例中,一种用于临近高速铁路盾构施工门式隔离桩加固的遇障实施方法,包括以下工况:In some preferred specific embodiments of the present invention, a method for implementing obstacles in the reinforcement of gate-type isolation piles adjacent to shield construction of high-speed railways includes the following working conditions:

(1)在临近高速铁路盾构施工普通段:在盾构段两侧施工钻孔灌注桩,顶部设置冠梁,两侧排桩采用横撑连接,以形成门式隔离桩。(1) In the ordinary section of shield construction adjacent to the high-speed railway: construct bored piles on both sides of the shield section, set up crown beams on the top, and connect the rows of piles on both sides with transverse braces to form portal isolation piles.

(2)当被保护对象位于隔离桩断开处的同侧:在断开处向被保护对象施工钻孔灌注桩至其对侧,顶部设置冠梁,并与非断开处的门式隔离桩之间设置水平斜撑,斜撑间布置横撑以提高斜撑的稳定性,以形成L型隔离桩。如果L型隔离桩不具备延伸条件,可以采用适当减小桩径、钢护筒跟进成桩等方法保证隔离桩的延伸满足条件。(2) When the protected object is located on the same side of the disconnection point of the isolation pile: construct a bored cast-in-place pile to the protected object at the disconnection point to the opposite side, set a crown beam on the top, and isolate it from the door type at the non-disconnection point Horizontal diagonal bracing is arranged between the piles, and horizontal bracing is arranged between the diagonal bracing to improve the stability of the diagonal bracing to form an L-shaped isolated pile. If the L-shaped isolation pile does not meet the extension conditions, methods such as appropriately reducing the pile diameter and following up the steel casing to form a pile can be used to ensure that the extension of the isolation pile meets the conditions.

(3)当被保护对象位于隔离桩断开处的对侧:在断开处对侧施工两排钻孔灌注桩,顶部设置冠梁,前后排桩之间设置系梁,后排桩与普通段门式隔离桩顺接,以形成双排隔离桩。如果双排隔离桩的前排桩距离被保护对象过近,困难地段采用钢护筒跟进成桩等方法保证隔离桩的设置。(3) When the protected object is located on the opposite side of the disconnection of the isolation pile: construct two rows of bored cast-in-place piles on the opposite side of the disconnection, set a crown beam on the top, set a tie beam between the front and rear rows of piles, and set the back row of piles with the common The segment gate type isolation piles are connected to form double row isolation piles. If the front row of double-row isolation piles is too close to the protected object, the installation of isolation piles can be ensured by using steel casings to follow up to form piles in difficult areas.

(4)当遇见连续分布的复杂障碍物,可将(2)和(3)中的两种方法结合使用。(4) When encountering complex obstacles with continuous distribution, the two methods in (2) and (3) can be used in combination.

上述隔离桩的直径、长度、间距可通过数值计算在满足安全性要求、经济性要求、施工可行性等条件综合确定。The diameter, length, and spacing of the above-mentioned isolation piles can be comprehensively determined through numerical calculation under the conditions of meeting safety requirements, economic requirements, and construction feasibility.

本发明第二个方面公开了上述方法在铁路施工防护技术领域中的应用。The second aspect of the present invention discloses the application of the above method in the technical field of railway construction protection.

在符合本领域常识的基础上,上述各优选条件,可任意组合,而不超出本发明的构思与保护范围。On the basis of conforming to common knowledge in the art, the above preferred conditions can be combined arbitrarily without departing from the concept and protection scope of the present invention.

本发明相对于现有技术具有如下的显著优点及效果:Compared with the prior art, the present invention has the following significant advantages and effects:

针对临近高速铁路盾构施工穿越各种复杂障碍物问题,提出了针对性的隔离桩加固方案,安全经济、科学可行,可有效控制盾构施工引起的高速铁路线路变形,确保邻近高速铁路的运营安全和新建盾构隧道的施工安全;不仅可为类似工程提供有益参考,对提高临近高速铁路施工的建设水平与科技创新能力,引领我国高速铁路运营安全保障技术也具有重要意义。Aiming at the problem that the shield construction of the nearby high-speed railway passes through various complex obstacles, a targeted isolation pile reinforcement scheme is proposed, which is safe, economical, scientific and feasible. It can effectively control the deformation of the high-speed railway line caused by the shield construction and ensure the operation of the adjacent high-speed railway Safety and construction safety of new shield tunnels; not only can provide a useful reference for similar projects, but also have important significance for improving the construction level and technological innovation ability of adjacent high-speed railway construction, and leading my country's high-speed railway operation safety assurance technology.

附图说明Description of drawings

图1为本发明隔离桩遇障实施示意图;Fig. 1 is the implementation schematic diagram of the isolation pile encountering obstacles of the present invention;

图2为盾构隧道与既有道路交叉节点处门式隔离桩实施示意图;Fig. 2 is a schematic diagram of the implementation of portal isolation piles at the intersection of shield tunnels and existing roads;

图3为超近距临近既有桥梁墩基盾构施工门式隔离桩实施示意图;Figure 3 is a schematic diagram of the implementation of gate isolation piles for shield construction of pier foundations adjacent to existing bridges at a super close distance;

图中,1—盾构隧道,2—钻孔灌注桩,3—冠梁,4—横撑,5—待保护对象,6—斜撑,7—系梁,8—高铁桥梁墩基,9—L型隔离桩,10—道路,11—双排隔离桩,12—既有桥梁墩基。In the figure, 1—shield tunnel, 2—bored pile, 3—crown beam, 4—cross brace, 5—object to be protected, 6—diagonal brace, 7—tie beam, 8—high-speed rail bridge pier foundation, 9 -L-shaped isolation pile, 10-road, 11-double row isolation pile, 12-existing bridge pier foundation.

具体实施方式Detailed ways

下面结合附图和实施例对本发明的技术方案进行详细描述,但并不因此将本发明限制在所述的实施例范围之中。The technical solutions of the present invention will be described in detail below with reference to the accompanying drawings and embodiments, but the present invention is not limited to the scope of the described embodiments.

如图1所示,一种临近高速铁路盾构施工隔离桩加固的遇障实施方法具体分为:As shown in Figure 1, a method of implementing obstacles for reinforcement of isolation piles adjacent to shield construction of high-speed railways is specifically divided into:

首先通过数值计算,确定钻孔灌注桩的直径、长度、间距以及横撑的尺寸、间距。Firstly, through numerical calculation, determine the diameter, length, spacing of bored piles, and the size and spacing of transverse braces.

在临近高速铁路盾构施工普通段,在盾构隧道1两侧分别按照一定间距施工一排钻孔灌注桩2,顶部设置冠梁3,两侧排桩采用横撑4连接,形成门式隔离桩,以降低盾构施工临近待保护对象5的影响,待保护对象包括但不仅限于高铁桥梁墩基8。In the ordinary section of shield construction near the high-speed railway, a row of bored cast-in-place piles 2 are constructed at certain intervals on both sides of the shield tunnel 1, and crown beams 3 are set on the top. piles, so as to reduce the impact of shield construction near the object to be protected 5 , and the object to be protected includes but is not limited to the high-speed rail bridge pier foundation 8 .

当被保护对象位于隔离桩断开处的同侧时,如图2所示,在盾构隧道1与既有道路10交叉节点,门式隔离桩无法连续设置,因此采用L型隔离桩9布置方案对高铁桥墩8进行防护,采用一定间距的钻孔灌注桩2使“L”型防护桩延伸至桥墩8承台对侧,顶部设置冠梁3,并与非断开处的门式隔离桩之间设置水平斜撑6,斜撑间布置横撑以提高斜撑的稳定性。为了减小施工对沪昆高铁桥墩8变形的影响,距离沪昆高铁桥梁桩基6m范围内的所有防护钻孔桩采用全护筒跟进的方法施工;距离沪昆高铁桥梁桩基6~10m范围内的所有防护钻孔桩采用护筒部分跟进的方法施工,护筒跟进范围为地表至淤泥质粉质粘土层的层底,从而减小隔离桩成孔过程对沪昆高铁桥梁的影响。When the protected object is located on the same side of the disconnection of the isolation pile, as shown in Figure 2, at the intersection of shield tunnel 1 and existing road 10, the portal isolation pile cannot be continuously installed, so the L-shaped isolation pile 9 is used. The plan is to protect the high-speed railway pier 8, using bored piles 2 with a certain spacing to extend the "L" type protection pile to the opposite side of the pier 8 cap, and set the crown beam 3 on the top, and the non-disconnected portal isolation pile. Horizontal diagonal braces 6 are arranged between the diagonal braces, and horizontal braces are arranged between the diagonal braces to improve the stability of the diagonal braces. In order to reduce the impact of construction on the deformation of the Shanghai-Kunming high-speed railway bridge pier 8, all the protective bored piles within 6m from the Shanghai-Kunming high-speed railway bridge pile foundation shall be constructed by the method of full casing follow-up; All the protective bored piles within the scope are constructed by the method of partial follow-up of the casing. The follow-up range of the casing is from the surface to the bottom of the silty silty clay layer, so as to reduce the impact of the hole-forming process of the isolation pile on the Shanghai-Kunming high-speed railway bridge. influences.

当被保护对象位于隔离桩断开处的对侧时,如图3所示,盾构隧道1距离既有桥梁墩基12较近,该处无条件实施隔离桩,因此高铁桥梁墩基8附近隔离桩为双排隔离桩11,在断开处对侧施工两排钻孔灌注桩2,顶部设置冠梁3,前后排桩之间设置系梁7,后排桩与普通段门式隔离桩顺接,其中双排隔离桩11间距、双排隔离桩11间系梁7间距可通过数值计算综合各种因素确定,如果双排隔离桩11的前排桩距离被高铁桥梁墩基8过近,困难地段采用钢护筒跟进成桩等方法保证隔离桩的设置。When the protected object is located on the opposite side of the disconnection of the isolation pile, as shown in Figure 3, the shield tunnel 1 is relatively close to the existing bridge pier 12, and the isolation pile is unconditionally implemented there, so the high-speed railway bridge pier 8 is isolated near the foundation 8. The piles are double-row isolation piles 11, two rows of bored cast-in-place piles 2 are constructed on the opposite side of the disconnection, crown beams 3 are arranged on the top, tie beams 7 are arranged between the front and rear rows of piles, and the rear row of piles are in line with the common section portal isolation piles. The distance between the double-row isolation piles 11 and the tie beams 7 between the double-row isolation piles 11 can be determined by combining various factors through numerical calculation. In difficult areas, steel casings are used to follow up to form piles to ensure the installation of isolation piles.

当遇见连续分布的复杂障碍物,可将L型隔离桩9和双排隔离桩11结合使用。When encountering complex obstacles that are continuously distributed, the L-shaped isolation piles 9 and the double-row isolation piles 11 can be used in combination.

上述对实施例子的描述是为了便于该技术领域的普通技术人员能理解和应用本发明。熟悉本领域技术的人员显然可以容易地对这些实施例进行各种修改,并把在此说明的一般原理应用到其他实施例中而不必经过创造性的劳动。因此,本发明不限于这里的实施例,本领域技术人员根据本发明的揭示,不脱离本发明范畴所做出的改进和修改都应该在本发明的保护范围之内。The above description of the embodiments is for the convenience of those of ordinary skill in the art to understand and apply the present invention. It will be apparent to those skilled in the art that various modifications to these embodiments can be readily made, and the general principles described herein can be applied to other embodiments without inventive step. Therefore, the present invention is not limited to the embodiments herein, and improvements and modifications made by those skilled in the art according to the disclosure of the present invention without departing from the scope of the present invention should all fall within the protection scope of the present invention.

Claims (8)

1. A barrier encountering implementation method for reinforcing an isolation pile in shield construction close to a high-speed railway is characterized by comprising the following steps of:
in the shield construction process near the high-speed railway, different types of isolation piles are adopted for reinforcement according to different position relations between a protected object and the isolation pile disconnection plane.
2. The method of claim 1, comprising:
s1: firstly, determining the diameter, the length and the spacing of the bored pile and the size and the spacing of the cross braces through numerical calculation;
s2: reinforcing a shield construction common section close to a protected object by adopting a gate type isolation pile; when the object to be protected is positioned at the same side of the disconnected position of the isolation pile, the L-shaped isolation pile is adopted for reinforcement; when the protected object is positioned on the opposite side of the disconnected position of the isolation piles, reinforcing by adopting double rows of isolation piles; when complex obstacles which are continuously distributed are encountered, the L-shaped isolation piles and the double rows of isolation piles are combined for reinforcement.
3. The method of claim 2, wherein the door-type spacer pile is obtained by: and constructing a row of cast-in-situ bored piles at two sides of the shield tunnel at intervals respectively, wherein the top of each cast-in-situ bored pile is provided with a crown beam, and the cast-in-situ bored piles at two sides are connected by adopting cross braces to form a gate type isolation pile.
4. The method according to claim 2, wherein the L-shaped spacer pile is obtained by:
and arranging a crown beam at the top of the cast-in-situ bored pile, arranging horizontal inclined struts between the gate type isolation piles at the non-disconnected positions, and connecting the horizontal inclined struts by adopting cross struts to form the L-shaped isolation pile.
5. The method of claim 2, wherein the double row of spacer piles is obtained by:
the method comprises the following steps of firstly arranging front and rear rows of cast-in-situ bored piles, arranging a crown beam at the top of each cast-in-situ bored pile, arranging a tie beam between the front and rear cast-in-situ bored piles, and connecting the rear row of piles with a gate type isolation pile in a sequential manner to form double rows of isolation piles.
6. The method of claim 1, wherein the protected object is a high-speed railway pier footing.
7. The method of claim 1, wherein the bottom of the spacer pile is provided with a casing.
8. Use of the method according to any one of claims 1 to 7 in the technical field of railway construction protection.
CN202010844334.2A 2020-08-20 2020-08-20 Obstacle encountering implementation method for reinforcing isolation pile in shield construction near high-speed railway Active CN111926866B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010844334.2A CN111926866B (en) 2020-08-20 2020-08-20 Obstacle encountering implementation method for reinforcing isolation pile in shield construction near high-speed railway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010844334.2A CN111926866B (en) 2020-08-20 2020-08-20 Obstacle encountering implementation method for reinforcing isolation pile in shield construction near high-speed railway

Publications (2)

Publication Number Publication Date
CN111926866A true CN111926866A (en) 2020-11-13
CN111926866B CN111926866B (en) 2021-09-21

Family

ID=73304899

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010844334.2A Active CN111926866B (en) 2020-08-20 2020-08-20 Obstacle encountering implementation method for reinforcing isolation pile in shield construction near high-speed railway

Country Status (1)

Country Link
CN (1) CN111926866B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4183137B2 (en) * 2005-12-07 2008-11-19 英将 太田 Seismic structure
CN201857619U (en) * 2010-11-16 2011-06-08 中铁十局集团第三建设有限公司 Protective pile foundation
CN103114611A (en) * 2013-03-01 2013-05-22 同济大学 Multistage cut-off method for underpass high-speed rail bridge opening deformation
CN108867692A (en) * 2018-07-18 2018-11-23 中铁十二局集团第二工程有限公司 The protection of city big cross section open trench tunnel Nearby Structure and tunnel foundation pit method for digging
CN109440545A (en) * 2018-11-30 2019-03-08 中铁第四勘察设计院集团有限公司 The road structure and construction method of operation high-speed railway are worn under a kind of
CN110528594A (en) * 2019-07-31 2019-12-03 浙江杭海城际铁路有限公司 A kind of tunneling shield causes the guard method of neighbour's high-speed rail deformation of pile foundation
CN111139721A (en) * 2020-01-16 2020-05-12 中铁第五勘察设计院集团有限公司 Frame bridge penetrating existing railway bridge downwards and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4183137B2 (en) * 2005-12-07 2008-11-19 英将 太田 Seismic structure
CN201857619U (en) * 2010-11-16 2011-06-08 中铁十局集团第三建设有限公司 Protective pile foundation
CN103114611A (en) * 2013-03-01 2013-05-22 同济大学 Multistage cut-off method for underpass high-speed rail bridge opening deformation
CN108867692A (en) * 2018-07-18 2018-11-23 中铁十二局集团第二工程有限公司 The protection of city big cross section open trench tunnel Nearby Structure and tunnel foundation pit method for digging
CN109440545A (en) * 2018-11-30 2019-03-08 中铁第四勘察设计院集团有限公司 The road structure and construction method of operation high-speed railway are worn under a kind of
CN110528594A (en) * 2019-07-31 2019-12-03 浙江杭海城际铁路有限公司 A kind of tunneling shield causes the guard method of neighbour's high-speed rail deformation of pile foundation
CN111139721A (en) * 2020-01-16 2020-05-12 中铁第五勘察设计院集团有限公司 Frame bridge penetrating existing railway bridge downwards and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王国富等: "小半径盾构下穿高铁桥支护优化及变形控制研究", 《防灾减灾工程学报》 *

Also Published As

Publication number Publication date
CN111926866B (en) 2021-09-21

Similar Documents

Publication Publication Date Title
Li et al. Numerical simulation and analysis of the pile underpinning technology used in shield tunnel crossings on bridge pile foundations
CN100554646C (en) Shield method combines the job practices of building the subway station with shallow burial hidden digging
CN105003272B (en) Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways
CN109914456A (en) A design and construction method when a bridge and a subway tunnel are adjacent to a new construction or are built at the same time
CN110528531A (en) A method of it utilizes and does close to foundation pit enclosure stake to excavation pit fender post
CN103485791A (en) Construction method for in-situ maintenance or extension of road tunnel
CN104532849B (en) A method for excavating a foundation pit above an operating subway tunnel
CN114457849B (en) Construction method for crossing existing subway cross section protection system on open cut tunnel
CN111411992A (en) Integrated structural system and its construction method passing through giant karst caves
CN204716248U (en) Tunnel Heng Dong enters main hole and to caunch structure
CN104775368A (en) Prefabricated jacking box culvert provided with steel blade corners
CN111926866A (en) Obstacle encountering implementation method for reinforcing isolation pile in shield construction near high-speed railway
CN111911169B (en) A shallow buried deep tunnel construction method and structure under an existing railway line
CN108798681A (en) What middle hole method zero distance passed through existing subway station underpins system and its construction method
CN105735056A (en) Method for reinforcing railway through piling girders combined with I-steel cross girders
CN112983493A (en) Reinforcing structure for shield to closely penetrate large-section bridge and culvert downwards and construction method
CN113235639A (en) Existing line lower row pile enclosure structure and construction method thereof
Konukhov et al. Ensuring the safety of the existing buildings during the construction of the underground in Moscow
CN103334451A (en) Underneath-passing channel formed between high-speed rail piers through secant pile walls and method thereof
CN116255162A (en) Reverse construction structure of multi-arch tunnel under scarp condition and construction method thereof
CN212154795U (en) Integrated structural system through giant karst caves
CN206144569U (en) Confined is advance in advance and is protected tunnel structure
CN208605183U (en) What a kind of middle hole method zero distance passed through existing subway station underpins system
CN113389218A (en) Retaining wall structure for entrance and exit of road bridge and construction method thereof
CN219472115U (en) Single-head tunneling reverse construction structure of multi-arch tunnel under scarp condition

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant