CN201826541U - Detachable reinforcing steel processing shed - Google Patents

Detachable reinforcing steel processing shed Download PDF

Info

Publication number
CN201826541U
CN201826541U CN201020257887XU CN201020257887U CN201826541U CN 201826541 U CN201826541 U CN 201826541U CN 201020257887X U CN201020257887X U CN 201020257887XU CN 201020257887 U CN201020257887 U CN 201020257887U CN 201826541 U CN201826541 U CN 201826541U
Authority
CN
China
Prior art keywords
roof truss
columns
reinforcing bar
post
purlin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201020257887XU
Other languages
Chinese (zh)
Inventor
陈守国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mcc13 Construction Co ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CMTCC Shanghai Shisanye Construction Co Ltd filed Critical CMTCC Shanghai Shisanye Construction Co Ltd
Priority to CN201020257887XU priority Critical patent/CN201826541U/en
Application granted granted Critical
Publication of CN201826541U publication Critical patent/CN201826541U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to the technical field of processing sheds, in particular to a detachable reinforcing steel processing shed, which comprises independent foundations under columns, the columns, a roof truss, purlins, a roofing board and a ridge folding piece, wherein the independent foundations under the columns are pre-embedded screws, and one ends of the columns are connected with the independent foundations under the columns; the other ends of the columns are connected with the roof truss, and the roof truss is connected with the purlins; and the roofing board is arranged on the purlins, and the ridge folding piece consists of color plates. The roof truss and the columns, and the purlins and the roof truss are in bolted connection by connecting plates, so that the whole structure can be detached, and the shed can be transferred to the next project to be reused after the completion of a project, thereby reducing production cost; and the structure is relatively safe and can bear certain wind and snow loads, and the reinforcing steel processing shed has safety and obvious effect compared with the traditional simple reinforcing steel processing shed.

Description

Detachable reinforcing bar adds builder's temporary shed
Technical field
The utility model relates to a kind of builder's temporary shed that adds, and relates in particular to a kind of detachable reinforcing bar and adds builder's temporary shed.
Background technology
The reinforcing bar processing space is the requisite operation place of construction enterprises' site operation, and the reinforcing bar processing space of standard is a necessary condition of creating the civilized building site of markization.Present stage, the reinforcing bar operation place of construction enterprises was various, the simple and easy reinforcing bar of tradition just abandons after adding the builder's temporary shed use, increased cost, what have only is the beta site of scaffold tubes and color steel simple combination, on-the-spot placing of material is in disorder, and it is bigger to stack area simultaneously, and the rainy day also can't operation, in the modern work progress of standardized management,, influence corporate image often for enterprise blackens the name of.
Summary of the invention
The utility model is intended to address the above problem, and provides a kind of detachable reinforcing bar to add builder's temporary shed.It is in disorder that the utility model can solve the placing of material of reinforcing bar operation field, and it is bigger to stack area, and the rainy day can't operation, often for enterprise blackens the name of, influences the deficiency of corporate image in the modern work progress of standardized management.
The utility model is achieved in that a kind of detachable reinforcing bar adds builder's temporary shed, comprises independent foundation under column, post, roof truss, purlin, roof panel, ridge folding part, and described independent foundation under column is a pre embedded bolt; One end of described post is connected with independent foundation under column, and the other end of post is connected with roof truss; Described roof truss is provided with purlin and connects; Described purlin is provided with roof panel; Described ridge folding part is made up of color steel.
Described post is connected by 4 M20 high-strength bolts with independent foundation under column, and the other end of post is connected by 4 M20 high-strength bolts with roof truss.
Described roof truss is connected by 2 M16 high-strength bolts with purlin.
Described pillar is ф 114 * 4.5 steel pipes.
Described roof truss adopts the L50*5 angle steel to be made into single truss sheet, and single roof truss is spliced into herringbone with bolt.
Described purlin is made into by the indented bars combination of L40 * 4 angle steel and ф 16.
Described roof panel adopts the thick color steel of 0.4mm, and roof panel is laid in turn and stretched out cornice 150~200mm to cornice by ridge.
All be connected between roof truss of the present utility model and post, purlin and the roof truss, make total detachable, can be transferred to next engineering recycling after the engineering completion, reduce cost of manufacture by the junction plate bolt.The operating personnel concentrates the processing reinforcing bar, avoids the in disorder situation of on-the-spot placing of material, and area is bigger simultaneously, and temporarily depositing of on-the-spot Keep away from rain material can be carried out in plentiful space, is convenient to site safety and the management of civilization markization.Structure of the present utility model is comparatively safe, can bear certain wind and snow load, traditional relatively simple and easy reinforcing bar add builder's temporary shed safety and effect obvious.
Description of drawings
Below, in conjunction with the accompanying drawings the utility model is further described:
Fig. 1 is a structure chart of the present utility model;
Fig. 2 is partial structurtes figure of the present utility model.
The specific embodiment
As depicted in figs. 1 and 2: a kind of detachable reinforcing bar adds builder's temporary shed, comprise independent foundation under column 1, post 2, roof truss 3, purlin 5, roof panel 6, ridge folding part 4, described post 2 is ф 114 * 4.5 steel pipes, described roof truss 3 adopts the L50*5 angle steel to be made into single truss sheet, single roof truss is spliced into herringbone with bolt, described purlin 5 is made into by the indented bars combination of L40 * 4 angle steel and ф 16, described roof panel 6 adopts the thick color steel of 0.4mm, roof panel 6 is laid in turn and is stretched out cornice 150~200mm to cornice by ridge, and described independent foundation under column 1 is a pre embedded bolt 7; One end of described post 2 is connected with independent foundation under column 1, and the other end of post 2 is connected with roof truss 3, and described post 2 is connected by 4 M20 high-strength bolts with independent foundation under column 1, and the other end of post 2 is connected by 4 M20 high-strength bolts with roof truss 3; Described roof truss 3 is connected with purlin 5, and described roof truss 3 is connected by 2 M16 high-strength bolts with purlin 5; The upper end of described purlin 5 is connected with roof panel 6; Described ridge folding part 4 is made up of color steel.
Before adding builder's temporary shed, the making reinforcing bar at first determines to add the geographical position of builder's temporary shed, the unwrapping wire excavation is basic then, assembling reinforcement and pre embedded bolt 7, concreting, treat concrete setting, post 2 is installed and is proofreaied and correct, and pieces together roof truss 3 in advance, lifting roof truss 3, roof purline 5 is installed, lay roof panel 6, ridge folding part 4 is installed, ancillary facility is installed is at last got final product.

Claims (7)

1. a detachable reinforcing bar adds builder's temporary shed, comprises independent foundation under column (1), post (2), roof truss (3), purlin (5), roof panel (6) and ridge folding part (4), and it is characterized in that: described independent foundation under column (1) is a pre embedded bolt (7); One end of described post (2) is connected with independent foundation under column (1), and the other end of post (2) is connected with roof truss (3); Described roof truss (3) is provided with purlin (5); Described purlin (5) is provided with roof panel (6); Described ridge folding part (4) is made up of color steel.
2. detachable reinforcing bar as claimed in claim 1 adds builder's temporary shed, it is characterized in that: described post (2) is connected by high-strength bolt with independent foundation under column (1), and the other end of post (2) is connected by high-strength bolt with roof truss (3).
3. detachable reinforcing bar as claimed in claim 1 adds builder's temporary shed, it is characterized in that: described roof truss (3) also is connected by high-strength bolt with purlin (5).
4. detachable reinforcing bar as claimed in claim 1 adds builder's temporary shed, it is characterized in that: described post (2) is a steel pipe.
5. detachable reinforcing bar as claimed in claim 1 adds builder's temporary shed, it is characterized in that: described roof truss (3) adopts angle steel to be made into single truss sheet, and single roof truss is spliced into herringbone with bolt.
6. detachable reinforcing bar as claimed in claim 1 adds builder's temporary shed, it is characterized in that: described purlin (5) is made into by angle steel and indented bars combination.
7. detachable reinforcing bar as claimed in claim 1 adds builder's temporary shed, it is characterized in that: described roof panel (6) adopts color steel, and roof panel (6) is laid in turn and stretched out cornice 150~200mm to cornice by ridge.
CN201020257887XU 2010-07-13 2010-07-13 Detachable reinforcing steel processing shed Expired - Fee Related CN201826541U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201020257887XU CN201826541U (en) 2010-07-13 2010-07-13 Detachable reinforcing steel processing shed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201020257887XU CN201826541U (en) 2010-07-13 2010-07-13 Detachable reinforcing steel processing shed

Publications (1)

Publication Number Publication Date
CN201826541U true CN201826541U (en) 2011-05-11

Family

ID=43965087

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201020257887XU Expired - Fee Related CN201826541U (en) 2010-07-13 2010-07-13 Detachable reinforcing steel processing shed

Country Status (1)

Country Link
CN (1) CN201826541U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102953553A (en) * 2012-11-14 2013-03-06 中冶天工集团有限公司 Method for installing large-span pipe truss by utilizing boom luffing mechanism
CN104612412A (en) * 2014-12-22 2015-05-13 山西省第五建筑工程公司 Construction method of steel structure exit passageway
CN111395822A (en) * 2020-03-24 2020-07-10 上海外高桥造船有限公司 Wind and rain shed

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102953553A (en) * 2012-11-14 2013-03-06 中冶天工集团有限公司 Method for installing large-span pipe truss by utilizing boom luffing mechanism
CN102953553B (en) * 2012-11-14 2015-04-15 中冶天工集团有限公司 Method for installing large-span pipe truss by utilizing boom luffing mechanism
CN104612412A (en) * 2014-12-22 2015-05-13 山西省第五建筑工程公司 Construction method of steel structure exit passageway
CN111395822A (en) * 2020-03-24 2020-07-10 上海外高桥造船有限公司 Wind and rain shed

Similar Documents

Publication Publication Date Title
CN103352563B (en) The board-like bar frame gang form of self-supporting and construction method thereof
CN204040464U (en) A kind of slab form supporting construction
CN105019555A (en) Novel steel reinforced concrete shearing wallboard fabricated building system
CN206903022U (en) A kind of steel bar truss floor support plate
CN107023099A (en) Prefabricated superimposed sheet double combined overlapped shear wall and its construction method
CN206859479U (en) A kind of steel bar girder laminated floor slab
CN202990197U (en) Lap joint rib type prestress double-direction composite slab
CN201826541U (en) Detachable reinforcing steel processing shed
CN103741970A (en) Assembled machining shed for building construction and manufacture and installation method thereof
CN104863296A (en) Integrally modular steel bar truss floor plate and construction method thereof
CN113860190B (en) Cantilever crane turnover-free beam rest bracket and installation method
CN106836600A (en) A kind of reinforcing bar composite floor for power transformation engineering
CN201972417U (en) Lightweight wood structure roof system
CN104775572A (en) Pre-stressed precast canopy plate for railway platform
CN112922237A (en) Take telescopic assembled reinforced concrete post and girder steel connected node
CN211037598U (en) Roofing photovoltaic support
CN101775876A (en) Spacial steel roof truss
CN203603542U (en) Fabricated electronic workshop
CN205591579U (en) Adopt girder steel to consolidate aerated concrete roof boarding structure
CN102418414A (en) Long-slab-span prefabricated beam floor formwork system
CN205776981U (en) A kind of floor and the structure of making floor
CN211114317U (en) Steel bar truss composite floor slab
CN104453045B (en) Separate prefabricated truss frame floor bearing plate and construction method thereof
CN207295990U (en) A kind of large-span prestressed prefabricated industrial plant building
CN210195053U (en) Prefabricated plate and steel construction connected node

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee after: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: CMTCC Shanghai 13th Construction Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110511

Termination date: 20180713