CN201811251U - Automatic soot cleaning device for shell and tube type heat exchanger - Google Patents
Automatic soot cleaning device for shell and tube type heat exchanger Download PDFInfo
- Publication number
- CN201811251U CN201811251U CN2010205593481U CN201020559348U CN201811251U CN 201811251 U CN201811251 U CN 201811251U CN 2010205593481 U CN2010205593481 U CN 2010205593481U CN 201020559348 U CN201020559348 U CN 201020559348U CN 201811251 U CN201811251 U CN 201811251U
- Authority
- CN
- China
- Prior art keywords
- tube
- shell
- heat exchanger
- air jet
- jet pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Automatic Assembly (AREA)
Abstract
The utility model discloses an automatic soot cleaning device for a shell and tube type heat exchanger. The device can clean the soot in a heat exchange tube of the shell and tube type heat exchanger automatically, timely and effectively under the condition of not stopping a machine or disassembling equipment so as to ensure continuous and normal running of the equipment. The device is connected in series between a high-temperature flue gas outlet and a gas inlet of the shell and tube type heat exchanger; a gas ejecting tube which is close to or parallel to a port plane of a group of heat exchange tubes inside the shell and tube type heat exchanger is arranged in a tubular shell of the device; a group of gas ejecting ports which are opposite to ports of heat exchange tubes are arranged on the gas ejecting tube; a transmission mechanism is connected between the gas ejecting tube and a motor; the gas ejecting tube is connected with a compacted air source by an air inlet tube; and a controller controls the motor and a valve arranged on the air inlet tube so as to ensure that the group of gas ejecting ports on the gas ejecting tube automatically eject gas to clean the soot in the whole group of heat exchange tubes in turn. The automatic soot cleaning device can be widely used in shell and tube type heat exchangers at various waste heat utilization occasions.
Description
Technical field
The utility model relates to the crock clearance technique field of shell and tube exchanger, particularly a kind of crock automatic clearing apparatus of shell and tube exchanger.
Background technology
High-temperature flue gas by various comburants produce as burnings such as fire coal, fuel oils generally all contains a large amount of cigarette ash things.In various shell and tube exchangers, when high-temperature flue gas when the heat exchanger tube, imperfect combustion or incombustible material will be attracted to the inner surface of heat exchanger tube in these fuel, forms crock, and along with the increase of running time, can be long-pending more thick more.These residues not only influence the transmission of heat, and can cause being heated surface corrosion.Therefore, crock such as untimely removing can have a strong impact on the heat exchange effect, even cause heat exchange efficiency to descend significantly, so that the equipment cisco unity malfunction.
Crock to shell and tube exchanger is removed (mainly being the removing to boiler one class heat exchanger crock in fact); though existing both at home and abroad manually cleaning with water or method such as steam removing; also develop chemical in recent years and removed crock; but the crock clearance rate is uneven; and generally all to shut down even dismounting equipment just can carry out, be difficult to reach ideal effect.At present, most power stations of China or Industrial Boiler all can only be allowed crock harm, or strengthen heat exchange area, in the hope of keeping the operation of equipment.
But the occasion of and specialized application extensive for other, as the utilization of engine tail gas waste-heat, the shell and tube exchanger that it adopts then often can not solve the problem that crock is removed to strengthen equipment volume or methods such as shutdown, dismounting.And the key areas of the current just exploitation power-saving technology of this UTILIZATION OF VESIDUAL HEAT IN.For example be used for a kind of absorption heat energy ice making equipment that utilizes engine tail gas waste-heat of fishing boat, its volume of environmental requirement is little, in light weight; The fresh-keeping ice making of fishery harvesting requires continuous operation; And the heat source temperature that absorption refrigeration requires is more than 320 ℃, its heat exchanger must have higher heat exchange efficiency, the heat exchanger tube crock gathers slightly, and heat exchange efficiency will descend rapidly, and the superheated steam that the high-temperature flue gas heat exchange produces does not just reach the temperature that thermal refrigerating requires.Therefore, as in time do not remove the crock in the heat exchanger tube in running, equipment is impossible operate as normal.
Summary of the invention
The purpose of this utility model is to provide a kind of crock automatic clearing apparatus of shell and tube exchanger; with solve shell and tube exchanger, utilize especially for engine tail gas waste-heat the crock of heat exchanger tube in the shell and tube exchanger of system can be in time and equipment need not shut down or dismantle the problem that can effectively remove; the continuous operate as normal of assurance equipment, thus make the utilization of heat energy utilization, particularly engine tail gas waste-heat enter into the practicable stage.
The technical solution that the utility model proposed is such: a kind of crock automatic clearing apparatus of shell and tube exchanger, comprise tubular shell, described tubular shell is a reducer pipe, this tubular shell one end face closely is connected with shell and tube exchanger one end face coupling, the tubular shell other end closely is connected with fume pipe one end face coupling, it is characterized in that: be provided with in the described tubular shell near and be parallel to the air jet pipe on one group of heat exchanger tube port plane in the described shell and tube exchanger, this air jet pipe is provided with one group respectively over against the puff prot of described each heat exchanger tube port, one group of puff prot that one transmission mechanism drives on the described air jet pipe carries out jet removing to crock in the full group heat exchanger tube in the described shell and tube exchanger in order, described transmission mechanism drives by motor and power transmission shaft thereof, described air jet pipe is connected with compressed air source by air inlet pipe, and motor is controlled by controller with the action that is located at the valve on the air inlet pipe.
When one group of heat exchanger tube in the described shell and tube exchanger is the isometric circle annular and arranges, described air jet pipe is rectangular in shape, the 1st section of this air jet pipe is positioned on the axis of described shell and tube exchanger and described tubular shell, and by a pair of location axle sleeve and supporting base expansion bearing on the tubular shell inwall, the 1st section of this air jet pipe is in transmission connection by a pair of bevel gear with described power transmission shaft, the 1st section lower port of described air jet pipe and air inlet pipe inner port are by the activity of sleeve pipe do, connect and connect, the 2nd section top of described air jet pipe has a row one by one over against the puff prot of the heat exchanger tube port of isometric circle annular array, and the endcapped of this section.
When one group of heat exchanger tube in the described shell and tube exchanger is in length and breadth when the square formation formula is arranged, described air jet pipe is straight tube shape and closed at both ends, these air jet pipe central authorities connect with the inner port of described air inlet pipe and are connected, described air jet pipe top has the puff prot of the heat exchanger tube port that a row arranges over against the square formation formula one by one, a screw mandrel that is parallel to this group heat exchanger tube port plane passes through the pair of bearing expansion bearing on two walls of described tubular shell symmetry, screw one side that cooperates with this wire rod thread is fixed with described air inlet pipe inner end, air inlet pipe can adopt metal expansion pipe, be parallel to this screw mandrel and two ends and be separately fixed at guide post on the described pair of bearing and the through hole on the described screw and slide and connect, described screw mandrel one end is connected with described power transmission shaft one end.
Compared with prior art, the utlity model has following beneficial effect:
(1) the crock automatic clearing apparatus of shell and tube exchanger of the present utility model is serially connected with between high-temperature flue gas outlet and the shell and tube exchanger air inlet, scale removal mechanism wherein only is the air jet pipe and the transmission mechanism thereof of a tubulose, it is little to take up room, and does not influence the circulation of high-temperature flue gas substantially.The removing of crock is to utilize the pressure-air that adds as working medium spary heat exchanger tube inwall, and the flue dust that pressure-air separates with spary is superimposed upon in the high-temperature flue gas and is discharged, and does not influence heat transfer process.Therefore, can in the normal course of operation of shell and tube exchanger, its crock be removed, need not shut down or dismantle, guarantee the shell and tube exchanger crock that can remove automatically in the heat exchanger tube in service continuously.
(2) controller of the utility model device can send signal according to the parameter value of device heat exchange effect, starts the action of pressure-air valve and air jet pipe, automatically performs the operation of removing heat exchanger tube inwall crock.Therefore, can in time remove the nominal situation condition of its crock with continuous maintenance heat-exchange system.For keeping the normal operation continuously of heat-exchange system, generally device starts the work of removing crock when crock does not gather in a large number, and at this moment, the crock that pressure-air heat exchanging inside pipe wall tentatively gathers can carry out abundant spary, can obtain to remove preferably effect.
(3) pressure-air is only used in simple, easy to operate, the automatic detection of the utility model apparatus structure, removing automatically, and power consumption is few, and cost is low; As consider and to shut down the dismounting scale removal, guarantee the continuously normal operation of equipment that then its economic benefit is difficult to estimate especially.
Once a kind of fishing boat engine tail gas waste-heat ice making equipment was compared discovery in the situation of using the utility model device front and back, when not adding the utility model device, the engine operation is after one day, and 1/2, one all backs that the day ice-making capacity of its ice making equipment drops to nominal value are 1/4 of nominal value.And after having installed the utility model device, the day ice-making capacity of this ice making equipment remains on the nominal value always.
The utility model can be widely used in the shell and tube exchanger of various UTILIZATION OF VESIDUAL HEAT IN occasions.The occasion of these UTILIZATION OF VESIDUAL HEAT IN comprises: the tail gas that the engine that automobile, fishing boat, generator etc. are equipped with is discharged, and all combustion systems using waste heat from tail gas of discharging can also be applied to the thermal power transfer of the direct heat form of non-waste heat occasion.
Description of drawings
Fig. 1 is that the heat exchanger tube of the utility model embodiment 1 is the shell and tube exchanger crock automatic clearing apparatus structural representation that the isometric circle annular is arranged.
Fig. 2 is an A-A cutaway view shown in Figure 1.
Fig. 3 is a B-B cutaway view shown in Figure 1.
Fig. 4 is that the heat exchanger tube of the utility model embodiment 2 is the shell and tube exchanger crock automatic clearing apparatus structural representation of arranging to the square formation formula in length and breadth.
Fig. 5 is a C-C cutaway view shown in Figure 4.
Fig. 6 is a D-D cutaway view shown in Figure 4.
Wherein, description of reference numerals is as follows:
1, the cast housing; 2, air inlet pipe; 3, air jet pipe; 4, motor;
5, support; 6, power transmission shaft; 7, bevel gear; 8, bevel gear;
9, supporting base; 10, the location axle sleeve; 11, the heat exchanger connector; 12, the fume pipe connector;
13, sleeve pipe; 14, puff prot; 15, shell and tube exchanger; 16, fume pipe;
17, air compressor; 18, magnetic valve; 19, controller; 20, screw;
21, screw mandrel; 22, bearing block; 23, guide post; 24, air inlet pipe;
25, air jet pipe.
The specific embodiment
By following embodiment the utility model is further elaborated.
Embodiment 1
Referring to Fig. 1-shown in Figure 3, the crock automatic clearing apparatus of a kind of shell and tube exchanger of the present utility model by tubular shell 1, advance air jet pipe 3 and transmission mechanism, air inlet pipe 2, motor 4 and power transmission shaft 6 thereof, air compressor 17 and controller 19 are formed.Tubular shell 1 is a reducer pipe, and one end closely is connected with shell and tube exchanger 15 1 end faces coupling, forms heat exchanger connector 11, and tubular shell 1 other end closely is connected with fume pipe 16 1 end faces coupling, forms fume pipe connector 12.One group of heat exchanger tube in the shell and tube exchanger 15 that present embodiment adopted is arranged with the isometric circle annular, air jet pipe 3 is rectangular in shape, its the 1st section axis is positioned on the same axis of shell and tube exchanger 15 and tubular shell 1, and by a pair of location axle sleeve 10 and supporting base 9 expansion bearings on tubular shell 1 inwall, a pair of bevel gear 7,8 is housed between power transmission shaft 6 ends of the 1st section of air jet pipe 3 and motor 4.The lower port that air jet pipe 3 is the 1st section is connected by sleeve pipe 13 do activities, perforation with air inlet pipe 2 inner port, these sleeve pipe 13 bottom locks, and air jet pipe 3 can rotate in sleeve pipe 13 for the 1st section.Air inlet pipe 2 external port are connected by the escape pipe of magnetic valve 18 with air compressor 17.The 2nd section of air jet pipe 3 near and be parallel to one group of heat exchanger tube port plane in the shell and tube exchanger 15, the length that air jet pipe 3 is the 2nd section slightly is shorter than the internal diameter of shell and tube exchanger 15 bodys, the 2nd section top of this air jet pipe 3 has the puff prot 14 of the heat exchanger tube port that a row arranges over against the isometric circle annular one by one, the 2nd section endcapped of this air jet pipe 3.
During work, high-temperature flue gas passes tubular shell 1 from fume pipe 16 and enters shell and tube exchanger 15 interior each heat exchanger tube, after after a while, for example 5 hours, in each heat exchanger tube, can accumulate to certain crock, its heat exchange efficiency is descended, the this day ice-making capacity descends, at this moment, controller 19 sends action command, starter motor 4 and open magnetic valve 18, motor 4 is by power transmission shaft 6, bevel gear is to 7,8 drive air jet pipe 3 rotations, meanwhile, compressed air enters air jet pipe 3 through air inlet pipe 2, and take turns to spray by 14 pairs of each heat exchanger tube inwalls of each puff prot of the 2nd section of air jet pipe 3, the crock that its inwall is adhered to peels off and is blown away, and injecting time is set according to the actual requirements.
Embodiment 2
Shown in Figure 6 referring to Fig. 4 one, the crock automatic clearing apparatus difference from Example 1 of the shell and tube exchanger that this is routine is:
(1) one group of heat exchanger tube in the shell and tube exchanger 15 is to arrange to the square formation formula in length and breadth;
(2) air jet pipe 25 is straight tube shape and closed at both ends, air jet pipe 25 central authorities connect with air inlet pipe 24 inner port and are connected, the length of air jet pipe 25 is longer than the length of side of heat exchanger tube square formation slightly, has the puff prot 14 of the heat exchanger tube port that a row arranges over against square formation one by one on air jet pipe 25 tops;
(3) air jet pipe 25 is made left and right back and forth movement, thereby its driving mechanism is such: the screw mandrel 21 that is parallel to each heat exchanger tube port plane passes through pair of bearing 22 expansion bearings on two walls of cast housing 1 symmetry, be fixed with air inlet pipe 24 inner ends with screw 20 1 sides of screw mandrel 21 threaded engagement, be parallel to screw mandrel 21 and two ends and be separately fixed at guide post 23 on the pair of bearing 22 and slide with through hole on the screw 20 and connect, screw mandrel 21 1 ends are connected with power transmission shaft 6 one ends.Air inlet pipe 24 can adopt metal expansion pipe.
All the other structures and the course of work are identical with embodiment 1.
Claims (5)
1. the crock automatic clearing apparatus of a shell and tube exchanger, comprise tubular shell, this tubular shell one end face closely is connected with shell and tube exchanger one end face coupling, the tubular shell other end closely is connected with fume pipe one end face coupling, it is characterized in that: be provided with in the described tubular shell near and be parallel to the air jet pipe on one group of heat exchanger tube port plane in the described shell and tube exchanger, this air jet pipe is provided with one group respectively over against the puff prot of described each heat exchanger tube port, one group of puff prot that one transmission mechanism drives on the described air jet pipe carries out jet removing to crock in the full group heat exchanger tube in the described shell and tube exchanger in order, described transmission mechanism drives by motor and power transmission shaft thereof, described air jet pipe is connected with compressed air source by air inlet pipe, and motor is controlled by controller with the action that is located at the valve on the air inlet pipe.
2. the crock automatic clearing apparatus of shell and tube exchanger according to claim 1, it is characterized in that: when one group of heat exchanger tube in the described shell and tube exchanger is the isometric circle annular and arranges, described air jet pipe is rectangular in shape, the 1st section of this air jet pipe is positioned on the axis of described shell and tube exchanger and described tubular shell, and by a pair of location axle sleeve and supporting base expansion bearing on the tubular shell inwall, the 1st section of this air jet pipe is in transmission connection by a pair of bevel gear with described power transmission shaft, the 1st section lower port of described air jet pipe and air inlet pipe inner port are by the activity of sleeve pipe do, connect and connect, the 2nd section top of described air jet pipe has a row one by one over against the puff prot of the heat exchanger tube port of isometric circle annular array, and the 2nd section endcapped.
3. the crock automatic clearing apparatus of shell and tube exchanger according to claim 1, it is characterized in that: when one group of heat exchanger tube in the described shell and tube exchanger is in length and breadth when the square formation formula is arranged, described air jet pipe is straight tube shape and closed at both ends, these air jet pipe central authorities connect with the inner port of described air inlet pipe and are connected, described air jet pipe top has the puff prot of the heat exchanger tube port that a row arranges over against the square formation formula one by one, a screw mandrel that is parallel to this group heat exchanger tube port plane passes through the pair of bearing expansion bearing on two walls of described tubular shell symmetry, screw one side that cooperates with this wire rod thread is fixed with described air inlet pipe inner end, be parallel to this screw mandrel and two ends and be separately fixed at guide post on the described pair of bearing and the through hole on the described screw and slide and connect, described screw mandrel one end is connected with described motor transmission shaft one end.
4. the crock automatic clearing apparatus of shell and tube exchanger according to claim 1, it is characterized in that: described tubular shell is a reducer pipe.
5. the crock automatic clearing apparatus of shell and tube exchanger according to claim 1, it is characterized in that: described air inlet pipe outer end is connected with the escape pipe of air compressor by magnetic valve, and controller is controlled described motor and magnetic valve automatically according to control instruction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205593481U CN201811251U (en) | 2010-09-28 | 2010-09-28 | Automatic soot cleaning device for shell and tube type heat exchanger |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010205593481U CN201811251U (en) | 2010-09-28 | 2010-09-28 | Automatic soot cleaning device for shell and tube type heat exchanger |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201811251U true CN201811251U (en) | 2011-04-27 |
Family
ID=43894191
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010205593481U Expired - Fee Related CN201811251U (en) | 2010-09-28 | 2010-09-28 | Automatic soot cleaning device for shell and tube type heat exchanger |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201811251U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101949545A (en) * | 2010-09-28 | 2011-01-19 | 佛山市汇控热能制冷科技有限公司 | Automatic fouling removing device for shell-and-tube heat exchanger |
CN105241298A (en) * | 2014-07-11 | 2016-01-13 | 优力沃思(北京)科技股份有限公司 | Air pre-heater washing system |
CN105396308A (en) * | 2015-12-17 | 2016-03-16 | 南京亚格泰新能源材料有限公司 | Evaporator based on air-flow cleaning |
CN107560494A (en) * | 2017-08-31 | 2018-01-09 | 安徽省格致绿色建筑设计有限公司 | A kind of On Line Foul Removing Technology device |
CN109163583A (en) * | 2018-09-11 | 2019-01-08 | 山东理工大学 | A kind of heat exchanger with fork type flushing device |
-
2010
- 2010-09-28 CN CN2010205593481U patent/CN201811251U/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101949545A (en) * | 2010-09-28 | 2011-01-19 | 佛山市汇控热能制冷科技有限公司 | Automatic fouling removing device for shell-and-tube heat exchanger |
CN105241298A (en) * | 2014-07-11 | 2016-01-13 | 优力沃思(北京)科技股份有限公司 | Air pre-heater washing system |
CN105241298B (en) * | 2014-07-11 | 2019-03-19 | 优力沃思(北京)科技股份有限公司 | Air preheater rinse-system |
CN105396308A (en) * | 2015-12-17 | 2016-03-16 | 南京亚格泰新能源材料有限公司 | Evaporator based on air-flow cleaning |
CN107560494A (en) * | 2017-08-31 | 2018-01-09 | 安徽省格致绿色建筑设计有限公司 | A kind of On Line Foul Removing Technology device |
CN109163583A (en) * | 2018-09-11 | 2019-01-08 | 山东理工大学 | A kind of heat exchanger with fork type flushing device |
CN109163583B (en) * | 2018-09-11 | 2020-03-24 | 山东理工大学 | Heat exchanger with shifting fork type scouring device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201811251U (en) | Automatic soot cleaning device for shell and tube type heat exchanger | |
CN101846325B (en) | Soot blower | |
CN102519051B (en) | Flue gas spraying, purifying and heat recovering system for coal burning boiler | |
CN101949545A (en) | Automatic fouling removing device for shell-and-tube heat exchanger | |
CN210486063U (en) | Modularized boiler | |
CN211041021U (en) | High-efficient flue gas waste heat recovery device | |
CN202511309U (en) | Smoke spraying purification and heat recovery system for coal-fired boiler | |
CN202220676U (en) | Waste heat recovery circulation system for drilling platform | |
CN102937055B (en) | For the heat recovery circulatory system of drill platform | |
CN201795514U (en) | Soot blowing device and boiler with same | |
CN205261510U (en) | Waste heat boiler | |
CN116202340A (en) | Spiral double-preheating heat exchanger suitable for pure oxygen combustion system | |
CN208205865U (en) | A kind of novel high-temperature flue gas waste-heat recovery device | |
CN203364124U (en) | Pulverized coal boiler modified from chain-grate boiler | |
CN203309917U (en) | Coal fired boiler vertical shaft flue provided with sound wave soot blowers | |
CN202074504U (en) | Boiler economizer | |
CN212691812U (en) | High-efficient deashing structure of boiler heat transfer face | |
CN210638006U (en) | Waste heat utilization equipment for thermal power plant | |
CN201412857Y (en) | Cold ash hopper-type ash remover of water-coal-slurry boiler | |
CN112432196A (en) | Waste heat recovery utilizes system of thermal power plant's boiler exhaust fume | |
CN202470027U (en) | Low-temperature flue gas heat recovery and utilization system | |
CN221991816U (en) | A heat exchanger fin tube sonic soot blowing device | |
CN222437943U (en) | Novel boiler deslagging machine | |
CN219494920U (en) | Efficient waste heat recovery device | |
CN105386960A (en) | Intelligent air compressor waste heat recovery unit with scale removal device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110427 Termination date: 20180928 |
|
CF01 | Termination of patent right due to non-payment of annual fee |